Sec. 42-263. - Design requirements.
Grading, erosion control practices, sediment control practices, and waterway crossings shall meet the design criteria set forth in the Stormwater Design Manual, and shall be adequate to prevent transportation of sediment from the site to the satisfaction of the City of Olive Branch's AEA.
(a) Clearing and grading. Clearing and grading of natural resources, such as forests and wetlands, shall not be permitted, except when in compliance with all other chapters of this article.
Clearing techniques that retain natural vegetation and retain natural drainage patterns, as described in Stormwater Design Manual, shall be used to the satisfaction of the AEA.
Phasing may be required on all Sites disturbing greater than 20 acres, with the size of each phase to be established at plan review and as approved by the AEA.
Clearing, except that necessary to establish sediment control devices, shall not begin until all sediment control devices have been installed and have been stabilized.
Cut and fill slopes shall be no steeper than 2:1, except as approved by the AEA to meet other community or environmental objectives.
(b) Erosion control. Soil must be stabilized within five days of clearing or inactivity in construction.
If vegetative erosion control methods, such as seeding, have not become established within two weeks, the AEA may require that the site be revegetated, or that a nonvegetative option be employed. The following criteria shall apply to revegetation efforts:
(1) Reseeding must be done with an annual or perennial cover crop accompanied by placement of straw mulch or its equivalent of sufficient coverage to control erosion until such time as the cover crop is established over 90 percent of the seeded area.
(2) Replanting with native woody and herbaceous vegetation must be accompanied by placement of straw mulch or its equivalent of sufficient coverage to control erosion until the plantings are established and are capable of controlling erosion.
(3) Any area of revegetation must exhibit survival of a minimum of 75 percent of the cover crop throughout the year immediately following revegetation. Revegetation must be repeated in successive years until the minimum 75 percent survival for one year is achieved.
On steep slopes or in drainage ways, special techniques that meet the design criteria outlined in Stormwater Design Manual shall be used to ensure stabilization.
Soil stockpiles must be stabilized or covered at the end of each workday.
At the close of the construction season or any termination of construction greater than two weeks, the entire site must be stabilized, using a heavy mulch layer, or another method that does not require germination to control erosion.
Techniques shall be employed to prevent the blowing of dust or sediment from the site.
Techniques that divert upland runoff past disturbed slopes shall be employed.
(c) Sediment controls. Sediment controls shall be provided in the form of settling basins or sediment traps or tanks, and perimeter controls.
Where possible, settling basins shall be designed in a manner that allows adaptation to provide long-term stormwater management.
Adjacent properties shall be protected by the use of a vegetated buffer strip, in combination with perimeter controls.
(d) Waterways and watercourses. When a wet watercourse must be crossed regularly during construction, a temporary stream crossing shall be provided, and an approval obtained from the AEA.
When in-channel work is conducted, the channel shall be stabilized before, during and after work.
All on-site stormwater conveyance channels shall be designed according to the criteria outlined in Stormwater Design Manual.
Stabilization adequate to prevent erosion must be provided at the outlets of all pipes and paved channels.
(e) Construction site access. A temporary access road shall be provided at all sites.
Other measures may be required at the discretion of the AEA in order to ensure that construction vehicles do not track sediment onto public streets, or washed into storm drains.
(Ord. of 1-21-2020(1))