For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 4-310 — Installations serviced by multiple sources

Official Code of the City of Clarksville (Supp. No. 110: codified through Ordinance No. 64-2025-26, enacted May 7, 2026) · Clarksville City Code § 4-310

Corpus is an independent public-information project, not the official City of Clarksville website. Stable reference: corpuslaw.us/code/b5d04953-4b53-4adb-a902-0dc25d8d5df0

Sec. 4-310. - Installations serviced by multiple sources.

Interconnected generation. Electric generators of any type and size, interconnected to CDE Lightband's (CDE) electric grid in any way, shape, form, fashion, or means, including wind, solar, fuel cell, reciprocating engine, hydro, and other similar electric generation devices, are required by CDE to install a load-break AC disconnect or transfer switch (Switch) between CDE facilities and the interconnected customer's equipment. Such switch must be installed on the customer's side of the electrical interconnection with CDE and must be able to isolate the generation source from CDE's electric grid, a) automatically when source power from CDE is lost and, b) manually when needed for emergencies, to perform maintenance, to assist in the restoration of service, or any other time/event deemed appropriate/necessary by CDE. The switch must be, a) accessible to CDE personnel at all times, b) located in close proximity to CDE's point of delivery, c) able to provide a clear visible open point of disconnection and a clear visible indication of switch position, d) have padlock provisions for locking the switch in the open position and, e) labeled "Generator Disconnect Switch" or "Generator Transfer Switch". Failure by customer to notify CDE of customer's generator installation, or failure by customer to install the switch according to the specifications listed herein, will result in immediate disconnection of customer's electric service by CDE. Electric service will be reconnected by CDE when the switch is installed and inspected/approved by the City of Clarksville, TN, Building and Codes Department. Transfer equipment associated with installations serviced by alternate sources of supply shall be equipped with all the necessary equipment to prevent back-feed of power onto the power supplier's system when the power supplier's system is not energized by its own source of power. Protective equipment and installation of equipment to prevent back-feed shall be approved by the power supplier.

(Ord. No. 12-2011-12, § 1, 9-1-11; Ord. No. 64-2016-17, § 6, 6-1-17; Ord. No. 40-2020-21, § 6, 12-3-20)

Ask a question about Clarksville law

Corpus searches the Clarksville sections it holds and shows the ones that match, with their citations. Free, no sign-in.