Sec. 65.100. - Inspections.
The Director shall be notified at least 24 hours, but not more than 72 hours, prior to the commencement of any excavation or fill work requiring a permit under SRC 65.040 or 65.060. Inspection may occur at any time throughout the project. A work schedule may be required at the discretion of the Director when notice of such requirement is given at the time of the permit issuance. A final inspection is required of all fill work and an approved set of plans shall be provided to the inspector.
(Prior Code, § 65.100; Ord. No. 69-79; Ord. No. 79-88)