Authority to resolve contract and breach of contract controversies.
R.I. Gen. Laws § 37-2-46
in effect37-2-46. Authority to resolve contract and breach of contract controversies.
Prior to the institution of arbitration or litigation concerning any contract, claim,
or controversy, the chief purchasing officer is authorized, subject to any limitations
or conditions imposed by regulations, to settle, compromise, pay, or otherwise adjust
the claim, by or against, or controversy with a contractor relating to a contract
entered into by the department of administration on behalf of the state or any state
agency, including a claim or controversy based on contract, mistake, misrepresentation,
or other cause for contract modification or rescission, but excluding any claim or
controversy involving penalties or forfeitures prescribed by statute or regulation
where an official other than the chief purchasing officer is specifically authorized
to settle or determine the controversy.
P.L. 1989, ch. 526, § 2.