33.550.200 Floor Area Ratio
A.
Maximum FAR. The maximum floor area ratio is 2 to 1 for all uses.
B.
FAR bonus options. The following bonus options are allowed in the commercial/mixed use
and residential zones. Adjustments to this Subsection, or to the amount of maximum floor
area allowed through the bonuses in this Subsection, are prohibited:
1.
Maximum increase in FAR. An increase in FAR through the use of bonuses of more
than 0.5 to 1 is prohibited.
2.
FAR bonus options:
a.
Mandatory inclusionary housing bonus option. Bonus FAR is allowed for
development that triggers 33.245, Inclusionary Housing. The amount of bonus
floor area earned is an amount equal to the net building area of the building that
triggers 33.245. To qualify for this bonus, the applicant must provide a letter
from the Portland Housing Bureau certifying that the regulations of 33.245 have
been met.
b.
Voluntary inclusionary housing. Bonus FAR is allowed when one of the following
voluntary bonus options is met:
(1) Bonus FAR is allowed for projects that voluntarily comply with the standards
of 33.245.040 and 33.245.050. The amount of bonus floor area allowed is an
amount equal to the net building area of the building that complies with
33.245.040 and .050. To qualify for this bonus, the applicant must provide a
letter from the Portland Housing Bureau certifying that the regulations of
33.245 have been met. The letter is required to be submitted before a
building permit can be issued for development, but is not required in order
to apply for a land use review; or
(2) Bonus FAR is allowed in exchange for payment into the Affordable Housing
Fund. For each square foot purchased a fee must be paid to the Portland
Housing Bureau (PHB). The Portland Housing Bureau collects and
administers the Affordable Housing Fund, and PHB determines the fee per
square foot and updates the fee at least every three years. The fee schedule
is available from Portland Permitting & Development. To qualify for this
bonus option, the applicant must provide a letter from the PHB
documenting the amount that has been contributed to the AHF. The letter is
required to be submitted before a building permit can be issued for the
development, but it is not required in order to apply for a land use review.