§ 13.03.0620 — Opening Street – Requirements
Spokane Municipal Code; partial · SMC 13.03.0620 · Effective
Corpus is an independent public-information project, not the official City of Spokane website. Stable reference: corpuslaw.us/code/bd578697-6299-4732-9053-153fa338cce2
Section 13.03.0620 Opening Street – Requirements
A. When a sewer is constructed requiring the opening of the street, the paving and earth must be deposited in a manner that will cause the least inconvenience to the public and provide for free drainage along the gutter. 1. One-half of the street must be kept clear for the passage of vehicles and bridgeways must be provided on sidewalks for foot passengers. 2. In refilling the pipe zone and trench, refer to Design Standard A-1 as prescribed in regulations, or as required by the Wastewater Superintendent, to prevent settlement. B. As soon as any such drain or sewer is completed, the paving, curbing and sidewalk must be restored to a condition equal to or exceeding that existing previous to the excavation and all rubbish and surplus earth must be immediately removed. C. On arterial streets and avenues, traffic is to be routed and controlled and construction performed as may be directed by the Director of the Development Services Center or the Street Director.
Date Passed: Monday, December 8, 2025 Effective Date: Sunday, January 18, 2026 ORD C36776 Section 40
Ask a question about Spokane law
Corpus searches the Spokane sections it holds and shows the ones that match, with their citations. Free, no sign-in.