§ 21.16.080 — Permit—Application—Authority of the Director of Seattle Public Utilities

Seattle Municipal Code (Supp. No. 44: codified through Ordinance No. 127459, passed June 30, 2026) · Seattle Mun. Code § 21.16.080

Corpus is an independent public-information project, not the official City of Seattle website. Stable reference: corpuslaw.us/code/afdbf32d-036a-4bb0-93f0-f1b423151ca2

21.16.080 - Permit—Application—Authority of the Director of Seattle Public Utilities.

A. For side sewer work in a public place, a permit shall only be issued to a registered side sewer contractor, unless authorized by the Director of Seattle Public Utilities. B. For side sewer work in other than a public place, a permit may be issued to the owner or occupant of the property or agent thereof. C. Application for the permit required by this section shall be filed with the Director of Seattle Public Utilities with the following: 1. The name, address and telephone number of the applicant; 2. Name, mailing address, and telephone number of the property owner; 3. Address of the property to be served; 4. A scale drawing showing the location of all structures on the property, dimensions of the structures, and the location of all existing and proposed utilities, including side sewers; 5. Purposes for which all structures are to be used; 6. Proof that all necessary permits have been obtained in conjunction with or prior to issuance of the side sewer permit; 7. Proof that all necessary easements, releases, and/or permissions to connect have been obtained and recorded with the King County Department of Records and Elections; 8. Proof of payment of all permit fees and other charges required by Section 21.16.070. D. The Director of Seattle Public Utilities may change or modify the application and designate the manner and place where the side sewer shall connect to the public sewer system, may specify the material, size and grade of the side sewer, and determine whether or not a permit shall be granted. The Director of Seattle Public Utilities may require the applicant to furnish plans prepared and stamped by a professional engineer, licensed in The State of Washington. E. Notwithstanding any other provisions of this Chapter 21.16.080, the Director of Seattle Public Utilities may refuse, until the condition is corrected, to issue a permit for work in a public place to a registered side sewer contractor for any of the following conditions: 1. Failure to pay within 60 days any bill for work performed by the City for which the owner or contractor is liable; 2. Failure to maintain the insurance or the bond required by Section 21.16.060; 3. Failure to comply with a notice posted pursuant to Section 21.16.358; 4. Failure to have a current business license issued under Chapter 6.208; or 5. Failure to have a current Washington State Contractor's license. F. Notwithstanding any other provisions of this chapter, the Director of Seattle Public Utilities may refuse, until the condition is corrected, to issue a permit for work in any place other than a public place as provided for in subsection E of this section to an applicant for any of the following conditions: 1. Failure to comply with a notice posted pursuant to Section 21.16.358; 2. Failure to pay within 60 days any bill for work performed by the City for which the owner or contractor is liable.

(Ord. 124963, § 12, 2015; Ord. 123494, § 12, 2010; Ord. 122036, § 7, 2006; Ord. 118396, § 93, 1996; Ord. 114298, § 8, 1988; Ord. 97016, § 7, 1968.)

Ask a question about Seattle law

Corpus searches the Seattle sections it holds and shows the ones that match, with their citations. Free, no sign-in.