Sec. 29.5-9. - Right-of-way improvements escrow fund.
(a)
This section 29-5.9 shall apply in those situations in which an applicant for development approval must, in compliance with the engineering design criteria manual, improve adjacent right-of-way including, but not limited to a half section of roadway, sidewalk, curb and gutter, as a condition precedent to the city issuing a certificate of occupancy to the development. In those situations, the city engineer, in his/her sole discretion, may determine an escrow fund deposit may be made by the applicant for development approval in lieu of said applicant constructing a new half section of roadway including sidewalk, curb and gutter. The city engineer shall consider the following factors in determining whether an applicant for development approval must construct a new half section of roadway including sidewalk, curb and gutter or, alternatively, must make a deposit into a city escrow fund:
(1)
The city engineer shall review the existing right-of-way cross section within the block of roadway adjacent to the real property subject to an application for development approval.
(2)
The city engineer shall review the proposed right-of-way cross section required by the engineering design criteria manual for the block adjacent to the real property subject to an application for development approval.
(3)
The city engineer shall determine the financial and technical feasibility and compatibility of constructing a new right-of-way cross section in compliance with the engineering design criteria manual within the same block as the existing right-of-way cross section.
(b)
If the city engineer, in his/her sole discretion, determines that it is financially and technically feasible and compatible to require an applicant for development approval to construct a new right-of-way cross section in compliance with the engineering design criteria manual, the applicant for development approval shall do so as a condition precedent to obtaining a certificate of occupancy for the proposed development.
(c)
If the city engineer, in his/her sole discretion, determines that it is not financially and technically feasible and compatible to require an applicant for development approval to construct a new right-of-way cross section in compliance with the engineering design criteria manual, the following shall occur:
(1)
The city engineer shall provide written notification to the applicant for development approval of the city engineer's determination.
(2)
The applicant for development approval shall obtain a cost estimate for the right-of-way improvements to the half section of roadway including, sidewalk, curb and gutter otherwise required by the engineering design criteria manual. The applicant shall obtain such written estimate from a contractor duly licensed and otherwise authorized to perform the roadway improvements. The applicant shall provide the written estimate to the city engineer within the sixty (60) day period immediately following the city engineer's written notice described above.
(3)
The city engineer shall have thirty (30) days from receipt of the cost estimate to review same and approve or disapprove the cost estimate in writing. If the city engineer disapproves the cost estimate, the city engineer shall so notify the applicant for development approval. The applicant shall have an additional sixty (60) day period to obtain another written cost estimate in compliance with this section. At such time as the city engineer issues a written approval of the cost estimate, the city engineer shall provide same to the applicant for development approval.
(4)
The applicant for development approval shall, within thirty (30) days of receipt of the city engineer's approval of the cost estimate, make a payment to the City of Sarasota in the amount of one hundred fifteen (115) percent of the cost estimate. The city shall place the cost estimate deposit into an escrow account. Any interest earned on the deposit shall be retained by the city. Alternatively, if the city engineer determines that some of the improvements are required to make the right-of-way functional until the full cross-section can be constructed, the city engineer may require the applicant for development approval to make such improvements. In this event, the cost of such improvements shall be deducted from the required payment to the City of Sarasota in the amount of one hundred fifteen (115) percent of the total cost estimate to be deposited into an escrow account. However, construction of such improvements shall not commence until the city engineer has provided written approval of a cost estimate for those improvements alone.
(5)
Upon city's receipt of the cost estimate escrow deposit, the applicant for development approval, if otherwise authorized, may receive a certificate of occupancy from the city.
(d)
The city shall hold the cost estimate deposit funds in escrow until the city engineer, in his/her sole discretion, determines there are an adequate number of properties within the block adjacent to the real property subject to the application for development approval which are ready, willing and able to rebuild the subject right-of-way cross section so as to make it financially and technically feasible and compatible to reconstruct the right-of-way cross section for the entire block in conformance with the requirements of the engineering design criteria manual. At that time, the city shall use the funds held in escrow to construct adjacent to the developed property, the right-of-way improvements, including, but not limited to, the half section of roadway including sidewalk, curb and gutter to the specifications of the engineering design criteria manual.
(e)
If the city engineer in his/her sole discretion, does not determine that there are an adequate number of properties within the block adjacent to the real property subject to the application for development approval which are ready, willing and able to rebuild the subject right-of-way cross section so as to make it financially and technically feasible and compatible to reconstruct the right-of-way cross section for the entire block in conformance with the requirements of the engineering design criteria manual within a period of twenty (20) years from the date of the escrow deposit described in subsection (c)(4) above, the provisions of subsection (e) shall control. In such event, the city engineer shall recommend to the city manager that the applicant receive a technical deviation from the engineering design criteria manual such that the reconstruction of the right-of-way cross section shall no longer be required. In such event, the escrow deposit, with any interest received by the City of Sarasota, shall be returned to the applicant. If the applicant is no longer the owner of the subject real property, the escrow deposit shall be returned to the current owner of the real property.
(Ord. No. 07-4739, § 1, 4-7-08; Ord. No. 24-5551, § 1, 11-18-24)