Montgomery City Code § 26-1 Plan for temporary traffic operations during construction in public right-of-way.
Sec. 26-1. - Plan for temporary traffic operations during construction in public right-of-way.
(a) Purpose of plan.
(1) The purpose of this plan is to outline proper traffic control methods and regulation for all public and private organizations to follow when temporary disruption of street traffic is required for street repairs or work on utility lines under a street.
(2) While the main use of streets is to carry vehicular traffic, pedestrians cross the streets and utility lines run underneath them. As the necessity arises for work on utility lines and street repairs, a conflict occurs between the movement of vehicles and the construction work on the street involved. To reduce this conflict to a minimum, certain controls are necessary.
(3) It is necessary to control the type of excavation, as to the size of the hole and the location of equipment, and the location of the spoil material obtained through excavation.
(4) Street space is at a minimum and no more space should be used for construction work than is absolutely necessary. Through barricading and channelization, the remaining street space is used to guide traffic around construction work in the best way possible.
(b) Purpose of barricading and channelization.
(1) The purpose of barricading and channelization is to:
a. Provide for the orderly flow of traffic;
b. Reduce hazards for motorists, pedestrians and workers;
c. Reduce overall job costs to the public; and
d. Improve public relations.
(2) By using advanced warning signs and traffic cones in addition to barricades, the best type of orderly flow under existing conditions can be maintained. Orderly traffic flow makes it safer for the workman, the pedestrian and the motorist.
(3) Good barricading may increase the construction cost slightly, but the overall result will be less delay and less cost to the motorists, as well as less delay and less cost to the contractor.
(4) Adequate signs to explain why work in the street is being performed and good barricading are great assets to the public. If the public understands why it is being delayed, there is likely to be less objection to being delayed.
(5) It should be noted that construction or repairs in streets create hazardous conditions which can result in traffic accidents if proper precautions are not taken. Public and private agencies can be liable for such accidents through gross negligence. Good signs, barricading and channelization around hazardous worksites in the streets are deterrents to such accidents.
(6) While it is important to provide adequate barricading on residential and minor streets, the most important location for proper channelization is on arterial streets and particularly at signalized intersections. Arterial streets serve the general public, particularly in the morning and evening during the peak-hour flow of traffic.
(7) The peak-hour in the city is from 7:00 to 9:00 a.m. and 4:00 to 6:00 p.m. During these times construction work will not be allowed on arterial streets, except during emergency conditions or with the approval of the traffic engineering and street maintenance departments.
(c) Procedure for obtaining permission to work in city streets. In order for the contractor to close a street partially or completely for construction work, it is necessary to obtain the approval of the traffic engineering department and the street maintenance department. For larger jobs this is done generally by a conference between the departments and the contractor prior to the work being started. It may be necessary during the progression of the work to hold several additional conferences. In addition to these conferences, the contractor must call in the street closure to the traffic engineering department 24 hours in advance for the closing of minor and residential streets, and 48 hours in advance for closure involving signalized intersections and arterial streets.
(d) Flagman or police officer.
(1) If traffic congestion warrants it or if the inspector on the job determines it to be necessary, a contractor will provide flagmen as required for adequate traffic control. Flagmen are mandatory at intersections where equipment is intermittently blocking a traffic lane or where only one lane is available for two directions of traffic. One flagman is required for each direction of traffic affected.
(2) The availability of free police manpower for assistance in construction traffic work is generally limited to emergencies only, as their services are required elsewhere. Off-duty police officers may be employed directly by the contractor, however, to maintain traffic control. For information, call the police department.
(3) The traffic engineering department, the police department and the fire department may determine if an emergency exists which will require on-duty police officers to maintain traffic control at a project site.
(e) Complete street closure.
(1) The closing of an entire street obstructs traffic to the maximum and, of course, requires detours. If it is found necessary to close any street, the traffic engineer must be consulted for the layout of detour routes and other important information. It is required that every intersection along the detour be marked until the diverted traffic returns to the original street. Work of this type usually extends over a period of several days or even weeks. Every sign or barricade must be illuminated at night with blinkers, lanterns or flare pots.
(2) If an emergency condition exists, such as a major fire or a water line break, the city engineer's office, the police department, the fire department or the traffic engineering department may close an arterial street. If such a closure occurs during the day when traffic congestion would result, the city traffic engineer should be notified as soon as possible.
(3) Rather than close an entire street for construction, it is required to close the street a portion at a time for backfilling as the work progresses. Temporary crossovers by plating or bridging also can be used and often can prevent complete closure of a street. When using temporary crossovers, it is essential that the steel plates be set in solidly and the edges tamped with plant mix. The use of dirt in tamping these plates is not acceptable.
(4) It is essential to have a large number of signs to inform the public of complete street closures and the detour routes.
(5) When one lane of a two-lane roadway has been closed for repairs and two-way traffic cannot be maintained by channelization, the traffic engineering department may require a full-time flagman for safety.
(Ord. No. 54-72, § 4-13; Ord. No. 100-74, § 1; Code 1980, § 25-41(d))