§ 158-62 — Preconstruction/pre-demolition inspections and ongoing inspections required
Atlanta City Code (Code of Ordinances, Part II) (Supp. No. 108, Update 1: codified through Ordinance No. 2026-37 (26-O-1511), enacted September 30, 2026) · Atlanta City Code § 158-62
Corpus is an independent public-information project, not the official City of Atlanta website. Stable reference: corpuslaw.us/code/95b5daae-607b-4bfa-806e-e6c2f06bf622
Sec. 158-62. - Preconstruction/pre-demolition inspections and ongoing inspections required.
(a) Pre-construction inspection required. Upon approval of any permit for grading, demolition, or construction, no land-disturbing activities other than installation of erosion control and tree protection measures may occur without approval by the city arborist. Tree fencing and other protection measures must be in place at the time of the pre-demolition or pre-construction inspection. Once tree fencing is in place the applicant must notify the city to schedule the inspection. Failure to do so may result in fines section 158-86. (b) Compliance with conditions of permit. The city arborist shall inspect the site to ensure the accuracy of the permit application data, site plan, and placement and efficacy of tree protection fences and other tree protection devices required by the site plan. (c) Exception. For any permit for an addition to a one-family or two-family residence, the city arborist may elect to rely on data submitted in the application and certified by the applicant for the building permit in lieu of an on-site pre-construction inspection.
(Ord. No. 2025-19(24-O-1691), § 1, 6-24-25)
Ask a question about Atlanta law
Corpus searches the Atlanta sections it holds and shows the ones that match, with their citations. Free, no sign-in.