Sec. 28-61. - Contracts for construction, reconstruction and remodeling—Responsive and nonresponsive bids or proposals.

(a) Responsive; compliance with requirements. If the low monetary bid or competitive selection process proposal subject to a participation goal meets such goal or shows adequate good faith efforts as set out in sections 28-60 or 28-64, then the director shall notify the department head to regard the bid or proposal as responsive as to compliance with this article III and its divisions. (b) Failure to meet requirements. If a bid or proposal subject to a participation goal does not meet such goal or show good faith efforts as set out in sections 28-60 or 28-64, or provide timely information as set out in section 28-59, then the director shall notify the department head to regard the bid or proposal as nonresponsive, and such determination shall result in no further consideration by the city or private owner of the bid or proposal. (c) Good faith efforts—Informal meeting. If the director finds inadequacies in a bidder or proposer's demonstration of good faith efforts under section 28-60, the director will provide written notice of such inadequacies to the bidder or proposer, consistent with section 28-61 (b), above, and the appropriate department head of bid or proposal nonresponsiveness. Within two (2) business days from the date that the city notifies the bidder or proposer of the inadequacies of its demonstration of good faith efforts, the bidder or proposer may request an informal meeting with the director. Such informal meeting shall be scheduled by the director. All deficiencies in good faith efforts shall be explained to the bidder or proposer at such informal meeting. Within twenty-four (24) hours after the informal meeting, the bidder or proposer shall be allowed to submit additional information or to clarify the original good faith efforts. The director will at no time, however, allow additional subcontractors, joint venturers, suppliers, manufacturers, manufacturer's representatives or brokers that may later be added to the contract or to the original MWBE participation submitted at the time of the bid or date of proposal in the case of a competitive selection process to be counted toward meeting of the participation goal. After this informal meeting, the director will: (1) Determine whether the bidder or proposal will be responsive or nonresponsive; (2) Make the notification as stated in subsection (b) above, as applicable; and (3) Provide written notice to the bidder or proposer of the director's final determination.

(Ord. No. 286-20, § 2, 4-13-20)