Same; interconnection facilities; grant or lease, when.
K.S.A. 66-1243
in effect66-1243. Same; interconnection facilities; grant or lease, when.
Any entity which, on or after January 1, 2004, constructs in this state new or expanded electric generation facilities having a capacity of at least 100 kilowatts may either grant or lease interconnection facilities to transmission operators, upon agreement between the entity and operator and approval by the commission.
L. 2004, ch. 120, § 4; July 1.
Source: Kansas Office of Revisor of Statutes (ksrevisor.gov)URL: https://www.ksrevisor.gov/statutes/chapters/ch66/066_012_0043.htmlFetched: 10/20/2026