Austin City Code § 25-11-111 BUILDING PERMIT INSPECTIONS.
§ 25-11-111 - BUILDING PERMIT INSPECTIONS.
(A) The owner or the owner's general contractor must obtain each building permit inspection described in this section, if applicable.
(B) Electrical, plumbing, and mechanical inspections may be requested only by the contractor authorized by the permit to perform the work.
(C) The building official may require the following inspections before issuing a certificate of occupancy:
(1) structural inspections, including layout, foundation, framing, and wallboard inspections;
(2) concrete inspections, including sidewalk pre-pour and driveway pre-pour inspections;
(3) electrical inspections, including slab and rough inspections;
(4) mechanical inspections, including rough and vent inspections;
(5) plumbing inspections, including rough, copper, top out, gas, wastewater, and fire line inspections;
(6) fire inspections, including access and water supply and system rough-in inspections;
(7) energy inspections, including insulation and infiltration inspections; and
(8) final inspections, including electric, plumbing, mechanical, energy, concrete, building, fire, health,landscape, and drainage/engineering inspections.
(D) The building official may require additional inspections if the building official determines that a hazardous condition exists. An inspection under this subsection must be performed by an inspector approved by the building official.
Source: Section 13-1-902; Ord. 990225-70; Ord. 031211-11.