Indianapolis-Marion County Revised Code § 511-521 Permit fees.
Sec. 511-521. - Permit fees.
(a) Purpose. This section 511-521 establishes permit fees due to the office at levels necessary to continue the process of developing and administering for Marion County the permit program required by Title V of the Clean Air Act of 1990. This section 511-521 and section 511-523 also establish all other types of permit fees due to the office.
(b) Application fees. The office shall collect an application fee of one hundred dollars ($100.00) whenever a person submits an application to:
(1) Obtain a construction permit;
(2) Obtain an operating permit;
(3) Obtain an asbestos abatement permit;
(4) Obtain an emission credit permit;
(5) Change the name of the permittee on a permit issued by the administrator;
(6) Transfer a permit to a new owner of the air contaminant emitter subject to a permit;
(7) The application fee for (1) through (6) above is waived if:
a. A permittee has already obtained a construction permit, and is submitting an application for an initial operating permit;
b. A permittee is renewing an operating permit;
c. A permittee is renewing an asbestos abatement permit;
d. A permittee is renewing an emission credit permit;
e. A permittee has already obtained an operating permit and is submitting an application for an initial Title V operating permit.
(8) If a permittee is applying simultaneously for permits for several facilities at the same source, the permittee shall pay a single application fee.
(c) Construction permits. The office shall collect a fee for reviewing plans and issuing a construction permit.
(1) Base fees.
a. The fee for each facility with potential emissions of any one (1) pollutant less than ten (10) tons per year shall be eight hundred dollars ($800.00).
b. The fee for each facility with potential emissions of any one (1) pollutant of ten (10) tons per year or greater but less than twenty (20) tons per year shall be twelve hundred dollars ($1,200.00).
c. The fee for each facility with potential emissions for any one (1) pollutant of twenty (20) tons per year or greater but less than twenty-five (25) tons per year shall be one thousand eight hundred dollars ($1,800.00).
d. The fee for each facility with potential emissions of any one (1) pollutant of twenty-five (25) tons per year or greater but less than one hundred (100) tons per year shall be four thousand five hundred dollars ($4,500.00).
e. The fee for each facility with potential emissions of any one (1) pollutant of one hundred (100) tons per year or greater shall be six thousand five hundred dollars ($6,500.00).
f. Facilities which elect to be subject to board Regulation IX-2 (Enhanced New Source Review) shall not be subject to the fees in subsections a. through e., but instead shall pay a fee of three thousand five hundred dollars ($3,500.00).
(2) Additional fees. In addition to fees collected under paragraph (1) above, the office shall collect all applicable fees specified in a. through g. below.
a. The fee for each review involving a facility or facilities subject to federal, state, or local new source performance standards shall be five hundred dollars ($500.00) per standard.
b. The fee for each review involving a facility or facilities subject to federal, state, and local national emission standards for hazardous air pollutants shall be five hundred dollars ($500.00) per pollutant.
c. The fee for each public notice required as a part of a construction permit review shall be three hundred dollars ($300.00).
d. The fee for each facility subject to best available control technology (BACT), maximum achievable control technology (MACT) or lowest achievable emission rate (LAER) shall be three thousand dollars ($3,000.00) per pollutant for each applicable pollutant.
e. The fee for each facility subject to generally achievable control technology (GACT) shall be one thousand dollars ($1,000.00) per pollutant for each applicable pollutant.
f. The fee for each facility subject to modeling analysis shall be four thousand dollars ($4,000.00) per pollutant for each applicable pollutant, except where such analysis is performed by the office, in which case the fee shall be six thousand dollars ($6,000.00) per pollutant for each applicable pollutant.
g. The fee for each facility which has federally enforceable permit restrictions to allow the facility to be exempt from federal prevention of significant deterioration or nonattainment new source review requirements shall be one thousand dollars ($1,000.00) per permit.
(d) Operating permits. This part (d) shall not apply to gasoline dispensing facility operating permits and sources which are required to pay Title V operating permit fees pursuant to subsection (e) or opt-out fees pursuant to subsection (f).
(1) Initial and annual fee. The office shall collect a fee for the initial issuance of an operating permit and an annual administrative fee for each succeeding year for the maintenance and renewal of an operating permit. The total fee shall be the per facility fee specified in subpart (2) below, plus the source category fee or fees specified in subpart (3) below, if applicable. The total fee, exclusive of the source category fees in subparts (3)c. and (3)d., shall not exceed three thousand three hundred dollars ($3,300.00).
(2) Per facility fees.
a. The fee for each facility with allowable emissions of any one (1) pollutant less than twenty-five (25) tons per year shall be two hundred fifty dollars ($250.00).
b. The fee for each facility with allowable emissions of any one (1) pollutant of twenty-five (25) tons per year or greater, but less than one hundred (100) tons per year, shall be nine hundred fifty dollars ($950.00).
(3) Source category fees.
a. The fee for each source with actual emissions of seventy-five (75) tons per year or greater shall be one thousand five hundred dollars ($1,500.00).
b. The fee for each source with actual emissions of twenty-five (25) tons per year or greater but less than seventy-five (75) tons per year shall be one thousand dollars ($1,000.00).
c. The fee for each source subject to federal, state or local national emission standards for hazardous air pollutants shall be two thousand dollars ($2,000.00).
d. The fee for each source subject to federal, state or local new source performance standards shall be two thousand dollars ($2,000.00) per standard.
(4) Annual adjustment. The fees set forth in subsection (d)(2) and (3)a. and b. shall automatically be adjusted annually by the Consumer Price Index (CPI) using the revision of the CPI which is most consistent with the CPI for the preceding year.
(e) Fees for 1995, 1996 and subsequent years for sources required to obtain Title V operating permits.
(1) Beginning in calendar year 1995, sources which, according to 40 CFR § 70.3 and applicable state and local regulations, will be required to obtain a Title V operating permit under a United States Environmental Protection Agency approved Title V operating permit program applicable to Marion County, shall pay an annual fee as set forth in subsection (2) of this section.
(2) A source's annual fee shall be calculated as follows:
a. Each source shall pay a base fee of two thousand five hundred dollars ($2,500.00) and shall pay an additional fee of thirty-seven dollars ($37.00) per ton for each ton of regulated pollutant emitted, provided that, no source shall pay more than one hundred fifty thousand dollars ($150,000.00), or, if a source emits more than one hundred (100) tons per year of NOx and more than one hundred (100) tons per year of VOC and is located in an area designated as serious or severe nonattainment for ozone in accordance with the Clean Air Act of 1990, the source shall pay no more than two hundred thousand dollars ($200,000.00). The administrator shall exclude from the fee calculation the amount of each source's actual emissions of any regulated pollutant that the source emits in excess of four thousand (4,000) tons per year. As used in this section, "regulated pollutant" shall have the meaning set forth in board Regulation 2-7, Section 1.
b. During the years 1995 through 1999 inclusive, any affected unit under Section 404 of the Clean Air Act of 1990 shall be exempted from the fees established under subsection (2)(i) and shall instead pay the following: Fifty thousand dollars ($50,000.00) shall be submitted upon billing for an electric power plant containing a Phase I affected unit, as identified in Table A of Section 404 of the Clean Air Act of 1990 or for a substitution unit as determined by U.S. EPA in accordance with Section 404 of the Clean Air Act of 1990.
c. Municipal solid waste incinerators with a capacity greater than two hundred fifty (250) tons per day shall be exempted from the fees established under subsection (2)(i) and shall instead pay the following: Twenty-five thousand dollars ($25,000.00) shall be submitted upon billing.
d. In addition to the fees established under subsection (2)(i), coke oven batteries shall pay the actual cost incurred in performing inspections required by 40 CFR § 63, Subpart L, not to exceed one hundred twenty-five thousand dollars ($125,000.00). As used in this subsection, "coke oven battery" shall have the meaning set forth in board Regulation 1.
(3) The annual emission statement submitted during the previous calendar year as required by 326 IAC 2-6 or an equivalent board regulation shall be the basis for determining total tons of actual emissions of each regulated pollutant. If an annual emission statement is not required or if more information is needed to accurately determine a source's emissions for a regulated pollutant, the administrator may require that the source report annual emissions using procedures acceptable to the administrator.
(4) After review of a source's annual emission statement and all other available information, the administrator shall calculate the total emissions to be included in the fee. No source shall be required to pay more than a single dollar-per-ton fee during any billing period for any one (1) ton of pollutant emitted. If the source disputes the calculation of total actual emissions used to determine the fee, the source shall remit the total fee billed, less the amount attributable to the disputed emissions and shall provide calculations or other data supporting the disputed emissions within thirty (30) days of receipt of the billing. The administrator shall review the information submitted and make a final determination of the total fee due. The source shall pay any remaining fee due within fifteen (15) days of receipt of the revised billing.
(5) The fees set forth in section (2)a. shall automatically be adjusted annually by the Consumer Price Index (CPI) using the revision of the CPI which is most consistent with the CPI for the preceding calendar year.
(6) Beginning in 1995, the administrator shall present a report to the board by August 15 of each calendar year. The report shall include the following information regarding the Title V permit program for the previous year:
a. The number of sources in Marion County required to obtain Title V operating permits, including those choosing to opt-out of the requirement to obtain a Title V operating permit by accepting in a federally enforceable permit physical or operational limits on the source's capacity to emit air pollutants;
b. The number of such permit applications received by the office;
c. The number and timeliness of final permit actions taken by the office;
d. The adequacy of the fees collected by the office to fund the Title V operating permit program;
e. An accounting of the monies deposited in the Air Pollution Control Program Fund, distinguishing fees used to fund the Title V operating permit program from other monies.
Based upon the report, the board may recommend that this section be amended to revise the fees to ensure that the fees collected are sufficient to cover the direct and indirect costs of the Title V operating permit program, and are used for no other purpose.
(7) Pursuant to an enforceable written agreement with the Indiana Department of Environmental Management (IDEM) documenting the office's and IDEM's relative Title V operating permit program roles and responsibilities, a portion of the fees collected by the division may be transmitted to IDEM to recover costs incurred by IDEM in connection with Marion County Title V operating permit program responsibilities performed by IDEM.
(f) Fees for sources "opting-out" of requirement to obtain Title V operating permits. Notwithstanding section (e), sources which according to 40 CFR § 70.3 and applicable state and local regulations will be required to obtain a Title V operating permit under a United States Environmental Protection Agency approved Title V operating permit program applicable to Marion County may opt-out of the requirements to obtain a Title V operating permit and to pay the Title V fees set forth in section (e) by: 1) accepting in a federally enforceable state or local operating permit ("FESOP") limits on the source's capacity to emit air pollutants, or 2) electing to be subject to federally enforceable state or local rules limiting the source's capacity to emit air pollutants ("Source Specific Operating Agreements"). The board shall adopt regulations establishing procedures for obtaining FESOP permits and Source Specific Operating Agreements. Pursuant to an enforceable written agreement with the Indiana Department of Environmental Management (IDEM) documenting the office's and IDEM's relative Title V operating permit program rules and responsibilities, a portion of the fees collected by the office may be transmitted to IDEM to recover costs incurred by IDEM in connection with Marion County Title V operating permit program responsibilities performed by IDEM.
(1) FESOP permit fees. An application fee of three thousand five hundred dollars ($3,500.00) and an annual administrative fee of one thousand five hundred dollars ($1,500.00) shall be due to the office from sources which file FESOP applications and are issued FESOP permits as set forth in the FESOP regulation adopted by the board. A source's obligation to pay operating permit fees set forth in section (d) or Title V operating permit fees set forth in section (e) and/or (f) pending issuance of the FESOP permit, or upon denial of the FESOP application, shall be as set forth in such regulations.
(2) Source specific operating agreement fees. An application fee of five hundred dollars ($500.00) shall be due to the office from sources electing to be subject to the source specific operating agreement regulation adopted by the board.
(g) Gasoline dispensing facility operating permits. The office shall collect a fee for the initial issuance of a gasoline dispensing facility operating permit and an annual administrative fee for each succeeding year for the maintenance and renewal of an operating permit. As used in this subpart "gasoline dispensing facility" shall have the meaning set forth in board Regulation 8-4-1, Section 6.
(1) The fee for each gasoline dispensing facility with allowable emissions of any one (1) pollutant less than twenty-five (25) tons per year shall be seventy-five dollars ($75.00).
(2) The fee for each gasoline dispensing facility with allowable emissions of any one (1) pollutant of twenty-five (25) tons or greater per year shall be two hundred dollars ($200.00).
(h) Emission credit permits. The office shall collect a fee of five hundred dollars ($500.00) for the initial issuance of an emission credit permit and an annual administrative fee for each succeeding year of two hundred dollars ($200.00) for the maintenance of an emission credit permit.
(i) Asbestos abatement permits. The office shall collect a fee of four hundred fifty dollars ($450.00) for the initial issuance of an asbestos abatement permit and an annual administrative fee for each succeeding year of four hundred fifty dollars ($450.00) for the maintenance and renewal of an asbestos abatement permit.
(Code 1975, § 4-52; G.O. 150, 1999, § 6; G.O. 15, 2001, § 44)