Applications for permits; erosion and sediment control plans and data; time for issuance or denial.
O.C.G.A. § 12-7-9
in effect12-7-9. Applications for permits; erosion and sediment control plans and data; time for issuance or denial.
(a) Completed applications for permits shall be submitted in accordance with this chapter and the rules and regulations, ordinances, and resolutions adopted pursuant to this chapter. The local issuing authority shall specify in clear and unambiguous language the criteria for approval of permits pursuant to this chapter. Such applications shall be accompanied by the applicant's erosion and sediment control plans and by such supportive data as will affirmatively demonstrate that the land-disturbing activity proposed will be carried out in such a manner that the minimum requirements set forth in Code Section 12-7-6 shall be met. All applications shall contain a certification stating that the plan preparer or his or her designee visited the site prior to creation of the plan or that such a visit was not required in accordance with rules and regulations established by the board.
(b) No permit shall be issued to any applicant unless the local issuing authority affirmatively determines that the plan embracing such activities meets the requirements of Code Section 12-7-6. All applicable fees shall be paid prior to issuance of the land disturbance permit by the local issuing authority.
(c) Permits shall be issued or denied as soon as practicable after the application for such permit has been filed with the local issuing authority, but in any event not later than 45 days after such filing. During the first five days after filing of the application, the local issuing authority shall determine whether the application is complete and whether external review will be required pursuant to subsection (e) of this Code section, in which event the local issuing authority shall notify the external reviewer of the filing of the application. If after such five-day period the local issuing authority fails to provide notice to the applicant that the application is incomplete, the application shall be deemed complete. In the event that a permit has been denied or deemed not accepted and the applicant thereafter resubmits the application in modified form to address deficiencies identified in the stated reasons for denial or nonacceptance pursuant to subsection (a) of Code Section 12-7-11, then the local issuing authority shall cause the permit to be issued or denied as soon as practicable after such resubmission, but in any event not later than:
(1) Twenty days after the first resubmission by the applicant; or
(2) Fourteen days after any subsequent resubmission by the applicant; provided, however, that, for any review by the local issuing authority following a resubmission by the applicant, the local issuing authority may not issue any comments on aspects of the application that are not related to its initial comments on such application or any changes made in a resubmission of the application. The provisions of this subsection shall not apply to any development of regional impact, as determined by the Department of Community Affairs pursuant to Article 1 of Chapter 8 of Title 50.
(d) If a local issuing authority requires compliance with additional regulatory items by the applicant beyond erosion and sediment control, including, but not limited to, storm-water management or utility approvals that are subject to the approval of such local issuing authority, all such requirements shall be subject to the review time frames imposed in subsection (c) of this Code section.
(e) If a local issuing authority is required to utilize a state agency, local government other than the local issuing authority, or utility provider to conduct a portion of its plan or permit review pursuant to this chapter, the local issuing authority shall provide to the applicant a list of such items that require external review. The review time frames imposed in subsection (c) of this Code section shall be tolled while such reviews are being conducted by a state agency.
(f) Notwithstanding any other provisions of this chapter to the contrary, in any county in which an airport is owned or operated either by such county or a local authority and such airport is adjacent to 9,000 acres or more of property currently or formerly owned by a municipality that has no incorporated territory within such county and any county adjacent to such county, the review time frames imposed in subsection (c) of this Code section shall not apply unless a local Act is adopted making such time frames applicable to such county; provided, however, that the effectiveness of such local Act shall be contingent upon such Act being approved by a majority of the voters of such county voting in a referendum thereon.
Ga. L. 1975, p. 994, § 8; Ga. L. 1989, p. 1295, § 6; Ga. L. 2003, p. 224, § 5. (Amended by Ga. L. 2026, Act 513 (SB 447), eff. July 1, 2026.)