Clinton Code of Ordinances § 82-81 Definitions.
Sec. 82-81. - Definitions.
The following terms contained in this policy or in related and supplemental documents, instruments, and/or permits shall be interpreted as follows:
Applicant: Any utility company, association or individual receiving a permit from the city to locate, relocate, adjust and maintain it utility facilities within the city highway rights-of-way.
Backfill: The replacement of soil around and over a pipe or conduit.
Bedding: The organization of soil to support a pipe.
Board: The City of Clinton of Hinds County.
Bond: The approved form of security furnished by the applicant and it surety, if required, as a guaranty of good faith and ability on the part of the applicant to execute the work and maintenance in accordance with the terms of the permit and the specifications included in this policy.
Bury: Depth of the top of pipe below the grade of roadway or ditch.
Cap: Rigid structural element surmounting a pipe.
Carrier: A pipe directly enclosing a transmittal fluid (liquid or gas).
Casing: A larger pipe enclosing a carrier pipe.
City: That area of land, designated by law, under the jurisdiction of the City of Clinton.
Clear roadside policy: The policy employed by highway authorities to increase safety, improve traffic operations, and enhance the appearance of highways by designing, constructing, and maintaining highway roadsides as wide, flat, and rounded as practicable and to eliminate physical obstructions above the ground, such as trees, drainage structures, sign supports, utility poles, and other ground mounted obstructions.
Coating: Material applied to or wrapped around a pipe.
Conventional highway: An arterial highway without access control.
Conduit or duct: An enclosed tubular runway for protecting wires or cables.
Cradle: Rigid structural element below and supporting a pipe.
Crown: The vertical rise between the edge of the road (shoulder line) and the center of the road.
Crown width: The horizontal distance between the shoulder lines of the road.
Direct burial: Installing a utility facility underground without encasement.
Drain: Appurtenance to discharge liquid contaminants from casings.
Encasements: Structural element surrounding a pipe.
Encroachment: Authorized or unauthorized use of highway rights-of-way or easements, as for signs, fences, building, etc.
Engineer: The city engineer employed by the City of Clinton accordance with law and acting under the rules and regulations of this policy and the approval of the State Aid engineer.
Flexible pipe: A plastic, fiberglass or metallic pipe having a large ratio of diameter to wall thickness which can be deformed without undue stress.
Gallery: An underpass for two or more pipelines.
Grounded: Connected to earth or to some extended conducting body, which serves instead of the earth, whether the connection is intentional or accidental.
Grout: A cement mortar or a slurry of fine sand or clay, as conditions govern.
Highway, street or road: A general term denoting a public way for the purpose of the vehicular travel, including the entire area within the right-of-way.
Jacket: Encasement by concrete poured around a pipe.
Manhole: An opening in an underground system which workman or others may enter for the purpose of making installations, inspections, repairs, connections and tests.
Median: The portion of a divided highway separating the traveled way for traffic in opposite directions.
Materials: Any specified substance, manufactured items or raw materials used in the utility facility construction.
Normal: Crossing at a right angle.
Oblique: Crossing at an acute angle.
Overfill: Backfill above a drainage structure above natural ground.
Pavement structure: The combination of subbase, base course, and surface course placed on the subgrade to support the traffic load and distribute it to the roadbed.
Permit: The permission, in written form, issued by the city through its authorized representative to the applicant to proceed with the utility facility location, relocation, and/or adjustment within the highway rights-of-way under the provisions of this policy.
Plans: The proposal of the applicant to do certain utility work with in a highway right-of-way, including working drawings showing the location, character of work, dimensions, and details of the work proposed.
Pipe: A tubular product made as a production item for sale as such. Cylinders formed from plate in the course of the fabrication of auxiliary equipment are not pipe as defined here.
Pressure: Relative internal pressure in PSIG (pounds per square inch gauge).
Project: Specific construction within a highway right-of-way for which a permit is sought by the applicant.
Right-of-way: The land conveyed, reserved, secured, dedicated, acquired, or used for highway or street purposes.
Rigid pipe: A welded or bolted metallic pipe or reinforced, prestressed, or pretensioned concrete pressure pipe designed for diametric diametric deflection of less than 1.0 percent.
Roadbed: The graded portion of a road, between the intersection of top and side slopes, upon which the pavement structure and shoulders are constructed.
Roadside: A general term denoting the area adjoining the outer edge of the roadway.
Roadway: The portion of a highway, including shoulders, for vehicular use.
Semi-rigid pipe: A large diameter, metallic pipe designed to tolerate diametric deflection up to 3.0 percent.
Sidefill: Backfill alongside a pipe.
Shoulders: That portion of roadway contiguous with the traveled way for accommodating stopped vehicles and for lateral support of the base and surface courses.
Sleeve: A short casing through a pier or abutment of a highway structure.
Special provisions: Specific directions and provisions additional to the specifications included in this policy and made a part of the permit, setting forth conditions or requirements peculiar to the permit or project and which govern over said specifications.
State aid engineer: The engineer who is responsible for administering the State Aid Road Program as provided for in Section 8035-02, Mississippi Code of 1942, Recompiled, as amended.
Subgrade: That portion of the roadway prepared as foundation for the subbase, base, and pavement structure. The subgrade may be considered as part of the subbase structure when treated with appropriate additives.
Surety: That corporate body, qualified under the laws of Mississippi, which is bound with and for the applicant for acceptable performance of the project construction and maintenance.
Traveled way: That portion of the roadway for the movement of vehicles, exclusive of shoulders and auxiliary lanes.
Trenched: Installed in a narrow open excavation.
Untrenched: Installed without breaking ground or pavement surface, such as by jacking or boring.
Use and occupancy agreement: The document by which the city regulates and gives approval of the use and occupancy of city highway right-of-way for utility facilities.
Utility: Any public or private company, whether owned by a person, partnership, district, association or corporation, including, but not limited to, operating an electric, telephone, radio, cable, telegraph, gas, oil, water, or sewer transmission or distribution, proposing to construct or adjust its lines with in the right-of-way of a city highway street. A utility shall include any contractor or subcontractor, or other person proposing to perform work for applicant within a city highway right-of-way. The words "applicant" and "utility" mean the same in the policy.
Vent: An appurtenance to discharge gaseous contaminants from casings.
Walled: Partially encased by concrete poured alongside the pipe.
(Ord. of 05-15-2007(2) )