Sec. 8-2096. - REIMBURSEMENT PROCEDURES FOR REPLACEMENT OF EXISTING MAINS.
(a) During the rezoning, development plan, or building permit review process, the Raleigh Director of Public Utilities or his designee may determine that the increase in sewer discharge associated with a project will exceed the available capacity of downstream sewer mains and that replacement of the existing downstream sewer mains is required or that replacement of existing water mains is necessary to facilitate the potable water demands or fire flow requirements for a project. The City's Urban Redevelopment Main Replacement Reimbursement Program will provide reimbursements to developers who are required by the City to replace existing water and sewer mains in association with development projects. Reimbursements under this program may be for replacing water and/or sewer mains to provide adequate pipe capacity, and/or when the City requires the replacement of existing water and sewer infrastructure adjacent to a proposed project based on the condition of the existing pipes. The available reimbursement amount, as a percentage of estimated construction cost, will vary based on the age, condition and available capacity of the existing mains that are being replaced in association with the development project. The highest levels of reimbursement will be provided for projects replacing mains which are old, deteriorated, or over capacity in existing conditions, with the intent of distributing the costs of such projects between developers, the existing customer base, and future developments equitably. The Raleigh Director of Public Utilities shall adopt an Urban Redevelopment Main Replacement Reimbursement Policy pursuant to the requirements and standards set forth in this §8-2096 to implement this program, which shall be approved by the Council and incorporated into this Code by reference. (b) The developer shall identify the proposed increase in sewer capacity associated with the proposed development project. The Raleigh Director of Public Utilities or his designee will determine if there is enough information readily available to ensure that there is adequate downstream capacity for the proposed project. If the City determines there is adequate downstream sewer capacity based on readily available information, no capacity improvements will be required downstream of the project. In the event that not enough information is available, the developer shall be required to provide a sewer capacity study, prepared and sealed by a North Carolina licensed professional engineer, evaluating the downstream sewer capacity. The Raleigh Director of Public Utilities or his designee may require the study to extend to include major interceptors where there is concern that a large project may exceed the capacity of downstream interceptors. (c) Raleigh Director of Public Utilities or his designee may determine that existing mains adjacent to a project require replacement as part of the proposed project due to age or deterioration. Replacement of mains adjacent to a project will only be required when the project will be modifying connections to the existing mains or constructing other improvements, such as street or storm drainage improvements in the right-of-way or easement containing the water and sewer mains. The City will provide 100% reimbursement based on the unit prices set forth in the Raleigh Water Fee Schedule when replacement of the mains is not needed to accommodate additional sewer capacity or water demands or to address conflicts associated with the project. (d) Following the identification by the Raleigh Director of Public Utilities or his designee of mains requiring replacement, the developer shall provide construction drawings for the proposed improvements through the infrastructure construction plan approval process. Prior to construction drawing approval, the developer shall notify the City that an application for reimbursement will be made for the proposed project. The City will determine the applicable reimbursement value based on the criteria described in this section and the Urban Redevelopment Main Replacement Reimbursement Policy. (e) Within one year following completion of the project and acceptance of utility improvements by the City, a reimbursement contract shall be prepared pursuant to §8-2095 and submitted to Council for approval, and then executed by the City and developer. No reimbursement contract shall be executed by the City until such time as main trunk or interceptor facilities which serve the major mains are operational. Should the developer fail to execute the reimbursement contract within one year of the City's acceptance of the utility improvements, the City shall have no further obligation to reimburse the developer for the cost of the main or interceptor facilities that the developer constructed. (f) The reimbursement amount will be calculated based on the unit costs set forth in the Raleigh Water Fee Schedule and the Urban Redevelopment Main Reimbursement Policy. The City will require that the reimbursement be based on the lowest cost alternative which is feasible for the construction being pursued. If the developer chooses to pursue a higher cost construction method or alignment, the City will reimburse based on the lower cost alternative. (i.e. the developer may choose a more expensive alternative to speed schedule). Reimbursement based on unit costs is intended to cover both design and construction. In the event that the developer believes that actual construction cost will significantly exceed the costs below, the developer may request to be reimbursed according to the amounts and procedures established in the Anomaly Process in §8-2096(g) below. (g) In the event that site conditions exist that may cause construction costs to exceed the published unit costs set forth in the Raleigh Water Fee Schedule, the developer may choose to pursue this Anomaly Process in lieu of applying for reimbursement according to the published costs. The developer shall provide the City with the approved construction drawings and specifications based on the City's standard specifications for Water and Sewer Construction in the Raleigh Public Utilities Handbook. After the developer enters into a contract with the City for payment of the developer's portion of the project costs, the City will initiate a Capital Improvement Project to construct the proposed improvements. The City will bid the proposed water or sewer main replacement project in accordance with North Carolina Law for Public Contracts, N.C.G.S. 143, Article 8 and award the construction contract to the lowest responsible, responsive bidder. The developer shall pay to the City the total amount of the developer's portion of the proposed construction costs prior to contract award based on the low bid construction cost and the Reimbursement Percentages calculated above. The City will administer the construction of the proposed main replacement. Upon project completion, the final project cost shall be determined including approved change orders. The developer's portion of the project cost shall be based on the actual final project cost. The Developer may choose to pursue building permits following the bid opening, however no Certificate of Occupancy will be provided until all required improvements have been completed and accepted by the City. The City does not guarantee the project will meet the Developer's schedule. (h) Projects which were approved for construction prior to effective date of this ordinance but which have not yet been accepted for ownership by the City are eligible to apply for reimbursement under this §8-2096.
(Ord. No. 2015-396, §3, 2-16-15, eff. 2-21-15; Ord. No. 2017-697, §1, 4-18-17, eff. 7-1-17; Ord. No. 2018-846, §1, 6-11-18, eff. 7-1-18; Ord. No. 2019-967, §1, 6-10-19, eff. 7-1-19; Ord. No. 2020-96, §19, 6-15-20, eff. 7-1-20)