19.32.130 - Final map - Improvement agreement requirements.

At the time the final map is presented for approval to the city engineer, if the improvements required in connection with the subdivision have not been completed, plans for the improvements which the subdivider is required to construct in connection with the subdivision shall be presented to the city engineer for approval unless plans therefore have been previously approved. Before approval and recording of the said final map, the subdivider of the subdivision shall enter into an agreement with the city agreeing to complete the said improvements within 18 months from the date of execution of the agreement in consideration of the acceptance by the city of the dedications offered on the final map. Said agreement shall be secured by a good and sufficient security, in forms approved by the city attorney, in the following minimum amounts: A. Faithful performance: 100 percent (100%) of the total estimated of the cost of the public improvements conditioned upon the faithful performance of the act to be performed or agreement; B. Labor and materials: An additional 100 percent (100%) of the total estimated cost of the public improvements securing payment to the contractor, to the subcontractors, and to persons furnishing labor, materials, or equipment for the improvement or the performance of the required act; and C. Warranty: An additional 20-five percent (25%) of the total estimated of the cost of the public improvements for a period of one year following the completion and acceptance thereof against any defective work or labor done or defective materials furnished, in the performance of the improvement agreement or the performance of the act. Such security shall be one of the following and in a form approved by the city Attorney: 1. Bond or bonds by one or more corporate sureties duly authorized by the California Insurance Commissioner to transact the business of insurance; 2. A certificate of deposit in favor of the city; or 3. An irrevocable standby letter of credit. The subdivider of the subdivision shall also agree in said improvement agreement to furnish to the city a policy or policies of liability insurance to be paid for by said subdivider, which policy or policies of insurance shall meet the requirements of insuring the city, its officers and employees which are established by resolution of the city council.

(Prior code § 9252; Ords. 21616, 26386, 28676.)