San José Municipal Code § 27.30.100 Change orders.
27.30.100 - Change orders.
A Change Order that modifies the scope of work must comply with either one of the following requirements:
A. The modification is needed to properly complete the construction work as contemplated by the City at the time the City awarded the Public Works Contract or work order; or
B. The modification meets each of the following requirements:
1. Its cost is not excessive relative to the cost of the Public Works Project to which it is being added;
2. It involves work on the same worksite as the Public Works Project to which it is being added and is related to that Public Works Project;
3. It is the most efficient way of completing the work reflected in the modification;
4. The Contractor has the expertise to perform the modification; and
5. The Contractor will perform the modification at a reasonable cost.
(Ord. 30308.)