Code of Ordinances of the City of Huntsville, Alabama (Supp. No. 30 (codified through Ord. No. 26-196, adopted March 12, 2026) with enacted ordinances through Ord. No. 26-837 (September 24, 2026) applied from official council minutes and ordinance copies) · Huntsville Code of Ordinances, App. B, art. 4, § 4.15

Corpus is an independent public-information project, not the official City of Huntsville website. Stable reference: corpuslaw.us/code/a0072873-ce19-4d47-a617-ed76155bd224

4.15. - Standards for geotechnical investigations and tests.

(1) Subsurface exploration. A. For all proposed structures other than roadways, acceptable subsurface explorations shall be performed at a minimum rate of two per structure or four per study if only one structure is proposed. B. For each proposed lot acceptable subsurface explorations shall be performed at a minimum rate of two per buildable area of each lot. Said subsurface explorations shall be adequately spaced to provide for a clear indication of the stability of the entire buildable area of each proposed lot. C. For roadway construction, acceptable subsurface explorations shall be performed along the centerline of the proposed roadway at a maximum space of 500 linear feet throughout the length of the roadway. In cases where the proposed roadway is less than 2,000 linear feet in length, a minimum of four subsurface explorations shall be performed and spaced adequately to cover the length of the roadway. D. Acceptable subsurface exploration methods include: (i) Test pit excavations down to unweathered bedrock. (ii) Soil (regolith) borings to unweathered bedrock. (iii) Rock corings. E. If unweathered bedrock is located at the surface of the buildable area of any proposed lot or any proposed area to be covered by a structure, as shown on the proposed plan, and no significant hazards have been documented or identified to exist within said area(s), the planning commission may waive the required subsurface explorations to be performed within those given buildable areas. F. Rock corings shall include a minimum of five feet of rock coring per boring. G. Soil (regolith) and rock classification for each subsurface exploration shall be performed according to American Society for Testing and Materials (ASTM) procedures. H. Each subsurface exploration shall be measured for ground water. Where necessary or required, piezometers shall be placed in the borings and measured periodically for high/low ground water tables. I. Subsurface explorations shall be sufficient to reasonably determine thickness and type of all soils (regolith). (2) Soil properties. Minimum soil properties tests shall be performed for each different soil or regolith type from each subsurface exploration having more than two feet of soil above bedrock and shall include: A. Standard classification tests (ASTM). B. Consolidation tests. C. Shrink/swell potential. D. Triaxial shear tests. E. Atterberg liquid limit (measured for soil fraction smaller than the no. 40 sieve-fine sand and smaller). F. Approximate mobility index (ratio of saturated water content of in-place or undisturbed soil to its Atterberg liquid limit). G. A separate sample for each soil sample analyzed shall be held by the geotechnical engineer for a minimum of 90 days or until all roadway construction is complete (whichever is longer) and shall be analyzed for additional tests if required or shall be made available for tests by an independent agency. Each soil sample shall be placed in a separate waterproof container to retain moisture and prevent contamination. (3) Slope stability and structural analyses (multiple analyses). Multiple analyses shall be performed on all fill slopes and all cut slopes of greater than four feet vertical relief in soil and should be performed on the best, worst, and average soil and embankment conditions as determined on site by the geotechnical engineer. A. Sliding wedge and slip circle analyses shall be performed on the uphill side of excavation embankments. B. Slip circle analyses shall be performed on all fill embankments. C. Based on the analyses, the lowest safety factors shall be reported for each method along with all of the design conditions. D. Structural performance should be analyzed with respect to bearing capacity and settlement.

Ask a question about Huntsville law

Corpus searches the Huntsville sections it holds and shows the ones that match, with their citations. Free, no sign-in.