Renewable energy standards.
Round Rock Zoning and Development Code, art. VIII, § 2-95
in effectSec. 2-95. - Renewable energy standards.
(a) Purpose. The purpose of this section is to facilitate the installation and construction of solar energy systems in the City of Round Rock, subject to reasonable restrictions, which will mitigate possible nuisances and preserve the public health, safety, and general welfare.
(b) Applicability. The requirements set forth in this section shall govern the siting of solar energy systems used to generate electricity or perform work which may be connected to the electric distribution grid, serve as an independent source of energy, or serve in a hybrid system. The requirements are not intended to apply to landscape lighting, security lighting, and other self-contained lighting fixtures that are not connected to other electrical components.
(c) Zoning. Solar energy systems may be permitted as an accessory structure in all zoning districts.
(d) Removal of defective or abandoned solar energy systems. Any solar energy systems found to be unsafe by the building official shall be repaired by the landowner to meet federal, state and local safety standards or removed within 10 days following written notice. If any solar energy system is not operational for a period of 12 consecutive months or more, the city shall give written notice to the landowner to take corrective action within 45 days after receipt of notice. In such a response, the landowner shall set forth reasons for the operational difficulty and provide a reasonable timetable for corrective action. If the city deems the timetable for corrective action to be unreasonable, the city must notify the landowner and the landowner shall remove the structure at the landowner's own expense within 30 days of receipt of notice from the city. The city shall have the authority to pursue legal action if necessary.
(e) Application requirements.
(1) Building permit applications for solar energy systems shall be accompanied by:
a. Standard drawings, and a site plan showing the location of the proposed system and the locations of all existing buildings, structures and property lines to scale along with distances;
b. A line drawing of the electrical components in sufficient detail to allow for a determination that the manner of installation conforms to the adopted electrical code; and
c. The specifications and performance standards of the system, as provided by the manufacturer.
(2) An engineering analysis of any structure over 20 feet in total height showing compliance with the International Building Code and certified by a licensed professional engineer shall also be submitted.
(3) When a solar energy system will be connected to the electric distribution grid, an interconnect agreement with the electrical utility provider must be in place prior to the issuance of a building permit.
(f) Additional requirements for solar energy systems.
(1) Height.
a. Roof-mounted systems:
i. Must conform to the slope of the roof and the top edge must be parallel to the roofline;
ii. Shall not project above the ridge of a gabled or gambrel roof;
iii. Shall not project more than five feet above the deck or parapet of a flat roof;
iv. Must screen all mounting hardware from public view; screening shall utilize the same or similar materials as the principal structure.
b. Ground-mounted systems shall not be higher than eight (8) feet. If located in a fenced yard or patio, height of the system shall not exceed the height of the fence.
c. Appurtenant components must be located within an enclosed structure or screened by the planting of one large shrub every four (4) linear feet around the boundary of the equipment.
Source: City of Round Rock, Texas, Code of Ordinances (Municode Library, library.municode.com)URL: https://library.municode.com/tx/round_rock/codes/code_of_ordinances?nodeId=PTIIIZODECO_CH2ZODIUSRE_ARTVIIIUSRE_S2-95REENSTFetched: 11/16/2026