Burden of proof to sustain increased rates — Modification of requirements.
R.I. Gen. Laws § 39-3-12
in effect39-3-12. Burden of proof to sustain increased rates — Modification of requirements.
At any hearing involving any proposed increase in any rate, toll, or charge, the burden
of proof to show that the increase is necessary in order to obtain a reasonable compensation
for the service rendered shall be upon the public utility; provided, that the commission
may, in its discretion and for good cause shown, allow changes within less time than
required by the notice specified in § 39-3-11, and without holding the hearing and investigation therein provided for, or modify
the requirements of § 39-3-11 with respect to filing and publishing tariffs, either in the particular instance
or by general order applicable to special or particular circumstances or conditions,
or may enter an interim order prescribing a temporary schedule of rates, tolls, and
charges pending the completion of its investigation.
P.L. 1912, ch. 795, § 48; P.L. 1918, ch. 1651, § 1; G.L. 1923, ch. 253, § 48; G.L.
1938, ch. 122, § 45; P.L. 1949, ch. 2172, § 1; G.L. 1956, § 39-3-12; P.L. 1973, ch.
199, § 3.