West Jordan City Code § 11-2-1 LAND DISTURBANCE PERMIT REQUIRED
11-2-1: LAND DISTURBANCE PERMIT REQUIRED:
A. Except as otherwise provided herein, no person
Includes individuals, bodies politic and corporate, companies, partnerships, associations, and other informal entities.
, developer, builder or contractor shall cause to be commenced or performed any land disturbance
LAND DISTURBANCE: Any disturbance of native soils, plants or environment, including, but not limited to, clearing, grubbing, grading, excavation, filling, dredging, construction of earth filled dams, and any other types of earthwork.
, grading
GRADING: The act or result of digging, excavating, transporting, spreading, depositing, filling, compacting, settling or shaping of land surfaces and slopes, and other operations or activities involving the physical movement of rock or soil.
, relocation of earth, or any other land disturbance activity, and no person
Includes individuals, bodies politic and corporate, companies, partnerships, associations, and other informal entities.
shall import or export any earth materials to or from any site
SITE: A parcel or parcels of real property owned by one or more persons on which activity regulated by this title is occurring or is proposed to occur.
, without first obtaining a land disturbance permit
LAND DISTURBANCE PERMIT: The land disturbance permit required by the City in accordance with provisions of this title.
. Except as set forth in subsection B of this section, no land disturbance permit shall be issued for any site or project
PROJECT: A defined site that has obtained final subdivision plat or site plan approval from the City.
requiring site plan approval until and unless a final site plan has been approved by the City
CITY: City of West Jordan, Utah.
for the site or project, and no land disturbance permit will be issued for any site or project requiring subdivision approval until and unless the final subdivision plat has been approved by the City for the site or project.
B. Notwithstanding the provisions of subsection A of this section, a land disturbance permit
LAND DISTURBANCE PERMIT: The land disturbance permit required by the City in accordance with provisions of this title.
may be issued by the City
CITY: City of West Jordan, Utah.
prior to receiving final site
SITE: A parcel or parcels of real property owned by one or more persons on which activity regulated by this title is occurring or is proposed to occur.
plan approval or final subdivision plat approval; provided, that an application for final site plan approval or final subdivision plat approval has been made and engineering grading
GRADING: The act or result of digging, excavating, transporting, spreading, depositing, filling, compacting, settling or shaping of land surfaces and slopes, and other operations or activities involving the physical movement of rock or soil.
plans have been reviewed and accepted by the City Engineer
CITY ENGINEER: The City Engineer of City of West Jordan, or the person engaged by the City and authorized to perform the duties assigned to the City Engineer, and shall include any deputies and representatives.
or designated representative. To issue the land disturbance permit without final site plan approval or final subdivision plat approval all the following conditions must be met:
1. The proposed project
PROJECT: A defined site that has obtained final subdivision plat or site plan approval from the City.
is located in an economic development area as adopted by the redevelopment agency of the City
CITY: City of West Jordan, Utah.
of West Jordan, in accordance with Utah Code
UTAH CODE, UCA: The Utah Code Annotated, as amended.
Annotated title 17C - Limited Purpose Local Government Entities - Community Reinvestment Agency Act, or its successor provision(s);
2. The project
PROJECT: A defined site that has obtained final subdivision plat or site plan approval from the City.
is for an industrial or commercial development considered of high economic value to the City
CITY: City of West Jordan, Utah.
as determined by the Mayor
MAYOR: This is the duly elected or appointed mayor of the city pursuant to the council-mayor form of municipal government.
with concurrence from the City Engineer
CITY ENGINEER: The City Engineer of City of West Jordan, or the person engaged by the City and authorized to perform the duties assigned to the City Engineer, and shall include any deputies and representatives.
;
3. The project
PROJECT: A defined site that has obtained final subdivision plat or site plan approval from the City.
is a minimum of fifty (50) acres as presented in the pending application for site
SITE: A parcel or parcels of real property owned by one or more persons on which activity regulated by this title is occurring or is proposed to occur.
plan or subdivision approval; and
4. The applicant
APPLICANT: Any person who submits an application for a permit pursuant to this title.
complies with all remaining provisions in this title, which still apply to the application and issuance of the land disturbance permit
LAND DISTURBANCE PERMIT: The land disturbance permit required by the City in accordance with provisions of this title.
. (2001 Code § 81-2-010; amd. Ord. 10-27, 9-8-2010; Ord. 16-29, 7-27-2016; Ord. 19-12, 2-27-2019; Ord. 21-11, 3-24-2021)