Expedited permit process.
R.I. Gen. Laws § 42-64.9-11
in effect42-64.9-11. Expedited permit process.
Any building designated by the enterprise zone council as a certified building shall
be immediately forwarded by the building owner to the governor and the board of directors
of the Rhode Island economic development corporation for consideration as a project
of critical economic concern as that term is defined in § 42-117-3 and shall be entitled to the benefits of chapter 117 of this title.
P.L. 2004, ch. 277, § 1; P.L. 2004, ch. 284, § 1.