Determination of public safety-related setbacks
35-A M.R.S. §3455
in effect3455. Determination of public safety-related setbacks
In making findings pursuant to Title 12, section 685‑B, subsection 4 or Title 38, section 484, subsection 3 on whether a wind energy development must be constructed with setbacks adequate to protect public safety, the primary siting authority must consider the recommendation of a professional, licensed civil engineer as well as any applicable setback recommended by a manufacturer of the generating facilities. The primary siting authority may require submission of this information as part of the application.
PL 2007, c. 661, Pt. A, §7 (NEW).
Source: Maine Legislature, Office of the Revisor of Statutes (legislature.maine.gov)URL: https://legislature.maine.gov/statutes/35-A/title35-Asec3455.htmlFetched: 10/20/2026