Sec. 25-24. - Credits.
(a)
Any person who initiates any development may apply for a credit against the impact fees imposed by this article for any contribution, payment, construction, or dedication of land accepted and received by the city for public facilities, not otherwise required in order to obtain development approval, consistent with the capital improvements program, including all public facilities capital costs.
(b)
Development agreements entered into prior to the adoption of this article which contained public facility improvements may be entitled to a credit under the provisions of this section if the improvement is a public facility and is consistent with the capital improvements program.
(c)
A developer may apply for a credit against the impact fees imposed by this article upon development of a vacant parcel, whereby the new building(s) or structure(s) does not produce a higher trip generation rate than a previously existing building or structure on the subject parcel. It is the responsibility of the developer to provide evidence to the director as to the highest intensity building or structure previously constructed upon the parcel by which to calculate the reduction in the total amount of impact fees otherwise required for the subject parcel. In the event that this evidence cannot be ascertained, the city shall use the trip generation rate of the last known building or structure on the parcel to determine whether payment of additional impact fees apply. In the event the parcel to be developed has been, or may be, annexed into the city, this credit shall be based upon recognition of the trip generation of the highest intensity building or structure in existence prior to the annexation, at the time of annexation, or post-annexation.
(d)
Except as limited above, if an applicant is entitled to a credit, such credit shall be equal to the dollar value of the cost of the public facilities contributed, paid for, constructed, or dedicated to the city, based on the following criteria:
(1)
The actual cost, or estimated cost of improvements based on recent bid sheet information of the city; and
(2)
A qualified appraisal of the fair market value of any land.
(e)
The property owner shall initiate a determination of entitlement to credit by submitting a proposed credit agreement to the director. The credit agreement shall include the following information:
(1)
A proposed plan of specific public facility improvements, prepared and certified by a duly qualified and licensed Florida engineer; and
(2)
The estimated costs for the suggested public facilities improvements consistent with the definition of public facilities capital costs, which shall be based on local information for similar public facilities improvements, along with a construction timetable for the completion of such improvements.
(f)
The proposed credit agreement shall be prepared by qualified professionals in the field of planning and engineering, impact analysis, and economics, as related to the particular impact fee to be credited.
(g)
Within ten (10) business days of receipt of the proposed credit agreement, the director shall determine if the proposal is complete. If it is determined that the proposed credit agreement is not complete, the director shall send a written statement to the applicant outlining the deficiencies. The director shall take no further action on the proposed credit agreement until all deficiencies have been corrected or otherwise settled.
(h)
Once the director determines the credit agreement is complete, he or she shall review it within thirty (30) business days, and shall recommend to the city commission that the proposed credit agreement be approved if it is determined that the proposed public facility improvement is consistent with the capital improvements program, and the proposed costs for the suggested public facility improvement are professionally acceptable and fairly assess the cost for the capital improvement. If the director determines that either the suggested public facilities improvement is not consistent with the capital improvements program or that the proposed costs are not acceptable, he or she may propose a suggested public facility improvement similar to that proposed, but consistent with the provisions of this article.
(i)
If the proposed credit agreement is approved by the city commission, a credit agreement shall be prepared and signed by the applicant and the city. The credit agreement shall specifically outline the public facility improvement that will be constructed by the applicant, the time by which it shall be completed, and the dollar credit the applicant shall receive for construction of the public facilities improvement.
(j)
Within ten (10) business days after execution by the city, the credit agreement shall be recorded with the Sarasota County Clerk of the Court.
(Ord. No. 14-5090, § 2, 6-16-14)