Sec. 44-59. - Specifications and construction requirements.
Such installation, repair or removal of water, sewer or gas mains, electric utility or telephone lines in existing paved, or unpaved streets, alleys or other public places in the corporate limits of the city shall be done in accordance with the following specifications and requirements:
(1) Backfilling. All excavations within a right-of-way and not under surfacing shall be back-filled by tamping in six-inch horizontal layers, ponding or jetting. All surface materials shall be removed from the right-of-way and the excavation finished flush with surrounding natural ground.
(2) Sodding on certain slopes. Where sodding is disturbed by excavation or back-filling operations, such areas shall be replaced by mulch sodding on all slopes of two percent or less. All slopes over two percent shall be replaced by black sodding.
(3) Back-filling gravel streets or streets under construction. All excavation in gravel streets or streets under construction shall be back-filled with select material by tamping six-inch horizontal layers to finished grade, then the top six inches of back-fill shall be removed and replaced with one-inch road base, tamped or rolled to 95 percent of density.
(4) Boring under surfaced streets. Crossings under surfaced streets within the right-of-way shall be placed by boring. Boring shall extend from crown line to crown line, or to a point two inches beyond back of curb. All lines under streets carrying pressure shall be enclosed in casing satisfactory to the city. Gravity flow sewer lines placed under existing paved streets by boring shall be cast iron pipe.
(5) Where boring impracticable. Where evidence is presented indicating the impracticability of boring or tunneling, the public works director of the city may grant permission to cut the surfacing. In the event a cut is permitted, the following conditions shall govern said operation:
a. If the surface to be cut is an asphalt surface, it shall be cut or scored in a straight line before any digging has begun to prevent breaking the seal of the paved area not to be disturbed.
b. All back-fill material shall be stabilized with Portland cement and mixed in a concrete mixer or transit mix equipment. If soil is used, it shall be sandy material free from lumps or clods, and shall be stabilized with two sacks of cement per cubic yard of soil. If sand and gravel are used, pit run material will be allowed, and it shall be stabilized with one sack of cement per cubic yard. Backfill may be mechanically tamped in a moist condition or water added to provide a free flowing mixture. Stabilized backfill shall be completed to a point 1½ inches below existing finished grade and the remaining 1½ inches shall be replaced with hot mix asphaltic concrete; hot or cold lay.
(6) Excavations along highways. Operations along highways shall be performed in compliance with state department of highways and public transportation specifications and in such manner that all excavated material is kept off the pavement at all times, as well as all operating equipment.
(7) Terms of permit to be complied with; damage to be avoided.
a. It shall be unlawful to make any such excavation or tunnel in any way contrary to or at variance with the terms of the permit therefor. Proper bracing shall be maintained to prevent the collapse of adjoining ground; and in excavations the excavations shall not have anywhere below the surface any portion which extends beyond the opening at the surface.
b. No injury shall be done to any pipes, cables, or conduits in the making of such excavations or tunnels; and notice shall be given to the persons maintaining any such pipes, cables or conduits or to the city department or officer charged with the care thereof which are or may be endangered or affected by the making of any such excavation or tunnel before such pipes, cables or conduits shall be disturbed.
c. No unnecessary damage or injury shall be done to any tree, shrub or the roots thereof.
(8) When sidewalk blocked by work. If any sidewalk is blocked by any such work, a temporary sidewalk shall be constructed or provided which shall be safe for travel and convenient for users.
(9) Responsibility for enforcement. The director of public works or his designee shall be responsible for the enforcement of the provisions of this article. Notice shall be given to him at least ten hours before the work of refilling any tunnel or excavation commences.
(10) Barriers and warning devices to be properly placed and maintained.
a. It shall be the duty of every person cutting or making an excavation in or upon any public place, to place and maintain barriers and warning devices necessary for the safety of the general public. Barriers, warning signs, lights, etc., shall conform to the requirements of the city. Warning lights shall be flares, torches, lanterns, electrical markers or flashers used to indicate a hazard to traffic from sunset of each day to sunrise of the next day.
b. The permittee shall take appropriate measures to ensure that during the performance of the excavation or other work, traffic conditions as near normal as possible shall be maintained at all times so as to minimize inconvenience to the occupants of the adjoining property and to the general public. When traffic conditions permit, the director of public works may, by written approval, permit the closing of streets and alleys to all traffic for a period of time prescribed by him, if in his opinion it is necessary. Such written approval may require that the permittee give notification to various public agencies and to the general public. In such cases, such written approval shall not be valid until such notice is given.
c. Warning signs shall be placed far enough in advance of the construction operation to alert traffic within a public street, and cones or other approved devices shall be placed to channel traffic, in accordance with the instructions of the director of public works.
(11) Access to vital equipment to be maintained. All works performed shall be performed and conducted so as not to interfere with access to fire hydrants, fire stations, fire escapes, water gates, underground vaults, valve housing structures and all other vital equipment as designated by the director of public works.
(12) Permittee to maintain safe crossings for vehicles and pedestrians. The permittee shall maintain safe crossings for two lanes of vehicle traffic at all street intersections where possible and safe crossings for pedestrians at intervals of not more than 300 feet. If any excavation or work is made across any public street, alley or sidewalk, adequate crossings shall be maintained for vehicles and for pedestrians. If the street is not wide enough to hold the excavated material without using part of the adjacent sidewalk, a passageway at least one-half of the sidewalk width shall be maintained along such sidewalk line.
(13) Permittee to preserve and protect private and public property. The permittee shall at all times and at his own expense preserve and protect from injury any adjoining property by providing proper foundations and taking other measures suitable for the purpose. Where in the protection of such property it is necessary to enter upon private property for the purpose of taking appropriate protecting measures, the permittee shall first obtain consent from the owner of such private property for such purpose and if he cannot obtain such consent, the director of public works may authorize him to enter the private premises solely for the purpose of making the property safe. The permittee shall, at his own expense, shore up and protect all buildings, walls, fences or other property likely to be damaged during the progress of the excavation work, and shall be responsible for all damage to public or private property or highways resulting from his failure to properly protect and carry out such work. Whenever it may be necessary for the permittee to trench through any lawn area, said area shall be re-seeded or the sod shall be carefully cut and rolled and replaced after ditches have been back-filled as required in this section. All construction and maintenance work shall be done in a manner calculated to leave the lawn area clean of earth and debris and in a condition as nearly as possible to that which existed before such work began. The permittee shall not remove, even temporarily, any trees or shrubs which exist in parking strip areas without first obtaining the consent of the appropriate city department or city official having supervision of such property.
(14) Streets to be thoroughly cleaned of debris. As the work progresses, all streets shall be thoroughly cleaned of all rubbish, excess rock, earth or other debris resulting from such work. All clean-up operations at the location of such excavation shall be accomplished at the expense of the permittee and shall be completed to the satisfaction of the director of public works. From time to time, as may be ordered by the director of public works and in any event immediately after completion of said work, the permittee shall, at his own expense, clean up and remove all refuse and unused materials of any kind resulting from said work, and upon failure to do so within 24 hours after having been notified to do so by the director of public works, said work may be done by the director of public works and the cost thereof charged to the permittee, and the permittee shall also be liable for the cost thereof under the surety bond provided hereunder.
(15) Street to be restored to original condition as quickly as possible. After an excavation or other work is commenced, the permittee shall prosecute with diligence and expedition all work covered by the permit and shall promptly complete such work and restore the street to its original condition, or as near as may be, so as not to obstruct the public place or travel thereon more than is reasonably necessary.
(16) Unnecessary inconvenience, annoyance, and noise to be avoided. Each permittee shall conduct and carry out the work in such a manner as to avoid unnecessary inconvenience and annoyance to the general public and occupants of neighboring property. The permittee shall take appropriate measures to reduce to the fullest extent practicable in the performance of the excavation work, noise, dust and unsightly debris and between the hours of 9:00 p.m. and 8:00 a.m. shall not use, except in case of emergency, any tool, appliance or equipment producing noise of sufficient volume to disturb the sleep or repose of occupants of the neighboring property.
(17) Emergency repairs authorized. Nothing in this article shall be construed to prevent the making of such repairs or excavations as may be necessary for the preservation of life or property or for the location of trouble in conduit or pipe, or for making repairs, or for restoring utility service, provided that the person making such excavation shall apply to the director of public works for a permit on the first working day after such work is commenced and fully comply with the other requirements of this article.
(Code 1995, § 10.305; Ord. No. 305, 12-19-1974; Ord. No. 307, 4-10-1975)