Interconnection.
R.I. Gen. Laws § 39-33-3
in effect39-33-3. Interconnection.
(a) No later than September 1, 2024, the commission shall commence a process, which includes
stakeholder engagement, to adopt a framework for an interconnection tariff for energy
storage systems connected to the electric distribution system that recognizes the
flexible operating characteristics of energy storage systems.
(b) Following the public utilities commission’s adoption of a framework, which shall be
completed no later than May 1, 2025, each electric distribution company as defined
in § 39-1-2 that has greater than one hundred thousand (100,000) customers shall file a proposed
energy storage system interconnection tariff for review and approval in a contested
proceeding.
P.L. 2024, ch. 404, § 2, effective June 26, 2024; P.L. 2024, ch. 405, § 2, effective
June 26, 2024.