Sec. 54-255. - Application requirements.
a. Generally. All sets of drawings and plans submitted as part of the PUD Master Plan shall be prepared in accordance with the following criteria.
1. Scale: All drawings should use a consistent scale.
2. Title page and locator map: Indicating the name of the development, the owner(s), the developer, the person or firm preparing the plan, the date of the plans and the location of the project area in relation to major streets, waterways or other geographical features.
3. Title block: Indicating the name of the development, the owner(s), the developer, the person or firm preparing the plan and the date of the drawing.
4. Professional certification: Each plan or drawing for the Master Plan submittal shall be prepared by a licensed architect, landscape architect, surveyor, or engineer.
5. Each drawing set shall be bound into one package.
b. PUD Pre-Application Plan Review. Prior to filing an application for a PUD, the applicant must submit twelve (12) sets of a PUD Pre-Application Plan to the Zoning Division in the Department of Planning and Preservation and meet with the Planning Director and representatives from other City departments regarding the proposed PUD development. The PUD Pre-Application Plan is not required to be prepared by an engineer. The PUD Pre-Application Plan shall, at a minimum, include the following information:
1. A conceptual land use plan for the entire PUD delineating the approximate location and area of buildable and nonbuildable land, proposed uses and acreages and related planning and development data including information on vegetation, to include forest cover and significant stands of trees, proposed buffers, cultural resources, and adjacent land uses.
2. A general plan for public facilities which includes an assessment of existing traffic patterns, storm drainage and the availability of sewer and water, and general topographic information from city topographic maps or other suitable maps.
c. Master Plan. The application for a Planned Unit Development shall require the submission of twelve (12) sets of a PUD Master Plan containing, at a minimum, the following information:
1. Plat prepared by a registered surveyor showing the exact location, size, shape, gross acreage, and ownership of the tract(s) to be developed as a PUD, all known easements located thereon, and the approximate location of all freshwater and saltwater wetlands and other critical areas as determined by a professional wetlands consultant.
2. Site analysis prepared by registered engineer or surveyor showing the following:
(a) Location of existing manmade features including, but not limited to, major utility lines or facilities, drainage canals, manmade water bodies and existing structures.
(b) General topographic information from city topographic maps or other suitable maps.
(c) Location and description of cultural resources identified in cultural resource inventories available through local and state government agencies.
3. An aerial photograph of the entire PUD with property lines indicated.
4. Land use plan showing the location, approximate net acreage and gross acreage of each type of residential, mixed-use, office, commercial, and industrial development pod, open space area, recreational area and water body in the PUD, and existing land uses adjacent to the PUD, except that for a PUD containing more than one thousand (1,000) acres, requirements for locating proposed open space areas and recreational areas may be generally defined in lieu of identifying locations on a land use plan to ensure that required useable open space areas are distributed throughout the PUD. The plan shall also show the approximate location of major vehicular, pedestrian and bicycle circulation systems within the PUD and include typical cross sections of major circulation systems indicating right-of-way width and design. The plan shall show proposed major transmission lines for utilities, proposed major stormwater drainage facilities, and proposed buffers. Within each residential development pod the maximum number of residential dwelling units and net density shall be specified.
Decisions regarding major land uses should be made on consultation with local government agencies and in consideration of the many impact factors listed below:
Traffic.
Schools.
Storm water drainage.
Fresh-water supply.
Sewerage.
Solid-waste management.
Other municipal services (e.g., health, safety).
Open space, natural and cultural resource preservation.
5. For each development pod identified on the Land Use Plan, the following PUD Zoning Regulations, prepared in accordance with Section 54-257 PUD Zoning Regulations shall be provided.
(a) For conservation and residential pods the regulations shall include, but not be limited to, the following:
(1) The type of dwelling units allowed, i.e. single-family detached, single-family attached, duplex, two-family, townhouse, or multi-family.
(2) Minimum lot size per dwelling unit and minimum lot frontage requirements.
(3) Minimum setback requirements for principal buildings and, where applicable, for accessory buildings.
(4) Maximum lot occupancy restrictions for buildings.
(5) Minimum and/or maximum building heights (in feet and stories) allowed for principal buildings and, where applicable, for accessory buildings.
(6) Regulations for neighborhood uses permitted in accordance with Section 54-257 PUD Zoning Regulations.
(7) Parking requirements.
(b) For mixed-use, commercial, office, civic and industrial pods the regulations shall include, but not be limited to the following:
(1) Minimum building setbacks.
(2) Building heights in feet and stories; minimum and maximum.
(3) Maximum lot occupancy for buildings.
(4) Regulations for residential uses as specified in the above section.
(5) Permitted uses and restrictions on hours of operation, if any are proposed.
(6) Parking requirements.
6. For each area designated for open space and recreational use, a list and description of the proposed improvements and facilities shall be provided with an explanation of the ownership and maintenance of the areas and facilities.
7. Proposed general plan for landscape buffers.
8. Additional information requested during PUD Pre-Application Plan review or which will be helpful in reviewing the PUD.
9. Traffic Impact Study. The type and scope of the study shall be determined by the Department of Traffic and Transportation and the Department of Planning, Preservation and Sustainability during the PUD Pre-Application Plan review based on the potential impacts the development is anticipated to have on the existing transportation infrastructure over and above the impact entitled development would have. Technical Review Committee requirements for traffic impact studies for Site Plans and Subdivision Concept Plans shall still apply.
10. A drainage basin analysis shall be required with the PUD Master Plan application. The scope of the analysis shall be determined by the Engineering Division during the PUD Pre-Application Plan review.
d. Subdivision Concept Plans, Preliminary Plats, Road Construction Plans, Final Plats and Site Plans shall be prepared in accordance with Article 6 and Article 8.
(Ord. No. 2013-125, § 1, 11-6-13; Ord. No. 2025-086, § 1, 6-17-25)