Sec. 40-396. - City engineer's final determination and notice.
(a) The city engineer shall determine before completion of final design of a public works project whether the design of the public works project requires relocation of a facility and shall provide notice thereof to the owner of any facility required to be relocated. The notice shall be given in the manner provided in section 40-395 of this Code. In making a determination pursuant to this section, the city engineer or the director, as applicable, shall consider the purpose and complexity of the public works project and timetable for its construction, the number of facilities potentially affected by the project, the number of facility relocations required for the project, the cost and complexity of relocating each facility and any other factors he determines in the exercise of sound engineering judgement are relevant to the public works project.
(b) Notwithstanding the notice provisions of this Code that are otherwise applicable, if the city engineer discovers during the construction of a public works project:
(1) That a facility located in the public right-of-way not previously known to the city engineer requires relocation; or
(2) That inaccurate information about the location of the facility was provided by or on behalf of the facility owner and relocation is required which was not previously anticipated;
the city engineer shall give notice of the necessity for relocation in the manner provided in section 40-395 of this Code.
(c) Except for facilities discovered under section 40-396 (b)(1) or (2), the owner of the facility shall have a period of 60 days following the date of the notice sent pursuant to subsection (a) of this section to submit a proposed schedule for relocation of the facility for approval by the city engineer. The city, through the city engineer, and the owner may enter into a memorandum of agreement, in a form approved by the city attorney, evidencing agreement on the relocation schedule. The city engineer for good cause may extend, for a period not to exceed an additional 60 days, the time for submission or re-submission of a relocation schedule. The owner of facilities discovered under section 40-396(b)(1) or (2) shall provide to the city engineer at the earliest possible date, but not later than five business days following the owner's receipt of notice under that section, a proposed schedule for relocation of the facility and shall diligently prosecute the relocation of such facility until completed.
(d) No schedule for the relocation of a facility shall provide a period for relocation of longer than 180 days without written approval of the director, who for good cause shown by the facility owner, may extend the period of time for relocation. The time allowed for relocation shall commence on the date agreed to by the city engineer and the facility owner, but no later than the date of the notice to proceed for the public works project, unless extended by the city engineer for good cause shown by the facility owner, and shall be suspended upon the occurrence, and extended for the duration of, an event of force majeure, which shall include a strike, war or act of war (whether an actual declaration of war is made or not), insurrection, riot, act of public enemy, accident, fire, flood or other act of God, sabotage or other events, where the facility owner has exercised all due care in the prevention thereof so that the causes or other events are beyond the control and without the fault or negligence of the facility owner. For good cause shown by the facility owner, the city engineer may determine that the failure of the city to timely process a properly filed, complete application for a city permit or approval required for the facility relocation constitutes an event of force majeure.
In determining "good cause" as used in this section (excluding the failure of the city to act timely as set forth in the preceding paragraph) the director shall be entitled to consider such factors, not attributable to any fault or negligence of the facility owner, including, but not limited to the following:
1. Availability of materials or supplies required for a relocation.
2. Availability of sufficient labor or technical personnel to timely effect a relocation.
3. Any loss or damage to the public or users of the facility to be relocated.
4. The availability of any alternative means of providing to the public or other users the services of the facility to be relocated.
(Ord. No. 05-371, § 2, 4-13-05)