Drawings and specifications.
R.I. Gen. Laws § 23-27.3-114.3.1
in effect23-27.3-114.3.1. Drawings and specifications.
Within three (3) months after the adoption of any amendment to this code, the owner
or the owner’s agent shall notify the building official that the drawings and specifications
for a project are based upon the provisions of the code in effect prior to the latest
amendment. The building official may require submission of the drawings and specifications,
although incomplete. The owner shall then be allowed to obtain a permit when the drawings
and specifications are completed, based upon the prior code provisions.
P.L. 1985, ch. 162, § 3.
Source: State of Rhode Island General Assembly (rilegislature.gov)URL: https://webserver.rilegislature.gov/Statutes/TITLE23/23-27.3/23-2/23-27.3-114.3.1.htmFetched: 10/20/2026