§ 48-593 — Residential and nonresidential structures
Wilmington City Code, Delaware (Supp. No. 72: codified through Ordinance No. 25-073, enacted December 11, 2025) · Wilmington City Code § 48-593
Corpus is an independent public-information project, not the official City of Wilmington website. Stable reference: corpuslaw.us/code/c59cab65-c3d8-4e5c-b22e-e3d52aaaec37
Sec. 48-593. - Residential and nonresidential structures.
(a) Foundations. (1) Buildings and structures shall be supported on pilings or columns and shall be adequately anchored to such pilings or columns. Piling shall have adequate soil penetrations to resist the combined wave and wind loads (lateral and uplift). Water loading values used shall be those associated with the base flood. Wind loading values shall be those required by applicable building standards. Pile embedment shall include consideration of decreased resistance capacity caused by scour of soil strata surrounding the piling. (2) Slabs, pools, pool decks and walkways shall be located and constructed to be structurally independent of buildings and structures and their foundations to prevent transfer of flood loads to the buildings and structures during conditions of flooding, scour or erosion from wave-velocity flow conditions, and shall be designed to minimize debris impacts to adjacent properties and public infrastructure. (b) Elevation requirements. (1) The bottom of the lowest horizontal structural member supporting the lowest floor (excluding the pilings, pile caps, columns, grade beams, and bracing), shall be located at or above the base flood elevation plus 18 inches. (2) Basement floors that are below grade on all sides are prohibited. (3) The space below the lowest floor shall either be free of obstruction or, if enclosed by walls, shall meet the requirements of subsection (c). See FEMA Technical Bulletin #5 — Free of Obstruction Requirements. (c) Enclosures below the lowest floor. (1) Enclosures below the lowest floor shall be used solely for parking of vehicles, building access or storage. (2) Walls and partitions are permitted below the elevated floor, provided that such walls and partitions are designed to break away under flood loads and are not part of the structural support of the building or structure. See FEMA Technical Bulletin #9 — Design and Construction Guidance for Breakaway Walls. (3) Electrical, mechanical, and plumbing system components shall not be mounted on or penetrate through walls that are designed to break away under flood loads. (4) Walls intended to break away under flood loads shall be constructed with insect screening or open lattice, or shall be designed to break away or collapse without causing collapse, displacement or other structural damage to the elevated portion of the building or supporting foundation system. Such walls, framing and connections shall have a design safe loading resistance of not less than ten pounds per square foot and no more than 20 pounds per square foot; or (5) Where wind loading values of the local building requirements exceed 20 pounds per square foot, the applicant shall submit a certification prepared and sealed by a licensed professional engineer or licensed professional architect that: a. The walls and partitions below the lowest floor have been designed to collapse from a water load less than that which would occur during the base flood. b. The elevated portion of the building and supporting foundation system have been designed to withstand the effects of wind and flood loads acting simultaneously on all building components (structural and nonstructural). Water loading values used shall be those associated with the base flood; wind loading values used shall be those required by the local building requirements. (d) Manufactured homes. New or replacement manufactured homes, including substantial improvement of existing manufactured homes, shall: (1) Meet the foundation requirements of subsection (a). (2) Meet the elevation requirements of subsection (b). (3) Meet the enclosure requirements of subsection (c). (4) Be installed in accordance with the anchor and tie-down requirements of the building code or the manufacturer's written installation instructions and specifications. (e) Certification of design. The applicant shall include in the application a certification prepared by a licensed professional engineer or a licensed professional architect that the design and methods of construction to be used meet the applicable criteria of these regulations.
(Ord. No. 14-053(sub 1), § 2, 12-18-14)
Ask a question about Wilmington law
Corpus searches the Wilmington sections it holds and shows the ones that match, with their citations. Free, no sign-in.