Sec. 47-652. - Bond.
(a) Except as provided in subsection (d), if the SWQMP includes structural controls, the applicant shall provide a performance bond that satisfies the following requirements:
(1) The bond shall name the owner or operator of the parcel subject to the SWQ permit as principal and a corporate bonding company licensed to conduct business in the state as surety to secure the city that the proposed structural controls to be covered by the bond will be constructed and installed in accordance with the SWQ permit, the SWQMP, and any plans and specifications contained therein, and securing the city against loss, damage, claim, or liability in connection therewith.
(2) The bond shall be in a sum that includes at a minimum the total estimated costs of the controls to be constructed.
(3) The bond shall be in favor of and for the use and benefit of the city.
(4) The bond shall describe, by reference to the number of the application together with such other brief descriptive matter as is necessary, the work proposed to be done or to be covered by the SWQ permit in connection with which the bond is given.
(5) The bond required by this section shall be conditioned that the work therein referred to will be performed in strict and full accordance with the terms and provisions of the SWQ permit, the SWQMP, and the plans and specifications therein; and that if any of the work is not performed in accordance therewith, or if any materials not in accordance therewith are used in the process of such work, such failure and default shall be promptly remedied and any defective material or work removed and replaced with material and by workmanship in accordance with the terms of the SWQ permit, the SWQMP, and plans and specifications therein without cost or expense to the city up to the sum of the bond. The bond must guarantee materials and workmanship for a period of one year after the city's initial inspection that confirms proper installation of the controls.
(6) The bond shall provide that the surety company will notify the city in writing 30 days prior to a cancellation, nonrenewal, or material change in the policy. In the case of nonrenewal or cancellation, the SWQ permittee shall then have 21 days after the surety company's notice to the city to replace the coverage or the SWQ permittee's SWQ permit shall be revoked after notice and the opportunity for a hearing without further action on the part of the city.
(7) The bond shall be in a form approved by the city attorney and must be accompanied by a power of attorney or other convincing evidence of the issuing agent's authority to act for the surety company and must meet the requirements of Article 7.19-1(b) of the Insurance Code.
(8) The bond shall be furnished to the city prior to the issuance of a construction permit for any construction on the parcel.
(b) The applicant must present to the city its estimate of the costs to construct the structural controls included in the SWQMP, and the city will assess the reasonableness of the estimate. If the city determines that the estimate is insufficient and the applicant does not provide a substitute bond in an amount deemed sufficient by the city, the city shall deny the SWQ permit that is supported by the bond.
(c) The bond shall be released one year after the date of the city's inspection that confirms that the structural controls covered by the bond have been properly installed and are performing as intended.
(d) A bond shall not be required if all structural controls will be completed and the certifications required by section 47-672(a) will be filed before any additional construction, including the construction of streets and utilities, commences.
(e) If the project is on public property, the owner or operator shall also provide a payment bond to the city to secure the payment of mechanics, materialmen and suppliers liens.
(Ord. No. 01-800, § 3, 8-29-01; Ord. No. 06-892, § 15, 8-23-06)