Permit to construct and operate required.
Tulsa Revised Ordinances tit. 17, § 712
in effectSection 712. - Permit to construct and operate required.
A. Scope and purpose. This regulation is adopted to define Air Resource Management Requirements, to protect and enhance Air Resources of the City of Tulsa and to assure attainment and maintenance of the ambient air quality through the use of a construction and operation permit system.
B. General requirements for permits to construct. No person shall cause or permit the construction of a new source or the modification, reconstruction or relocation of a source, without first obtaining a permit to construct from the Director, approving the location and the design of such source and assuring compliance with applicable rules, regulations and ambient air quality standards. Any person who violates the requirements of this section shall be deemed to be creating a public nuisance.
C. Application for permits to construct.
1. A separate application is required for each source described in Subsection B which has the potential of emitting pollutants to the atmosphere.
2. Each application shall be signed by the applicant. The signature of the applicant shall constitute an agreement that the applicant assumes responsibility for the construction, modification, reconstruction, relocation and use of the proposed source in accordance with this code.
D. Information required for permits to construct. Each application for a permit to construct shall be accompanied by two (2) complete copies of plans and specifications showing how the proposed source is designed and will be operated and how air pollutants will be controlled.
E. Standards for granting permits to construct.
1. No permit to construct shall be granted unless the applicant demonstrates that:
a. The source is designed and will be constructed to operate without causing a violation of federal, state and local air pollution laws;
b. The source is designed, built and equipped in accordance with the best available control technology (BACT);
c. The source will not endanger maintenance nor attainment of any applicable ambient air quality standard; and
d. The source will provide reasonable, practical and available control measures for those air contaminants not controlled by the above regulations if the Director determines such controls are necessary and in the interest of public health, welfare and property.
2. The Director may establish special conditions if it appears likely from all of the information submitted that, as a result of the conditions, the source will satisfy the requirements of this subsection.
F. Action on applications for permits to construct.
1. The application shall be acted upon within thirty (30) days of receipt of a complete application for a permit to construct. The Director shall notify the applicant in writing of his approval, conditional approval or denial of the application.
2. If any application is denied, the Director shall set forth his objections in the notice of denial. If the objection cannot be resolved by conference and conciliation, the applicant may appeal pursuant to the provisions of this chapter.
G. Cancellation of a permit to construct.
1. The Director shall cancel a permit to construct if the construction has not begun within eighteen (18) months from the date of issuance, or if the work involved in the construction is suspended for eighteen (18) months or more.
2. An applicant may secure an extension of the expiration date by written request to the Director stating the reasons for the extension. Extensions may be granted for a period of not more than eighteen (18) additional months.
H. General requirements for permits to operate. No person shall cause, suffer or allow the operation of a source constructed after October 1, 1972, without a state or City permit to operate.
1. Within sixty (60) days of startup of a new, modified or reconstructed source, an application for a permit to operate must be filed with the Director.
2. No owner or operator shall cause or permit the operation of a new, modified or reconstructed source if the Director denies or revokes a permit to operate.
3. Sources existing on the effective date of this ordinance shall have sixty (60) days in which to secure a permit to operate.
I. Applications for permits to operate. Applications for a permit to operate shall include two (2) signed application forms. Plans and specifications need not be submitted unless changes have been made since issuance of permit to construct.
J. Asbestos permits required. A permit shall be required prior to commencing any asbestos renovation or demolition project at any facility.
For the purposes of this subsection, the terms "project" and "facility" shall be defined as follows: "project" shall mean any renovation or demolition operation at any one (1) facility submitted under separate notification; "facility" shall mean any institutional, commercial or industrial structure, installation or building (excluding apartment buildings having no more than four (4) dwelling units).
K. Standards for granting permits to operate. No permit to operate a source shall be granted unless the applicant shows that the source has satisfied the requirements of the applicable rules, regulations, and has been constructed, modified or reconstructed in accordance with the requirements and conditions contained in the permit to construct.
L. Performance testing for permits to operate. Before a permit to operate a source is granted, the applicant may be required to conduct performance tests in accordance with Section 717 herein. The test will be made at the expense of the applicant. The Director shall monitor performance tests conducted by the applicant and may also conduct performance tests.
M. Action on applications for permits to operate.
1. The Director shall act within a seventy-five (75) day period on an application for a permit to operate and shall notify the applicant in writing of his approval, conditional approval or denial of the application. The seventy-five (75) day period shall begin when all test data, plans and specifications are received. The source may operate during this review period.
2. If any application is denied, the Director shall set forth his objections in the notice of denial. If the objection cannot be resolved by conference and conciliation, the applicant may appeal pursuant to Section 718.
N. Conditional permits to operate. The holder of a permit to operate shall comply with the conditions contained in his permit as well as with all applicable delegated federal, state and local laws.
O. Suspension or revocation of permits to operate.
1. A permit may be revoked or suspended for willful or continued violation of code or permit conditions.
2. Suspension or revocation of a permit to operate shall become final thirty (30) days after service of notice on the holder of the certificate unless the violation is corrected or appealed to the review board pursuant to Section 718.
3. A permit to operate which has been revoked pursuant to these provisions shall be surrendered forthwith.
P. Transfer of permit. A permit to operate shall not be transferred to another person or location. If a transfer of ownership or location occurs, a new permit to operate is necessary, but the cost of the new permit shall be one-half (½) the amount provided in Subsection Q. Transfer of stock does not constitute change of ownership unless such transfer results in a change of the controlling fifty percent (50%) interest.
Q. Permit fees required.
1. Definitions. For the purpose of this subsection, the following words and phrases shall have the meanings given herein.
a. Major source means any new or modified stationary source which directly emits or has the capability at maximum design capacity, and if appropriately permitted, authority to emit one hundred (100) tons per year or more of a given pollutant.
b. Minor source means any source for which a permit is required but is not a major source.
c. Permit renewal means the process whereby operating permits are extended for another one-year term. In no case shall the term "permit renewal" be construed to allow the imposition of additional permit requirements not otherwise required or authorized by law or ordinance.
d. Relocate means to move a source from one (1) geographical location to another. The term shall not include de minimis moves within the proximity of the original site, or contiguous areas when such moves are readily observable by inspectors.
e. Annual permit renewal fee equivalent means the annual fee assessed on facilities which, because of the date of startup or construction, are exempt from the requirements to have a permit.
2. Construction and operating permit fees - new sources. All new permits, the construction permit application for which is received after the effective date of this section, will be assessed a fee which must accompany the application, in accordance with the following schedule.
a. Major source.
(1) Construction permit .....$2,000.00
(2) Operating permit .....$1,500.00
b. Minor source (actually emitting twenty-five (25) tons, but less than one hundred (100) tons per year of any one (1) pollutant and minor NSPS sources) .....
(1) Construction permit .....$1,000.00
(2) Operating permit .....$250.00
c. Minor source (emitting more than one (1) pound per hour, but less than twenty-five (25) tons per year of any one (1) pollutant) .....
(1) Construction permit .....$200.00
(2) Operating permit .....$100.00
(3) Asbestos renovation/demolition permit .....$50.00
3. Review to determine applicability - new sources. Upon submittal of a written request, a One Hundred Dollar ($100.00) determination fee and any relevant information needed to make a permit determination, the Tulsa City-County Health Department will make a determination of whether or not a permit is required. If a determination is made that a permit is required, the One Hundred Dollar ($100.00) fee will be credited against the construction and operation permit fees. If it is determined that a permit is not required, the One Hundred Dollar ($100.00) fee will be retained by the Tulsa City-County Health Department to cover the cost of making the determination.
4. Permit renewal and renewal equivalents.
a. Applicability.
(1) The Tulsa City-County Health Department shall annually assess and collect a permit renewal fee or permit renewal fee equivalent from all facilities in the County according to their classification as set forth in Table III below. Assessments for existing facilities grandfathered from permit requirements (i.e., permit renewal fee equivalents) shall be made in the same manner and on the same basis as a new facility of the same type (permit renewal fees).
(2) New facilities shall not be subject to a permit renewal fee until a minimum of one (1) year shall have elapsed from the operating permit application due date.
b. Facility classification.
(1) Any new facility for which an appropriate classification does not exist shall be assigned a classification and class number in Table III as a permit condition.
(2) Any existing facility for which an appropriate classification does not exist shall be assigned a facility classification and class number in the same manner as (b)(1) above except that:
(a) Such assignment shall be made in writing, setting forth the reasons why the facility has been assigned to any particular category; and
(b) Any person aggrieved by such assignment shall be entitled to a hearing on the reasonableness of the assignment.
c. De Minimis.
(1) A permit renewal fee or renewal fee equivalent shall not be required, regardless of the requirement to have a permit, provided that total emissions from the facility do not exceed ten (10) tons per year for any one (1) criteria pollutant.
(2) Exceptions to the ten (10) ton de minimis facilities are the service station industry and the dry cleaning industry.
d. Assessments.
(1) Fees established under this section shall be assessed and paid on the basis of facility classification as identified in Table III. The annual fee collected for a facility in any class shall be determined by multiplying the class number for the facility, as determined by Table III, by Fifty Dollars ($50.00). In no case shall more than one (1) fee per source be assessed, unless such source shall constitute two (2) or more facilities as defined herein.
(2) On or before the first working day of each year, the Tulsa City-County Health Department will mail fee assessments to all facilities subject to this regulation. Such assessments shall be made pursuant to data contained in the emissions inventory and shall set forth:
(a) The facility classification;
(b) The class number assigned to the facility; and
(c) The amount of the fee that is to be remitted to the Tulsa City-County Health Department.
(3) Service stations and dry cleaners shall be assessed on an annual renewal fee of Twenty-Five Dollars ($25.00).
(4) For the calendar year 1989, fee assessments will be mailed on or about the effective date of this regulation and shall be due in the Offices of the Tulsa City-County Health Department, Air Quality Control, thirty (30) days from the date of receipt of the assessment.
e. Exemption. Fees set out herein shall not apply to oil and gas wells and their associated facilities or oil and gas pipelines and their associated facilities involved in the production (prior to custody transfer) of oil and gas. This exemption does not apply to storage facilities with greater than ten thousand (10,000) BBL. total capacity, compressor facilities on transmission lines and gas processing facilities.
f. Fees. Fees will be paid by check or money order made payable to the reviewing agency, Tulsa City-County Health Department. No cash will be accepted. Fees shall be due in the Offices of the Tulsa City-County Health Department thirty (30) days from the date of postmark. A ten (10) calendar day grace period will be given before any enforcement action will be taken. Upon the expiration of the ten-day grace period, notices of violation (NOV) may be issued. Further action will be in accordance with Sections 718 and 720 of this chapter.
g. No pre-emption. The fee provisions set forth herein shall apply to those permits, renewals and renewal fee equivalents processed by the Tulsa City-County Health Department and are not intended to preempt any state fee program.
R. Exemptions. Permits to construct or operate shall not be required for:
1. The installation or alteration of an air contaminant detector, air contaminant recorder, combustion controller or combustion shut-off device;
2. An air conditioning or ventilating system not designed to remove air contaminants generated by or released from process equipment;
3. Fuel-burning equipment which uses natural gas as a fuel for space heating, air conditioning or heated water, or which is used in a private dwelling or which has a BTU input of less than five hundred thousand (500,000) BTU per hour;
4. Stationary internal combustion engines smaller than two hundred forty (240) cubic inches per cylinder;
5. Laboratory equipment used exclusively for chemical or physical analyses; and
6. Changes which do not increase or change the characteristics of the emissions.
S. Opportunity for public review and comment.
1. The permit application and Tulsa City-County Health Department review for sources with potential emissions greater than one hundred (100) tons per year or one thousand (1,000) pounds per day of any air contaminant must be available for review in a suitable public building in the geographical area affected by the proposed source, project or facility. The letter of intent of the Director to approve or disapprove the application shall accompany the review package.
2. The Director will advertise in a prominent local newspaper the availability and location of all items described above. The format of the announcement will be adequate to ensure that the public is aware that an air pollution source is to be constructed. The notice shall be published once per week for a five (5) week period. The cost of publication will be borne by the applicant.
3. The Director may cause a public hearing to be held if interested persons show all pertinent air pollution data were not considered or if an error can be shown in the application or agency review. Requests for public hearing must be made within seven (7) days of final publication.
TABLE III
Industrial Classification Table
for Annual Permit Renewal and Equivalent Fees
Class Number | Facility Type
10 | Electric Power Generation: Coal
Industrial Steam Generation: Coal
Petroleum Refinery
Portland Cement Plants
Sulfuric Acid Manufacturing
Nitric Acid Manufacturing
Fertilizer Manufacturing
Municipal Incinerators
Paper Products
Carbon Black
Secondary Steel Production
New Source Performance Standard
(NSPS) Sources
Explosives
9 | Gasoline Terminals
Natural Gas Processing and Transportation:
>=10,000 hp/facility
Grain Elevators:
>=10 million bushels storage capacity
Industrial Chemical Manufacturing
Commercial Pathological Incinerators
Electric Power Generation: Gas Turbines
Felt Asphalt Coating and Other Roofing
Manufacturing
Gypsum Process and Wallboard Manufacturing
Automotive Assembly Plants
Asphalt Pipe Coating
8 | Non-Metallic Quarrying and Processing:
>=150 tons/hour rated capacity
Tile and Floor Products Manufacturing:
other than ceramic
Electronics and Related Products Manufacturing
Commercial Printers
Glass Manufacturing
Brick Manufacturing
Ceramic Tile Manufacturing
Magnetic Tape Manufacturing
Gasohol Plants
Secondary Aluminum Processing
Gray Iron Foundries
Coal Crushing Plants
Wood Related Products
Tire Manufacturing
7 | Asphalt Concrete Plants:
>=200 tons/hour rated capacity
Natural Gas Processing and Transportation:
1,000 - 10,000 hp/facility
Fiberglass Processing
Paint and Related Products
Alfalfa Drying
Roofing Granules
Cement Bulk Terminals
Flour and Grain Mills
Research and Development Labs
Plastics Processing
Petroleum Storage Facilities
Hospital Incinerators
6 | Grain Elevators:
2.5 - 10 million bushels storage capacity
Electric Power Generation:
other than coal
Industrial Steam Generation:
>=10 MMBTU/hr rated capacity, other than coal
Lubricant, Blending and Waste Oil Refining
Vermiculite and Perlite Production
Meat Packing Plants
Drilling Mud Manufacturing
Aircraft and Auxiliary Equipment
Prepared Foods
Canned Pet Food
Canneries
5 | Natural Gas Processing and Transportation:
450 - 1,000 hp/facility
Non-metallic Quarrying and Processing:
<150 tons/hour rated capacity
Paper Box Manufacturing
Metal Dross Processing
Non-Metallic General Manufacturing
Salt and Brine Extraction
Tire Retreaders
4 | Asphalt Concrete Plants:
<200 tons/hour rated capacity
Ready-Mix Concrete Plants:
>=100 cubic yards/hour capacity
Millwork and Wood Furniture Manufacturing
Charcoal Manufacturing
Non-Ferrous Foundry
Forging and Metal Stamping
Valves and Pipe Fitting
Feed and Feed Ingredients
Micro-Nutrient Manufacturing
Fertilizer Terminals
Metallic General Manufacturing
Metal Plating
Barrel and Drum Reconditioning
Steel Foundry
Rendering Plants
3 | Fabricated Structural Metal Products
Farm Machinery and Equipment Manufacturing
General Industrial Machinery and Equipment Manufacturing
Motor Vehicle Parts and Accessories
Fabricated Rubber Products
Metal Furniture and Appliance Manufacturing
Sand Plants
Signs
2 | Ready-Mix Concrete Plants:
<100 cubic yards/hour capacity
Grain Elevators:
875,000 - 2.5 million bushels storage capacity
Coal Loadout
Concrete Block Plants
Sawmill and Planing Mills
Metal Shredders
Insulation Manufacturing
1 | Wire Recovery Incinerator and Burnout Ovens
Cotton Gins
(Ord. No. 17168)
Source: City of Tulsa, Revised Ordinances and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/ok/tulsa/codes/code_of_ordinances?nodeId=COOR_TIT17HERE_CH7CLAICO_S712PECOOPREFetched: 10/28/2026