Sec. 36-93. - Permit required to work within city right-of-way.
Anytime a contractor performs any work within the street right-of-way of the City of Pasadena, the contractor shall be required to obtain written permission from the traffic director. This permit is in addition to any other permit required by the city. All routine submissions for permits shall be received a minimum of forty-eight (48) hours in advance of beginning of the work. At no time shall the contractor begin work without obtaining the required permit. The permit shall be kept on site and shall be presented on demand at all times for review by the police, fire, public works, permit, and traffic departments' personnel.
In the event of an emergency, the contractor may take immediate action to correct the situation but shall also immediately and personally contact the office of the traffic and transportation department to make application for a permit. If the emergency occurs after normal working hours and the traffic and transportation department is closed, the contractor shall immediately contact the emergency dispatcher and make application for a permit in the morning of the next normal working day.
When applying for the permit, the contractor or contractors' designated representative shall be required to submit all pertinent information including but not limited to the number of days required to complete the work, the times of day, area of work (including street names, block numbers, direction of travel affected), and reason for working in the city right-of-way.
Depending of the complexity of the work, the traffic director or his designated representative may require plans to be submitted by a licensed traffic engineer and bear the appropriate seal, signature, and date of preparation. In all cases, the contractor, as a minimum, shall be required to install any and all signs and pavement markings required by the latest revision of the Texas Manual on Uniform Traffic Control Devices. Flagmen or other means of traffic control may be required upon the determination of the traffic director.
In the interest of increasing public safety and reducing delay and inconvenience, no lane closures shall be allowed during the morning and evening peak periods of traffic from 7 to 9 a.m. and from 4 to 6 p.m., Monday through Friday. The traffic director may grant exceptions upon specific request.
Upon issuance of the permit, the traffic director shall notify the police and fire dispatch, police operations, and public works department of the nature and terms of the permit.
Failure to comply with any of the provisions of this section may result in immediate termination of work within the right-of-way and revocation of any other city permit. Any police officer or representative of the traffic and transportation department, permit department, or public works department may order immediate termination of work within the right-of-way.
(Ord. No. 1780, § 1 (28-76), 3-15-66; Ord. No. 01-53, § 1, 3-20-01)