Sec. 24-143. Construction and Post-Construction Stormwater Management; Completion of Work.
When construction activities have been completed and the site has met the final stabilization requirements of the Construction General Permit, the authorized site representative may file a Notice of Termination (NOT) with ADEQ, with a copy submitted to the City Manager, to terminate coverage under the SWMP permit. (Ord. 2010-06, 02/02/2010, Enacted (SUPP 2010))