Enforcement.
Milwaukee Code of Ordinances § 290-15
in effect290-15. Enforcement.
1. BUILDING, SITE DEVELOPMENT AND SERVICES NOT LET TO PUBLIC WORKS CONTRACT. a. The department may issue an order to correct violations or a stop-work order or both if any land disturbing construction activity regulated under this chapter is being undertaken without a permit or in violation of the conditions of the permit.
b. If the prime contractor or owner does not cease the activity or comply with the permit conditions within 24 hours or as specified by the department, the department may revoke the permit.
c. If the prime contractor or owner does not cease the activity within 24 hours or as specified by the department, the department may request the city attorney to obtain a cease and desist order.
d. The department may retract the stop-work order or the revocation.
e. After the time for compliance on the stop-work order or order to correct violations notice has passed, the department may issue a notice of intent to the prime contractor or owner of the department's intent to perform work necessary to comply with this chapter. The department may go on the land and commence the work after 3 days from mailing or serving the notice of intent.
f. The department may issue a citation with or without prior order for any violation of this chapter as provided in s. 200-19-2.
g. Any person violating this chapter shall be subject to penalty pursuant to s. 200-19-2.
2. RIGHT-OF-WAY AND PUBLIC UTILITY EASEMENTS; PUBLIC WORKS CONTRACT. a. The department of public works may order construction halted if:
a-1. The activity regulated under this chapter is undertaken without a permit.
a-2. The control plan is not being implemented in good faith.
a-3. The conditions of the permit are not being met.
b. After the department of public works notifies the offender of noncompliance, it may take whatever steps are necessary to enforce the plan, including, but not limited to, having the permittee make corrections, using its own forces, or engaging other contractors. The cost of such work shall be charged to the permittee and collectable as provided in chs. 79, 115 and 116 or the contract specifications.
3. RECOVERY OF COSTS. If the actual costs of implementing an erosion control plan exceeds the amount deposited in the irrevocable letter of credit, the department shall recover the additional cost from the prime contractor or owner by initiating within 30 days a court action to recover from such person an amount sufficient to compensate the city for the expense and labor in making such repairs or providing such utilities or fuel services as well as associated administrative costs. Administrative costs shall be deemed to be no less than $50 per hour per inspector field hour incurred pursuant to actions under this section.