39-26.4-2. Definitions.
Terms not defined in this section herein shall have the same meaning as contained
in chapter 26 of this title. When used in this chapter:
(1) “Community remote net-metering system” means a facility generating electricity using
an eligible net-metering resource that allocates net-metering credits to a minimum
of one account for a system associated with low- or moderate-income housing eligible
credit recipients, or three (3) eligible credit-recipient customer accounts, provided
that no more than fifty percent (50%) of the credits produced by the system are allocated
to one eligible credit recipient, and provided further at least fifty percent (50%)
of the credits produced by the system are allocated to the remaining eligible credit
recipients in an amount not to exceed that which is produced annually by twenty-five
kilowatt (25 KW) AC capacity. The community remote net-metering system may transfer
credits to eligible credit recipients in an amount that is equal to or less than the
sum of the usage of the eligible credit recipient accounts measured by the three-year
(3) average annual consumption of energy over the previous three (3) years. A projected
annual consumption of energy may be used until the actual three-year (3) average annual
consumption of energy over the previous three (3) years at the eligible credit recipient
accounts becomes available for use in determining eligibility of the generating system.
The community remote net-metering system may be owned by the same entity that is the
customer of record on the net-metered account or may be owned by a third party.
(2) “Core forest” refers to unfragmented forest blocks of single or multiple parcels totaling
two hundred fifty (250) acres or greater unbroken by development and at least twenty-five
(25) yards from mapped roads, with eligibility questions to be resolved by the director
of the department of environmental management. Such determination shall constitute
a contested case as defined in § 42-35-1.
(3) “Electric distribution company” shall have the same meaning as § 39-1-2, but shall not include Block Island Power Company or Pascoag Utility District, each
of whom shall be required to offer net metering to customers through a tariff approved
by the public utilities commission after a public hearing. Any tariff or policy on
file with the public utilities commission on the date of passage of this chapter shall
remain in effect until the commission approves a new tariff.
(4) “Eligible credit recipient” means one of the following eligible recipients in the
electric distribution company’s service territory whose electric service account or
accounts may receive net-metering credits from a community remote net-metering system.
Eligible credit recipients include the following definitions:
(i) Residential accounts in good standing.
(ii) “Low- or moderate-income housing eligible credit recipient” means an electric service
account or accounts in good standing associated with any housing development or developments
owned or operated by a public agency, nonprofit organization, limited-equity housing
cooperative, or private developer that receives assistance under any federal, state,
or municipal government program to assist the construction or rehabilitation of housing
affordable to low- or moderate-income households, as defined in the applicable federal
or state statute, or local ordinance, encumbered by a deed restriction or other covenant
recorded in the land records of the municipality in which the housing is located,
that:
(A) Restricts occupancy of no less than fifty percent (50%) of the housing to households
with a gross, annual income that does not exceed eighty percent (80%) of the area
median income as defined annually by the United States Department of Housing and Urban
Development (HUD);
(B) Restricts the monthly rent, including a utility allowance, that may be charged to
residents, to an amount that does not exceed thirty percent (30%) of the gross, monthly
income of a household earning eighty percent (80%) of the area median income as defined
annually by HUD;
(C) Has an original term of not less than thirty (30) years from initial occupancy.
Electric service account or accounts in good standing associated with housing developments
that are under common ownership or control may be considered a single low- or moderate-income
housing eligible credit recipient for purposes of this section. The value of the credits
shall be used to provide benefits to tenants.
(iii) “Educational institutions” means public and private schools at the primary, secondary,
and postsecondary levels.
(iv) “Commercial or industrial customers” means any nonresidential customer of the electric
distribution company.
(5) “Eligible net-metering resource” means eligible renewable energy resource, as defined
in § 39-26-5 including biogas created as a result of anaerobic digestion, but, specifically excluding
all other listed eligible biomass fuels.
(6) “Eligible net-metering system” means a facility generating electricity using an eligible
net-metering resource that, for any system with a nameplate capacity in excess of
twenty-five kilowatts (25 KW), is reasonably designed and sized to annually produce
electricity in an amount that is equal to, or less than, the renewable self-generator’s
usage at the eligible net-metering system site measured by the three-year (3) average
annual consumption of energy over the previous three (3) years at the electric distribution
account(s) located at the eligible net-metering system site. A projected annual consumption
of energy may be used until the actual three-year (3) average annual consumption of
energy over the previous three (3) years at the electric distribution account(s) located
at the eligible net-metering system site becomes available for use in determining
eligibility of the generating system. For any system with a nameplate capacity equal
to or less than twenty-five kilowatts (25 KW), eligibility shall not be restricted
based on prior consumption. The eligible net-metering system may be owned by the same
entity that is the customer of record on the net-metered accounts or may be owned
by a third party that is not the customer of record at the eligible net-metering system
site and which may offer a third-party, net-metering financing arrangement or net-metering
financing arrangement, as applicable. Notwithstanding any other provisions of this
chapter, any eligible net-metering resource: (i) Owned by a public entity, educational
institution, hospital, nonprofit, or multi-municipal collaborative; or (ii) Owned
and operated by a renewable-generation developer on behalf of a public entity, educational
institution, hospital, nonprofit, or multi-municipal collaborative through a net-metering
financing arrangement shall be treated as an eligible net-metering system and all
accounts designated by the public entity, educational institution, hospital, nonprofit,
or multi-municipal collaborative for net metering shall be treated as accounts eligible
for net metering within an eligible net-metering system site; or (iii) Owned and operated
by a renewable-generation developer on behalf of one or more commercial or industrial
customer(s) through net-metering financing arrangement(s) shall be treated as an eligible
net-metering system within an eligible net-metering system site. Notwithstanding any
other provision to the contrary, effective July 1, 2060, an eligible net-metering
system means a facility generating electricity using an eligible net-metering resource
that is interconnected behind the same meter as the net-metering customer’s load.
(7) “Eligible net-metering system site” means the site where the eligible net-metering
system or community remote net-metering system is located or is part of the same campus
or complex of sites contiguous to one another and the site where the eligible net-metering
system or community remote net-metering system is located or a farm on which the eligible
net-metering system or community remote net-metering system is located. Except for
an eligible net-metering system owned by or operated on behalf of a public entity,
educational institution, hospital, nonprofit, or multi-municipal collaborative or
for a commercial or industrial customer through a net-metering financing arrangement,
the purpose of this definition is to reasonably assure that energy generated by the
eligible net-metering system is consumed by net-metered electric service account(s)
that are actually located in the same geographical location as the eligible net-metering
system. All energy generated from any eligible net-metering system is, and will be
considered, consumed at the meter where the renewable energy resource is interconnected
for valuation purposes. Except for an eligible net-metering system owned by, or operated
on behalf of, a public entity, educational institution, hospital, nonprofit, or multi-municipal
collaborative, or for a commercial or industrial customer through a net-metering financing
arrangement, or except for a community remote net-metering system, all of the net-metered
accounts at the eligible net-metering system site must be the accounts of the same
customer of record and customers are not permitted to enter into agreements or arrangements
to change the name on accounts for the purpose of artificially expanding the eligible
net-metering system site to contiguous sites in an attempt to avoid this restriction.
However, a property owner may change the nature of the metered service at the accounts
at the site to be master metered in the owner’s name, or become the customer of record
for each of the accounts, provided that the owner becoming the customer of record
actually owns the property at which the account is located. As long as the net-metered
accounts meet the requirements set forth in this definition, there is no limit on
the number of accounts that may be net metered within the eligible net-metering system
site.
(8) “Excess renewable net-metering credit” means a credit that applies to an eligible
net-metering system or community remote net-metering system for that portion of the
production of electrical energy beyond one hundred percent (100%) and no greater than
one hundred twenty-five percent (125%), except for any system with a nameplate capacity
equal to or less than twenty-five kilowatts (25 KW) for which excess renewable net-metering
credit applies to all production of electrical energy beyond one hundred percent (100%)
of the renewable self-generator’s own consumption at the eligible net-metering system
site or the sum of the usage of the eligible credit recipient accounts associated
with the community remote net-metering system during the applicable billing period.
For electrical energy produced greater than one hundred percent (100%) of the renewable
self-generator’s own electricity consumption at the eligible net-metering system site
or the sum of the usage of the eligible credit recipient accounts associated with
the community remote net-metering system during the applicable billing period, excess
renewable net-metering credits shall be equal to the wholesale electricity rate, which
is hereby declared to be the ISO-New England energy clearing price. When applying
the ISO-New England energy clearing price to calculate the value of excess renewable
net-metering credits, the electric distribution company, subject to commission approval
and subject to amendment from time to time, may use an annual average, monthly average,
or other time increment and may use Rhode Island zone pricing or other applicable
locational pricing. The commission shall have the authority to make determinations
as to the applicability of this credit to specific generation facilities to the extent
there is any uncertainty or disagreement.
(9) “Farm” shall be defined in accordance with § 44-27-2, except that all buildings associated with the farm shall be eligible for net-metering
credits as long as: (i) The buildings are owned by the same entity operating the farm
or persons associated with operating the farm; and (ii) The buildings are on the same
farmland as the project on either a tract of land contiguous with, or reasonably proximate
to, such farmland or across a public way from such farmland.
(10) “Hospital” means and shall be defined and established as set forth in chapter 17 of title 23.
(11) “Multi-municipal collaborative” means a group of towns and/or cities that enter into
an agreement for the purpose of co-owning a renewable-generation facility or entering
into a financing arrangement pursuant to subsection (15).
(12) “Municipality” means any Rhode Island town or city, including any agency or instrumentality
thereof, with the powers set forth in title 45.
(13) “Net metering” means using electrical energy generated by an eligible net-metering
system for the purpose of self-supplying electrical energy and power at the eligible
net-metering system site, or with respect to a community remote net-metering system,
for the purpose of generating net-metering credits to be applied to the electric bills
of the eligible credit recipients associated with the community net-metering system.
The amount so generated will thereby offset consumption at the eligible net-metering
system site through the netting process established in this chapter, or with respect
to a community remote net-metering system, the amounts generated in excess of that
amount will result in credits being applied to the eligible credit-recipient accounts
associated with the community remote net-metering system.
(14) “Net-metering customer” means a customer of the electric distribution company receiving
and being billed for distribution service whose distribution account(s) are being
net metered.
(15) “Net-metering financing arrangement” means arrangements entered into by a public entity,
educational institution, hospital, nonprofit, multi-municipal collaborative, or a
commercial or industrial customer with a private entity to facilitate the financing
and operation of a net-metering resource, in which the private entity owns and operates
an eligible net-metering resource on behalf of a public entity, educational institution,
hospital, nonprofit, multi-municipal collaborative, or commercial or industrial customer,
where: (i) The eligible net-metering resource is located on property owned or controlled
by the public entity, educational institution, hospital, municipality, multi-municipal
collaborative, or commercial or industrial customer as applicable; and (ii) The production
from the eligible net-metering resource and primary compensation paid by the public
entity, educational institution, hospital, nonprofit, multi-municipal collaborative,
or commercial or industrial customer to the private entity for such production is
directly tied to the consumption of electricity occurring at the designated net-metered
accounts.
(16) “Nonprofit” means a nonprofit corporation as defined and established through chapter 6 of title 7, and shall include religious organizations that are tax exempt pursuant to 26 U.S.C. § 501(d).
(17) “Person” means an individual, firm, corporation, association, partnership, farm, town
or city of the state of Rhode Island, multi-municipal collaborative, or the state
of Rhode Island or any department of the state government, governmental agency, or
public instrumentality of the state.
(18) “Preferred site” means a location for a renewable energy system that has had prior
development, including, but not limited to: landfills, gravel pits and quarries, highway
and major road median strips, brownfields, superfund sites, parking lots or sites
that are designated appropriate for carports, and all rooftops including, but not
limited to, residential, commercial, industrial, and municipal buildings.
(19) “Project” means a distinct installation of an eligible net-metering system or a community
remote net-metering system. An installation will be considered distinct if it is installed
in a different location, or at a different time, or involves a different type of renewable
energy. Subject to the safe-harbor provisions in § 39-26.4-3(a)(1), new and distinct projects cannot be located on adjoining parcels of land within
core forests, except for preferred sites.
(20) “Public entity” means the federal government, the state of Rhode Island, municipalities,
wastewater treatment facilities, public transit agencies, or any water distributing
plant or system employed for the distribution of water to the consuming public within
this state including the water supply board of the city of Providence.
(21) “Public entity net-metering system” means a system generating renewable energy at
a property owned or controlled by the public entity that is participating in a net-metering
financing arrangement where the public entity has designated accounts in its name
to receive net-metering credits.
(22) “Renewable net-metering credit” means a credit that applies to an eligible net-metering
system or a community remote net-metering system up to one hundred percent (100%)
of either the renewable self-generator’s usage at the eligible net-metering system
site or the sum of the usage of the eligible credit-recipient accounts associated
with the community remote net-metering system over the applicable billing period.
This credit shall be equal to the total kilowatt hours of electrical energy generated
up to the amount consumed on-site, and/or generated up to the sum of the eligible
credit-recipient account usage during the billing period multiplied by the sum of
the distribution company’s:
(i) Last resort service kilowatt-hour charge for the rate class applicable to the net-metering
customer, except that for remote public entity and multi-municipality collaborative
net-metering systems that submit an application for an interconnection study on or
after July 1, 2017, and community remote net-metering systems, the last resort service
kilowatt-hour charge shall be net of the renewable energy standard charge or credit;
(ii) Distribution kilowatt-hour charge;
(iii) Transmission kilowatt-hour charge; and
(iv) Transition kilowatt-hour charge.
For projects after April 15, 2023, subject to the allowable two hundred seventy-five
megawatts alternating current (275 MWac), under § 39-26.4-3(a)(1)(vi), the credit shall be reduced by twenty percent (20%).
Notwithstanding the foregoing, except for systems that have requested an interconnection
study for which payment has been received by the distribution company, or if an interconnection
study is not required, a completed and paid interconnection application, by December
31, 2018, the renewable net-metering credit for all remote public entity and multi-municipal
collaborative net-metering systems shall not include the distribution kilowatt-hour
charge commencing on January 1, 2060.
(23) “Renewable self-generator” means an electric distribution service customer of record
for the eligible net-metering system or community remote net-metering system at the
eligible net-metering system site which system is primarily designed to produce electrical
energy for consumption by that same customer at its distribution service account(s),
and/or, with respect to community remote net-metering systems, electrical energy which
generates net-metering credits to be applied to offset the eligible credit-recipient
account usage.
(24) “Third party” means and includes any person or entity, other than the renewable self-generator,
who or that owns or operates the eligible net-metering system or community remote
net-metering system on the eligible net-metering system site for the benefit of the
renewable self-generator.
(25) “Third-party, net-metering financing arrangement” means the financing of eligible
net-metering systems or community remote net-metering systems through lease arrangements
or power/credit purchase agreements between a third party and renewable self-generator,
except for those entities under a public entity net-metering financing arrangement.
A third party engaged in providing financing arrangements related to such net-metering
systems with a public or private entity is not a public utility as defined in § 39-1-2.
P.L. 2011, ch. 134, § 2; P.L. 2011, ch. 147, § 2; P.L. 2014, ch. 493, § 1; P.L. 2014,
ch. 524, § 1; P.L. 2016, ch. 149, § 3; P.L. 2016, ch. 163, § 3; P.L. 2017, ch. 188,
§ 1; P.L. 2017, ch. 306, § 1; P.L. 2017, ch. 451, § 17; P.L. 2020, ch. 79, art. 1,
§ 19; P.L. 2023, ch. 300, § 1, effective June 24, 2023; P.L. 2023, ch. 301, § 1, effective
June 24, 2023; P.L. 2024, ch. 83, § 1, effective June 12, 2024; P.L. 2024, ch. 84,
§ 1, effective June 12, 2024; P.L. 2025, ch. 256, § 1, effective June 27, 2025; P.L.
2025, ch. 269, § 1, effective June 27, 2025.