Contracts; changes authorized.
Neb. Rev. Stat. § 39-2821
in effect39-2821. Contracts; changes authorized.
A design-build contract, a progressive design-build contract, and a construction manager-general contractor contract may be conditioned upon later refinements in scope and price and may permit the contracting agency in agreement with the design-builder, progressive design-builder, or construction manager to make changes in the project without invalidating the contract.
Laws 2016, LB960, § 21; Laws 2019, LB583, § 15; Laws 2022, LB1016, § 10.
Source: Nebraska Legislature (nebraskalegislature.gov)URL: https://nebraskalegislature.gov/laws/statutes.php?statute=39-2821Fetched: 10/20/2026