§ 1008 — Testing of gas pipelines and correction of defects

Tulsa Revised Ordinances (Supp. No. 3, Update 2: codified through Ordinance No. 25794, passed May 13, 2026) · Tulsa Revised Ordinances tit. 42-A, § 1008

Corpus is an independent public-information project, not the official City of Tulsa website. Stable reference: corpuslaw.us/code/918ad896-c09e-4049-a953-69450ea7de61

Section 1008. - Testing of gas pipelines and correction of defects.

Each owner or operator of a gas pipeline other than a high-pressure line for which a permit is required under this title shall have it tested at least once every six (6) months for the purpose of determining whether it is in safe condition and free from leaks, breaks, or open spaces, and make a report of the test supported by an affidavit by the person making the test to the Public Works Director. The test may be by the stench method, electrical detection method, or any other method approved by the Inspector; provided that each gas pipeline at the time of its installation shall be tested by the Inspector, and a report of the test shall be filed with the Public Works Director before the operation of that line. Testing periods shall end on September 15 and March 15 of each year. No person shall continue the operation of any pipeline after the termination of any testing period provided herein without having it tested and making the required report. For failure to make the test and report, or if the report discloses or it otherwise appears that any line is leaking, defective, or unsafe, the Inspector shall, within five (5) days of such disclosure, or within five (5) days after the closing of any testing period, close and shut the pipeline.

(Ord. No. 22189, § 1, 1-14-2010)