Provisions applicable to public works contracts — Lists of subcontractors.
R.I. Gen. Laws § 37-13-4
in effect37-13-4. Provisions applicable to public works contracts — Lists of subcontractors.
All public works shall be done by contract, subject to the same provisions of law
relating thereto and to the letting thereof, which are applicable to similar contracts
of the awarding authority or authorized agency, hereinafter called the “proper authority”,
in the general location where the work is to be performed and which are not contrary
to the provisions of §§ 37-13-1 — 37-13-14 and § 37-13-16. Each contractor after the award of a contract for public works shall submit to the
proper authority a list of his or her subcontractors of any part or all of the work.
The list shall be submitted in such manner or form as the proper authority shall uniformly
require from contractors in all public works.
P.L. 1936, ch. 2361, § 1; G.L. 1938, ch. 290, §§ 1, 3; P.L. 1955, ch. 3580, § 1; G.L.
1956, § 37-13-4; P.L. 1965, ch. 77, § 1.