Utility location policies.
El Paso City Code § 19.14.020
in effect19.14.020 - Utility location policies.
A. Placement. It is in the city's best interest to coordinate and regulate the placement of utilities within public rights-of-way or public or private easements. Such regulations and coordination shall be managed under the general standards of this chapter.
B. Standards.
1. Public street rights-of-way shall be the preferred location for all utility extensions to the extent reasonably possible.
2. In order to accommodate the multiple public and franchise utilities within the public street right-of-way, there shall be a minimum amount of unpaved right-of-way outside of and in addition to the right-of-way covered by street paving, sidewalk and curb-and-gutter in accordance with the SDM street cross sections and requirements. This unpaved area may be between the curb and sidewalk or on the outside of the sidewalk. The minimum roadway cross sections in Chapter 19.15 have been designed with a minimum area behind the curb, and sufficient right-of-way to meet this requirement in accordance with the SDM shall be dedicated to accommodate over-width sidewalks, bikeways, or any surface improvement.
3. Easements on private property may be used in the following instances and under conditions specified therein:
a. For pedestal, transformer and utility hut pads;
b. Where special developments (i.e., cluster subdivisions and planned development districts) occur;
c. Where public or private streets are platted lacking sufficient parkway to install required and franchise utilities and, even then, such easements as needed shall be provided adjacent and parallel to the street;
d. Where on-site ponding is proposed and the parkway is proposed to be removed to accommodate the on-site ponding, then the utilities must be located in an adjacent easement;
e. Where unusual circumstances prevent use of the public right-of-way or private street; and
f. Easements shall be a minimum of ten feet on private property, or as specified by the utility provider utilizing the easement.
4. Prior to the pavement installation, the subdivider shall obtain a written release from each utility provider indicating that required utility installation is complete. Subdividers shall provide such release to the city.
5. A joint trench for electric and communication utilities shall be provided, in accordance with the SDM. Separate trenching for electric and communication utilities will be allowed only:
a. In the mountain development area, in accordance with Chapter 19.24;
b. For individual street crossings;
c. For service drops;
d. Where existing service feeds or sources are coming from demonstrably different directions;
e. In replats where existing utilities are in separate trenches.
6. Conduit, to accommodate electric, telephone and cable television service lines at street crossings extending from closures on one side of the street, shall be provided. Utilities shall meet the locational criteria, if any, contained in the SDM.
(Ord. 16882 § 2 (part), 2008; Ord. No. 19327, § 18, 4-26-2022)
Source: City of El Paso, City Code and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/tx/el_paso/codes/code_of_ordinances?nodeId=TIT19SUDEPL_ART2SUST_CH19.14UTGE_19.14.020UTLOPOFetched: 10/28/2026