Austin City Code § 25-1-61 ORDER OF PROCESS.
§ 25-1-61 - ORDER OF PROCESS.
(A) An applicant must obtain approvals in the following order:
(1) zoning;
(2) subdivision;
(3) site plan; and
(4) building permit.
(B) An applicant must obtain approvals for subdivision development in the following order:
(1) preliminary plan, if required;
(2) plat; and
(3) subdivision construction plan.
(C) An applicant may concurrently file zoning and site plan applications if no subdivision is required.
(D) An applicant may concurrently file subdivision, site plan, and building permit applications, if:
(1) no zoning or rezoning is required or requested; and
(2) the site plan has been certified as complete under Section 25-1-82 (Nonsubdivision Application Requirements and Expiration).
(E) The director may authorize concurrent review of applications for subdivision development under the following circumstances:
(1) Plat and preliminary plan if the director determines that the application for the preliminary plan only has outstanding deficiencies that are of an administrative nature that will not require significant changes to the layout or design of the subdivision.
(2) Plat and subdivision construction plan if:
(a) the preliminary plan has been approved;
(b) the director determines that the application for the preliminary plan only has outstanding deficiencies that are of an administrative nature that will not require significant changes to the layout or design of the subdivision; and
(c) the subdivision construction plan has been certified complete under Section 25-1-84 (Subdivision Construction Application Requirements and Expiration).
Source: Section 13-1-36; Ord. 990225-70; Ord. 031211-11; Ord. No. 20190822-117, Pt. 2, 9-1-19; Ord. No. 20230831-141, Pt. 3, 9-11-23.