§ 14-02 — Where Building Permit Not Required for Project

New York City Administrative Code (current through L.L. 2026/147, enacted September 12, 2026, and amendments effective through October 10, 2026) · 19 RCNY § 14-02

Corpus is an independent public-information project, not the official City of New York website. Stable reference: corpuslaw.us/code/acd9077b-b9b0-4935-a0bd-c1b7a9b27035

§ 14-02 Where Building Permit Not Required for Project.

Where construction work that was the subject of an application for a certificate of eligibility does not require a building permit or is to be performed under authority of an open permit issued by the Department of Buildings, a notarized letter from the project's architect or engineer notifying the Department of this fact must be filed within 30 calendar days. The date of commencement indicated in the letter will be the project's effective date.

Ask a question about New York law

Corpus searches the New York sections it holds and shows the ones that match, with their citations. Free, no sign-in.