Action on application.
R.I. Gen. Laws § 23-27.3-114.1
in effect23-27.3-114.1. Action on application.
(a) The building official shall examine or cause to be examined all applications for permits
and amendments thereto within fifteen (15) days after filing. Before a permit is granted
for the excavation or for the erection of any building or structure, a written statement
shall be furnished by the owner from a town or city engineer as to the established
grades. If the application or plans do not conform to the requirements of this code
or of all applicable laws, the building official shall reject the application citing
the specific sections of this code or applicable law upon which the rejection is based.
If the building official is satisfied that the proposed work conforms to the requirements
of this code and all laws applicable thereto, he or she shall issue a permit.
(b) In cases where the permit application is for the construction of a new residential
dwelling occupied by one, two (2), and/or three (3) families, the building official
shall reject the application or issue the permit within forty-five (45) calendar days
after the filing of the application. If after forty-five (45) calendar days the application
has not been either rejected or a permit issued, the permit fee shall be reduced by
fifty percent (50%). The review period shall begin on the date when the application
is filed with the building official and shall include any actions on the application
required by subsection (a) herein, subsection 23-28.1-2(b)(2) and 23-28.1-6 and actions by any other departments with authority over the issuance of the permit.
(c) In cases where the permit application is for the rehabilitation of an existing residential
dwelling occupied by one, two (2), and/or three (3) families and affecting not more
than fifty percent (50%) of the square footage of the original dwelling, the building
official shall reject the application or issue the permit within fifteen (15) calendar
days after the filing of the application. If after fifteen (15) calendar days the
application has not been either rejected or a permit issued, the permit fee shall
be reduced by fifty percent (50%). The provisions of this subsection shall apply to
actions by other departments with authority over the issuance of the permit except
in cases where the permit application requires plan review under §§ 23-28.1-2(b)(2) and 23-28.1-6.
(d) In cases where the permit application is for the rehabilitation of an existing residential
dwelling occupied by one, two (2), and/or three (3) families and affecting more than
fifty percent (50%) of the square footage of the original dwelling, the building official
shall reject the application or issue the permit within forty-five (45) calendar days
after the filing of the application. If, after forty-five (45) calendar days, the
application has not been either rejected or a permit issued, the permit fee shall
be reduced by fifty percent (50%). The provisions of this subsection shall apply to
actions by other departments with authority over the issuance of the permit except
in cases where the permit application requires plan review under sections 23-28.1-2(b)(2) and 23-28.1-6.
(e) In cases where the permit application is for the construction of a new or existing
light commercial building affecting not more than fifty thousand square feet (50,000
sq ft), the building official shall reject the application or issue the permit within
forty-five (45) calendar days after the filing of the application. If, after forty-five
(45) calendar days, the application has not been either rejected or a permit issued,
the permit fee shall be reduced by fifty percent (50%). The provisions of this subsection
shall apply to actions by other departments with authority over the issuance of the
permit except in cases where the permit application requires plan review under sections 23-28.1-2(b)(2) and 23-28.1-6.
(f) If an application requires access by driveway to a state highway or state highway
right of way, or the placement or alteration of curbs, or the connecting to, pumping
or draining water to, the state highway drainage system, or making any alteration
to the state highway system, a physical alteration permit shall first be obtained
from the director of the department of transportation pursuant to rules and regulations
promulgated under §§ 24-8-9, 24-8-33 and 24-8-34. The issuance of a physical alteration permit shall be a requirement for issuance
of a building permit; however, the lack of a physical alteration permit shall not
be cause for a building official to delay examination of the building permit application.
The director of the department of transportation shall respond within thirty (30)
business days; provided, however, the director of the department of transportation
may extend the timeline for unusual circumstances or for complex projects.
P.L. 1976, ch. 256, § 1; P.L. 1992, ch. 401, § 1; P.L. 2007, ch. 159, § 1; P.L. 2007,
ch. 275, § 1; P.L. 2008, ch. 301, § 1; P.L. 2008, ch. 425, § 1; P.L. 2008, ch. 475,
§ 71; P.L. 2011, ch. 174, § 1; P.L. 2011, ch. 323, § 1; P.L. 2012, ch. 220, § 1; P.L.
2012, ch. 229, § 1.
Source: State of Rhode Island General Assembly (rilegislature.gov)URL: https://webserver.rilegislature.gov/Statutes/TITLE23/23-27.3/23-2/23-27.3-114.1.htmFetched: 10/20/2026