20.08 - SCHEDULE AND CALCULATION OF IMPACT FEES.

(1) West Elderberry Neighborhood Sanitary Sewer Improvement Impact Fee. (a) In response to new and future Development demands in the Lower Badger Mill Creek watershed, in the area generally west of Schewe Road and Bear Claw Way, and east of Pioneer Road (extended north and south), and north of Mineral Point Road and south of Old Sauk Road, on the far west side of Madison, additional new public sanitary sewer facilities must be constructed to allow such Developments to proceed. Specifically, to adequately serve this new and future Development, the City must extend and construct new sanitary sewer interceptors. Therefore, the Common Council hereby establishes the West Elderberry Neighborhood Sanitary Sewer Improvement Impact Fee District as a mechanism to equitably charge all new Developments in this District their proportional share of the cost for necessary sanitary sewer improvements in the watershed. For purposes of the Sanitary Sewer Improvement Impact Fee imposed under this section, the said District shall be all existing undeveloped land that currently drains or is altered to drain to the West Elderberry Neighborhood Sanitary Sewer Improvement drainage area, as more specifically described and identified as follows: Any and all undeveloped parcels (platted and/or metes and bounds), or portions thereof, located within, or that are altered or pumped to discharge sewer outflow within the West Elderberry Neighborhood Sanitary Sewer Improvement service area. These lands are located within the City of Madison and the Town of Middleton as follows: Parts of the NE ¼ of Section 20, all of the SE ¼ of Section 20, and parts of the SW ¼ of Section 21, all within Town 7 North, Range 8 East, located in the Town of Middleton and the City of Madison. The said District shall also be shown on the Development Impact Fee District Map. (b) Calculation of the Impact Fee. The amount of the West Elderberry Sanitary Sewer Improvement Impact Fee to be imposed on individual properties shall be calculated based on the amount of Net Developable Area of the land being developed within the above-described District. The subject Impact Fee is based upon the estimated Cost to construct the necessary public improvements. Prior to the recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed, based on the proposed certified survey map, final Subdivision Plat, or other applicable public records. In the undeveloped areas of the West Elderberry Neighborhood Sanitary Sewer Improvement Impact Fee District, the Impact Fee shall be $109.26 per 1,000 square feet of Net Developed Area. In areas already developed without public sanitary sewer, the Impact Fee does not apply, but these parcels may be specially assessed or charged connection fees for sanitary sewer service at a rate of $109.26 per 1,000 square feet. The said Impact Fee, special assessment, and connection fee rates are established in 2018 dollars and shall be indexed for inflation annually (January 1st) thereafter with June, 2018 as the base, using the Construction Cost Index as published by the Engineering News Record or equivalent successor index. (2) Park Impact Fees. (a) Policy. In response to new and future development and population generating demands for new City parks and park infrastructure, the Common Council hereby establishes Park Impact Fees city-wide as the mechanism to equitably require all developments to pay for the costs that are necessary to accommodate the development. The Park Impact Fees shall include both a Park-Land Impact Fee and a Park-Infrastructure Impact Fee. The Park-Land Impact Fee shall be the complementary mechanism to equitably require all developments to dedicate land for necessary parks and open spaces under Section 16.23(6)(f), MGO, pay the Park-Land Impact Fee in lieu of dedication for public acquisition of parkland, or a combination of both. The Park-Infrastructure Impact Fee, formerly known as the Park Development Impact Fee, shall be the mechanism to equitably require all developments to pay for necessary infrastructure in City parks to accommodate the development. (b) Needs Assessment. For the purposes of the Park Impact Fees imposed under this subsection, a Park Needs Assessment has been prepared on a city-wide basis and is available for inspection at the Parks Division. The Needs Assessment provides the rationale and basis for the impact fees created under this Subsection. (c) Calculation of the Impact Fees. 1. General. The Park Impact Fees shall be imposed on individual properties based upon the type and number of dwelling units or lodging rooms to be generated by the property at the time of development, as set forth in this subdivision. 2. Park Impact Fee Categories. Park Impact Fees shall be based upon the five following categories of development: a. Single-Family or Duplex. Includes all types of single-family dwelling units, including single-family detached dwellings, single-family attached dwellings and two-family dwelling units. b. Multi-Family. Includes all three-family and multi-family dwelling units with three (3) or fewer bedrooms, as well as accessory dwelling units. c. Large Multi-Family. Multi-family dwelling units with four (4) or more bedrooms. d. Age Restricted Multi-Family. Multi-family dwelling units that are limited to occupancy by persons fifty-five (55) years of age or older by appropriate recorded restriction for a period of not less than thirty (30) years. e. Group Living Quarters. A building, or portion thereof, that contains an assembly of five (5) or more bedrooms for monthly or longer-term occupation, and that includes shared bathroom and/or kitchen facilities. This category includes, but is not limited to, lodging houses, fraternity or sorority houses, housing cooperatives, and some cohousing communities. 3. Determining Basis for Calculating Impact Fee. Prior to the recording of any certified survey map or any final plat, or the issuance of building permits following approval of rezoning or conditional use permits, the City shall calculate the number of residential dwelling units to be developed on each lot and, if necessary, the number of bedrooms per multi-family unit or within the group living quarters being proposed. These estimations shall be based on the proposed certified survey map or final subdivision plat, the zoning on each of the lots, and any further limitations on development imposed by notes on the face of the certified survey map or final plat. Where fees have been paid for future dwelling units on a lot or lots on a certified survey map or final plat, or credits given based on existing dwelling units, such payments and credits shall be noted on the face of the instrument. 4. Park-Land Impact Fee Determination. a. Determining the Land Dedication Requirements. The required land dedication and authorized credits to meet the community's park and open space needs shall be as provided in Sec. 16.23(6)(f), MGO. Under that subdivision, the land dedication requirements are as follows: Type of Development | Square Feet/Unit or Lodging Room Single-Family/Duplex | 1,081 Multi-Family | 734 Large Multi-Family | 1,424 Age Restricted Multi-Family | 573 Group Living Quarters | 410 b. Fee in Lieu of Land Dedication. In the event that land dedication would result in sites too small to be usable, or if the Comprehensive Plan calls for such public sites or open spaces to be located elsewhere, or if such sites would not otherwise be suitable as determined by the Plan Commission, after recommendation of the Park Superintendent or Board of Park Commissioners, a payment of the Park-Land Impact Fee in lieu of land dedication shall be required for each parcel proposed for development. c. Park-Land Impact Fee. The Park-Land Impact Fee shall be the product of the above-noted land dedication requirement, less any land dedications or credits, and the city-wide average assessed value of land per square foot, as of January 1 of each year. 5. Park-Infrastructure Impact Fee Determination. a. General. This impact fee is based upon the estimated cost to provide park facilities for new residents at a comparable level to park facilities which have traditionally been provided for existing residents, as detailed in the Needs Assessment. b. Park-Infrastructure Impact Fee. The Park-Infrastructure Impact Fee shall be as follows: Type of Development | Fee/Unit or Lodging Room Single-Family/Duplex | $1,520 Multi-Family | $1,032 Large Multi-Family | $2,003 Age Restricted Multi-Family | $806 Group Living Quarters | $577 The impact fee is charged in Year 2016 dollars and shall be indexed for inflation on January 1 of every year using 2016 as the base year with the Construction Cost Index as published by the Engineering News Record or equivalent successor index. c. Park-Infrastructure Impact Fee Benefit Districts. There are hereby created five benefit districts for administration of the Park-Infrastructure Impact Fee, as follows: i. City-Wide District. This District consists of all land within the City. ii. North District. This District consists of all land north of East Washington Avenue/USH 151 and east of Wisconsin Avenue. iii. East District. This District consists of all land south of East Washington Avenue and east of Martin Luther King, Jr. Boulevard. iv. Central District. This District consists of all land west of Wisconsin Avenue and Martin Luther King, Jr. Boulevard, west of Lake Monona, the Yahara River and Lake Waubesa, and east of Midvale Boulevard and Verona Road/USH 18 and 151. v. West District. This District consists of all land west of Midvale Boulevard and Verona Road/USH 18 and 151. d. Apportioning the Park-Infrastructure Impact Fee. Twenty percent (20%) of the Park-Infrastructure Impact Fee for a development shall go towards the City-Wide District. The remaining eighty percent (80%) of the fee shall go toward the benefit district in which the development lies. 6. Phasing of Implementation. The Common Council finds that the impact fees set forth in this subsection should be phased in over a three-year period. In determining the Park Impact Fees due for a development, the Park Impact Fees will be determined as set forth in this subdivision. Once determined, the following phasing factors will be applied to determine the amount actually imposed on the development, based on the calendar year in which the impact fee is due: Year | Phasing Factor 2017 | 80% 2018 | 90% 2019+ | 100% (d) Low-Cost Housing. 1. Definitions. For the purposes of this subdivision, "low-cost housing" means development that creates rental or owner-occupied housing units that are affordable, as that term is defined in Sec. 4.22(2), MGO, and which meet the deed restriction requirements of Sec. 4.22(7). 2. Determination. The determination whether a proposed development will create low-cost housing, and how much low-cost housing it will create, shall be made by the Community Development Division. 3. Low-Cost Housing Park Impact Fee Exemption. Pursuant to the authority established under Wis. Stat. § 66.0617(7), and in the interests of promoting the development of low-cost housing in the City, low-cost housing is exempt from the park impact fees established under this Subsection. This exemption only applies to those dwelling units or bedrooms within a development that are determined to be low-cost housing. This exemption does not extend to the land dedication requirements set forth under Sec. 16.23(6)(f), MGO, nor any other impact fees that may apply to a development. 4. Limitation. No amount of impact fees for which an exemption is provided for under this subdivision may be shifted to any other development in the project or in the City. (3) Upper Badger Mill Creek Stormwater Improvement Impact Fee. (a) In response to new and future Development and Redevelopment demands in the Upper Badger Mill Creek Watershed and the new public stormwater management facilities that must be constructed to allow such Developments and Redevelopments to proceed, the Common Council hereby establishes the Upper Badger Mill Creek Stormwater Improvement Impact Fee Zone as a mechanism to equitably charge all new Developments and Redevelopments their proportional share of the cost for such necessary off-site public stormwater facilities in the watershed. For purposes of the stormwater improvement Impact Fee imposed under this section, the said Zone shall be all land that currently drains or is altered to drain to the Upper Badger Mill Creek Watershed North of County Highway PD, and as more specifically described and identified as follows: Any and all parcels (platted and/or metes and bounds), or portions thereof, that reside within, or are altered to discharge within the Upper Badger Mill Creek Watershed. These lands are located within the City of Madison, Town of Middleton, and Town of Verona as follows: Parts of Section 25; Southwest ¼, Section 26; Southeast ¼, Section 26; Southwest ¼, Section 27; Southeast ¼, Section 27; Northeast ¼, Section 33; Southeast ¼, Section 33; Section 34 and 35; Northeast ¼, Section 36; and Southwest ¼, Section 36, all within Town 7 North, Range 8 East, located in the Town of Middleton and the City of Madison. Parts of Section 2 and 3; Northeast ¼, Section 4; Southwest ¼, Section 4; and Southeast ¼, Section 4, all within Town 6 North, Range 8 East, located in the Town of Verona and the City of Madison. The said Zone shall also be shown on the Development Impact Fee Zone Map. (Cr. by Ord. 13,472, 12-11-03) (b) Calculation of the Impact Fee. The amount of the stormwater improvement Impact Fee to be imposed on individual properties shall be calculated based on the amount of Net Developed Area of the land being Developed or Redeveloped within the above-described Zone. The subject Impact Fee is based upon the estimated Cost to provide Public (stormwater management ) Facilities to allow Development or Redevelopment of land in accord with the Upper Badger Mill Creek Stormwater Management Plan, as identified in the Needs Assessment for this Impact Fee. Prior to recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed, based on the proposed certified survey map, final Subdivision Plat, or other applicable public records. The Upper Badger Mill Creek Stormwater Improvement Impact Fee shall be $51.3569 per 1,000 square feet of Net Developed Area. The said Impact Fee rate is established in October, 2003 dollars and shall be indexed for inflation by month thereafter with October, 2003 as the base, using the Construction Cost Index as published by the Engineering News Record or equivalent successor index. (4) Door Creek North, Phase II Improvements Impact Fee. (a) Door Creek North, Phase II Improvements Impact Fee Zone. In response to new and future development in the Door Creek Watershed generating the need for improvements to the storm water drainage and public sanitary sewer systems, the Common Council hereby designates the Door Creek North, Phase II Improvements Impact Fee Zone as a part of a two-prong approach of special assessment district and Impact Fee Zone as the mechanism to equitably treat all new developments in regard to paying for necessary off-site storm water drainage and public sanitary sewer infrastructure improvements. For the purpose of the Impact Fee imposed under this section, the Zone shall be all land that currently drains or is made to drain to the Door Creek Watershed west of Sprecher Road, and as more specifically described and identified as follows: Any and all parcels (platted and/or metes and bounds), or portions thereof, that reside within, or is altered to discharge within the Door Creek Watershed. These lands are located within the City of Madison and the Town of Blooming Grove: Parts of Section 1, Section 2 and Northwest ¼ Section 11 of Township 07 North, Range 10 East, located in the City of Madison and the Town of Blooming Grove. The said Zone shall also be shown on the Development Impact Fee Zone Map. (b) Calculation of the Impact Fee. The amount of the Impact Fee to be imposed on individual properties shall be calculated based on the amount of Net Developed Area of the lot being Developed within the above-described Zone. The subject Impact Fee is based upon the estimated Cost to provide Public Facilities (storm water management and sanitary sewer) to allow Development of land in accord with the Sprecher Road Neighborhood Development Plan, as detailed in the Needs Assessment for this Impact Fee. Prior to recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed based on the proposed certified survey map, final Subdivision Plat, or applicable public records. The Door Creek North, Phase II Improvements Impact Fees shall be as follows: Section 1: $200.64 Section 2: $104.45 Section 3: $53.91 Section 4: $104.82 Section 5: $100.67 Section 6: $53.91 All Impact Fees in this Subdivision (b) are per 1,000 square feet of Net Developed Area and the sections are as defined in the Needs Assessment for this Impact Fee. The said Impact Fee is established in January, 2004 dollars and shall be indexed for inflation by month thereafter with January, 2004 as the base, using the Construction Cost Index as published by the Engineering News Record or equivalent successor index. (5) Valley View Road Sewer and Drainage Improvement Impact Fee. (a) In response to new and future Development demands in the Valley View Road area of the Upper Badger Mill Creek watershed, additional new public stormwater management facilities and public sanitary sewer facilities must be constructed to allow such Developments to proceed. The Common Council hereby establishes the Valley View Road Sewer and Drainage Improvement Impact Fee District as a mechanism to equitably charge all new Developments their proportional share of the cost for necessary additional public stormwater and sanitary facilities in the watershed. For purposes of the Sewer and Drainage Improvement Impact Fee imposed under this section, the said District shall be all existing undeveloped land that currently drains or is altered to drain to the Valley View Road drainage area, and as more specifically described and identified as follows: Any and all undeveloped parcels (platted and/or metes and bounds), or portions thereof, that reside within, or is altered to discharge within the Valley View area of the Upper Badger Mill Creek Watershed. These lands are located within the City of Madison and Town of Middleton as follows: Parts of the South ½ Section 27; Section 34; and the Northeast ¼ Section 33 all within Town 7 North, Range 8 East, located in the Town of Middleton and the City of Madison. The said Zone shall also be shown on the Development Impact Fee District Map. (b) Calculation of the Impact Fee. The amount of the Sewer and Drainage Improvement Impact Fee to be imposed on individual properties shall be calculated based on the amount of Net Developable Area of the land being Developed within the above-described District. The subject Impact Fee is based upon the estimated Cost to construct the necessary improvements. Prior to recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed, based on the proposed certified survey map, final Subdivision Plat, or other applicable public records. In the undeveloped areas, the Valley View Road Sewer and Drainage Improvement Impact Fee shall be $134.9837 per 1,000 square feet of Net Developed Area. In areas already developed without public sanitary sewer, the Impact Fee does not apply, but these parcels may be specially assessed or charged connection fees for sanitary sewer service at a rate of $57.2140 per 1,000 square feet. The said Impact Fee and connection fee rates are established in 2005 dollars and shall be increased or decreased annually each January 1 thereafter, with June 2005 as the base, by the product of (i) the percentage increase or decrease in the Construction Cost Index annual average, as published by the Engineering News Record or equivalent successor index, for the immediately prior year and the year next preceding and (ii) the fee applicable for the prior calendar year. (6) Westside Drainage Improvement Impact Fee. (a) In response to new and future Development demands on the far west side of Madison, in the area generally west of Pleasant View Road and east of Pioneer Road (extended north and south), and north of McKee Road and south of Blackhawk Road, additional public stormwater management facilities will need to be constructed to allow such Developments to proceed. Specifically, to adequately serve this new and future Development, the City must extend and construct new storm sewer improvements. Therefore, the Common Council hereby establishes the Westside Drainage Improvement Impact Fee District as a mechanism to equitably charge all new Developments in this District their proportional share of the cost for necessary stormwater management facilities in the watershed. Because the stormwater management needs of a particular development area will vary depending upon the location throughout the District, impact fee zones will be created within the District as a way for the Common Council to impose impact fees on developers to pay for the capital costs that are necessary to accommodate land development within the particular zone. (b) Westside Drainage Improvement Impact Fee Zones. The Common Council hereby establishes the following impact fee zones within the District: 1. Bear Claw Way Drainage Improvement Impact Fee Zone. The Bear Claw Way Drainage Improvement Impact Fee Zone of the Westside Drainage Improvement Impact Fee District shall be all existing undeveloped land that currently drains or is altered to drain to the Bear Claw Way stormwater drainage area, as more specifically described and identified as follows: Any and all parcels (platted and/or metes and bounds), or portions thereof, located within, or that are altered to discharge storm sewer outflow within the Bear Claw Way drainage area. These lands are located within the City of Madison and Town of Middleton as follows: Parts of the SE ¼ of the NW ¼ of Section 21 within Town 7 North, Range 8 East, located in the Town of Middleton and the City of Madison. The said Zone shall also be shown on the Development Impact Fee District Map. 2. Mineral Point Road Drainage Impact Fee Zone. The Mineral Point Road Drainage Impact Fee Zone of the Westside Drainage Improvement Impact Fee District shall be all existing undeveloped land that currently drains or is altered to drain to the Mineral Point Road stormwater drainage area, as more specifically described and identified as follows: Any and all parcels (platted and/or metes and bounds), or portions thereof, located within, or that are altered to discharge stormwater within the Mineral Point Road drainage area. These lands are located in the Town of Middleton and the City of Madison as follows: Parts of the NE ¼ of Section 28, parts of the SE ¼ of Section 21, part of the SE ¼ of the SW ¼ of Section 21, and part of the NW ¼ of Section 28 all within Town 7 North, Range 8 East, located in the Town of Middleton and the City of Madison. The said Zone shall also be shown on the Development Impact Fee District Map. (c) Calculation of the Impact Fee. The amount of the Westside Drainage Improvement Impact Fee to be imposed on individual properties shall be calculated based on the amount of Net Developable Area of the land being developed within the above-described District and Zones. The subject Impact Fee is based upon the estimated Cost to construct the necessary public improvements within the specific zones. Prior to recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed, based on the proposed certified survey map, final Subdivision Plat, or other applicable public records. The Impact Fee shall consist of the following: 1. In the undeveloped areas of the Bear Claw Way Drainage Improvement Impact Fee Zone, the Impact Fee shall be $390.04 per 1,000 square feet of Net Developed Area. 2. In the undeveloped areas of the Mineral Point Road Drainage Impact Fee Zone, the Impact Fee shall be $169.91 per 1,000 square feet of Net Developed Area. The said Impact Fee rates are established in 2018 dollars and shall be indexed for inflation annually (January 1st) thereafter with June, 2018 as the base, using the Construction Cost Index as published by the Engineering News Record or equivalent successor index. (7) Felland Road Sanitary Sewer Improvement Impact Fee. (a) In response to new and future Development demands in the Felland Road Neighborhood area of the Starkweather Creek watershed, additional new public sanitary sewer facilities must be constructed to allow such Developments to proceed. The Common Council hereby establishes the Felland Road Neighborhood Sanitary Sewer Improvement Impact Fee District as a mechanism to equitably charge all new Developments their proportional share of the cost for necessary sanitary facilities in the watershed. For purposes of the Sanitary Sewer Improvement Impact Fee imposed under this section, the said District shall be all existing undeveloped land that currently drains or is altered to drain to the Felland Road Neighborhood drainage area, and as more specifically described and identified as follows: Any and all undeveloped parcels (platted and/or metes and bounds), or portions thereof, that reside within, or are altered to discharge within the Felland Road Neighborhood Watershed. These lands are located within the City of Madison and Town of Burke as follows: Parts of the South ½ of the South ½ of Section 14; the Southwest ¼ of the Southwest ¼ of Section 13; Parts of Sections 23, 24, 25,26; Parts of the Southeast ¼ of Section 27; the Northeast ¼ Section 34; Parts of Section 35; Parts of the Northwest ¼ of Section 36, all within Town 8 North, Range 10 East in the Town of Burke and the City of Madison. The said Zone shall also be shown on the Development Impact Fee District Map. (b) Calculation of the Impact Fee. The amount of the Sanitary Sewer Improvement Impact Fee to be imposed on individual properties shall be calculated based on the amount of Net Developable Area of the land being developed within the above-described District. The subject Impact Fee is based upon the estimated Cost to construct the necessary improvements. Prior to recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed, based on the proposed certified survey map, final Subdivision Plat, or other applicable public records. In the undeveloped areas, the Felland Road Neighborhood Sanitary Sewer Improvement Impact Fee shall be per 1,000 square feet of Net Developed Area. In areas already developed without public sanitary sewer, the Impact Fee does not apply, but these parcels may be specially assessed or charged connection fees for sanitary sewer service at a rate of $56.2268 per 1,000 square feet. The said Impact Fee and connection fee rates are established in 2008 dollars and shall be indexed for inflation annually (January 1 st ) thereafter with January 2008 as the base, using the Construction Cost Index as published by the Engineering News Record or equivalent successor index. (8) Elderberry Neighborhood Sanitary Sewer Improvement Impact Fee. (a) In response to new and future Development demands in the Elderberry Neighborhood area of the Pheasant Branch watershed, additional new public sanitary sewer facilities must be constructed to allow such Developments to proceed. The Common Council hereby establishes the Elderberry Neighborhood Sanitary Sewer Improvement Impact Fee District as a mechanism to equitably charge all new Developments their proportional share of the cost for necessary sanitary sewer facilities in the watershed. For purposes of the Sanitary Sewer Improvement Impact Fee imposed under this section, the said District shall be all existing undeveloped land that currently drains or is altered to drain to the Elderberry Neighborhood drainage area, and as more specifically described and identified as follows: Any and all undeveloped parcels (platted and/or metes and bounds), or portions thereof, that reside within, or are altered to discharge within the Elderberry Neighborhood area watershed. These lands are located within the City of Madison and Town of Middleton as follows: Parts of the South ½ of Section 21 and parts of the Southwest ¼ of Section 22, all within Town 7 North, Range 8 East, in the Town of Middleton and the City of Madison. The said Zone shall also be shown on the Development Impact Fee District Map. (b) Calculation of the Impact Fee. The amount of the Sanitary Sewer Improvement Impact Fee to be imposed on individual properties shall be calculated based on the amount of Net Developable Area of the land being developed within the above-described District. The subject Impact Fee is based upon the estimated Cost to construct the necessary improvements. Prior to recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed, based on the proposed certified survey map, final Subdivision Plat, or other applicable public records. In the undeveloped areas, the Elderberry Neighborhood Sanitary Sewer Improvement Impact Fee shall be $112.69 per 1,000 square feet of Net Developed Area. In areas already developed without public sanitary sewer, the Impact Fee does not apply, but these parcels may be specially assessed or charged connection fees for sanitary sewer service at a rate of $112.69 per 1,000 square feet. The said Impact Fee and connection fee rates are established in 2009 dollars and shall be indexed for inflation annually (January 1 st ) thereafter with January 2009 as the base, using the Construction Cost Index as published by the Engineering News Record or equivalent successor index. (9) Northeast Neighborhood Sanitary Sewer Improvement Impact Fee. (a) In response to new and future Development demands in the Northeast Neighborhood area located primarily north of Interstate 94 and east of Interstate 39-90-94, additional new public sanitary sewer facilities must be constructed to allow such Developments to proceed. The Common Council hereby establishes the Northeast Neighborhood Sanitary Sewer Improvement Impact Fee District as a mechanism to equitably charge all new Developments their proportional share of the cost for necessary sanitary sewer facilities in the watershed. For purposes of the Sanitary Sewer Improvement Impact Fee imposed under this section, the said District shall be all existing undeveloped land that currently drains or is altered to drain to the Northeast Neighborhood drainage area, and as more specifically described and identified as follows: Any and all undeveloped parcels (platted and/or metes and bounds), or portions thereof, that reside within, or are altered to discharge within the Northeast Neighborhood area watershed. These lands are located within the City of Madison and Towns of Burke and Blooming Grove as follows: Part of all quarters of Section 35 and West ½ of Section 36, Town 8 North, Range 10 East in the Town of Burke and City of Madison; and, parts of the North ½ Section 2 and Northwest ¼ of Section 1, Town 7 North, Range 10 East in the Town of Blooming Grove and the City of Madison. The said Zone shall also be shown on the Development Impact Fee District Map. (b) Calculation of the Impact Fee. The amount of the Sanitary Sewer Improvement Impact Fee to be imposed on individual properties shall be calculated based on the amount of Net Developable Area of the land being developed within the above-described District. The subject Impact Fee is based upon the estimated Cost to construct the necessary improvements. Prior to recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed, based on the proposed certified survey map, final Subdivision Plat, or other applicable public records. In the undeveloped areas, the Northeast Neighborhood Sanitary Sewer Improvement Impact Fee shall be $134.58 per 1,000 square feet of Net Developed Area. In areas already developed without public sanitary sewer, the Impact Fee does not apply, but these parcels may be specially assessed or charged connection fees for sanitary sewer service at a rate of $134.58 per 1,000 square feet. The said Impact Fee and connection fee rates are established in 2009 dollars and shall be indexed for inflation annually (January 1 st ) thereafter with February, 2009 as the base, using the Construction Cost Index as published by the Engineering News Record or equivalent successor index. (10) Lower Badger Mill Creek Sewer and Drainage Improvement Impact Fee. (a) In response to new and future Development demands in the Lower Badger Mill Creek watershed, in the area generally west of County Trunk Highway M and east of Pioneer Road (extended north and south), and north of County Trunk Highway PD and south of Blackhawk Road, on the far west side of Madison, additional new public sanitary sewer and stormwater management facilities must be constructed to allow such Developments to proceed. Specifically, to adequately serve this new and future Development, the City must extend and construct a new sanitary sewer interceptor, sanitary force main and lift station, greenways, storm water basins, and roadway culverts. Therefore, the Common Council hereby establishes the Lower Badger Mill Creek Sewer and Drainage Improvement Impact Fee District as a mechanism to equitably charge all new Developments their proportional share of the cost for necessary sanitary sewer and stormwater management facilities in the watershed. Because of the differing needs for sanitary sewer and stormwater management facilities in the District, the Common Council hereby establishes two impact fee zones within the District, the Lower Badger Mill Creek Sanitary Sewer Impact Fee Zone and the Lower Badger Mill Creek Stormwater Impact Fee Zone. The combined boundaries of the two Impact Fee Zones make up the boundary of the Impact Fee District. The Impact Fee Zones are established as follows: 1. Lower Badger Mill Creek Sanitary Sewer Impact Fee Zone. For purposes of the Sanitary Sewer Impact Fee portion of the Lower Badger Mill Creek Sewer and Drainage Improvement Impact Fee imposed under this section, the Lower Badger Mill Creek Sanitary Sewer Impact Fee Zone shall be all existing undeveloped land that currently drains or is altered to drain to the Lower Badger Mill Creek sanitary sewer drainage area, and as more specifically described and identified as follows: Any and all parcels (platted and/or metes and bounds), or portions thereof, that reside within, or are altered to discharge sanitary sewer outflow within the Lower Badger Mill Creek Watershed. These lands are located within the City of Madison, Town of Middleton, and Town of Verona as follows: Parts of the SE ¼ of Section 17, all of the East ½ of Section 20, parts of the West ½ and SE ¼ of Section 21, parts of the West ½ of Section 27, parts of all quarters of Section 28, all of the East ½ of Sections 29 and 32, and parts of all quarters of Section 33, all within Town 7 North, Range 8 East, located in the Town of Middleton and the City of Madison. Also parts of the North ½ of Section 4 within Town 6 North, Range 8 East, located in the Town of Verona and the City of Madison. 2. Lower Badger Mill Creek Stormwater Impact Fee Zone. For purposes of the Stormwater Impact Fee portion of the Lower Badger Mill Creek Sewer and Drainage Improvement Impact Fee imposed under this section, the Lower Badger Mill Creek Stormwater Impact Fee Zone shall be all existing undeveloped land that currently drains or is altered to drain to the Lower Badger Mill Creek stormwater drainage area, and as more specifically described and identified as follows: Any and all parcels (platted and/or metes and bounds), or portions thereof, that reside within, or are altered to discharge stormwater within the Lower Badger Mill Creek Watershed. These lands are located within the City of Madison, Town of Middleton, and Town of Verona as follows: Parts of the SW ¼ of Section 16, parts of the SE ¼ of Section 17, all of the East ½ of Section 20, parts of the West ½ and SE ¼ of Section 21, parts of the West ½ of Section 27, parts of all quarters of Section 28, all of the East ½ of Sections 29 and 32, and parts of all quarters of Section 33, all within Town 7 North, Range 8 East, located in the Town of Middleton and the City of Madison. Also parts of the NE ¼ of Section 4 within Town 6 North, Range 8 East, located in the Town of Verona and the City of Madison. Both of said Zones, and said District, shall be shown on the Development Impact Fee District Map. (b) Calculation of the Impact Fee. The amount of the Sewer and Drainage Improvement Impact Fee to be imposed on individual properties under this Section shall be calculated based on the amount of Net Developable Area of the land being developed within the above-described District and Zones, as well as the number of dwelling units developed within the Sanitary Sewer Impact Fee Zone. The subject Impact Fee is based upon the estimated Cost to construct the necessary improvements. Prior to recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed, based on the proposed certified survey map, final Subdivision Plat, or other applicable public records, and, if in the Sanitary Sewer Impact Fee Zone, the amount of dwelling units, as defined in Sec. 28.211 of the Madison General Ordinances, to be developed. The Impact Fee shall consist of the following: (Am. by ORD-12-00134, 1-2-13) 1. In the undeveloped areas of the Lower Badger Mill Creek Sanitary Sewer Impact Fee Zone, the Sanitary Sewer component of the Impact Fee shall be $56.52 per 1,000 square feet of Net Developed Area. In areas already developed without public sanitary sewer, the Impact Fee does not apply, but these parcels may be specially assessed or charged connection fees for sanitary sewer service at a rate of $56.52 per 1,000 square feet. 2. For the first one thousand (1,000) dwelling units within the Lower Badger Mill Creek Sanitary Sewer Impact Fee Zone that benefit from the new lift station and force main improvement prior to MMSD interceptor relief to the area, the Lift Station component of the Impact Fee shall be $595.05 per dwelling unit. 3. In the undeveloped areas of the Lower Badger Mill Creek Stormwater Impact Fee Zone, the Stormwater component of the Impact Fee shall be $121.42 per 1,000 square feet of Net Developed Area. The said Impact Fee, special assessment, and connection fee rates are established in 2009 dollars and shall be indexed for inflation annually (January 1st) thereafter with October, 2009 as the base, using the Construction Cost Index as published by the Engineering News Record or equivalent successor index. (11) Jeffy Trail Sanitary Sewer Improvement Impact Fee. (a) In response to new and future Development demands in the Upper Badger Mill Creek watershed, in the area generally consisting of the 2 nd Addition to Hawks Creek located to the northwest of Raymond Road, south of Flagstone Drive, east of Tail Water Drive, and along Jeffy Trail and Trevor Way extended, on the south west side of Madison, additional new public sanitary sewer facilities must be constructed to allow such Developments to proceed. Specifically, to adequately serve this new and future Development, the City must extend and construct a new sanitary sewer interceptor. Therefore, the Common Council hereby establishes the Jeffy Trail Sanitary Sewer Improvement Impact Fee District as a mechanism to equitably charge all new Developments their proportional share of the cost for necessary sanitary sewer facilities in the drainage area. For purposes of the Sanitary Sewer Improvement Impact Fee imposed under this section, the said District shall be all existing undeveloped land that currently drains or is altered to drain to the Jeffy Trail Sanitary Sewer Improvement drainage area, and as more specifically described and identified as follows: Any and all undeveloped parcels (platted and/or metes and bounds), or portions thereof, that reside within, or are altered or pumped to discharge within the Jeffy Trail sanitary sewer improvement service area. These lands are located within the City of Madison and the Town of Verona as follows: Parts of the Southeast ¼ of the Northeast ¼ of Section 3, and part of the Southwest ¼ of the Northwest ¼ of Section 2, all within Town 6 North, Range 8 East, in the Town of Verona and the City of Madison. The said District shall also be shown on the Development Impact Fee District Map. (b) Calculation of the Impact Fee. The amount of the Sanitary Sewer Improvement Impact Fee to be imposed on individual properties shall be calculated based on the amount of Net Developable Area of the land being developed within the above-described District. The subject Impact Fee is based upon the estimated Cost to construct the necessary improvements. Prior to recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed, based on the proposed certified survey map, final Subdivision Plat, or other applicable public records. In the undeveloped areas, the Jeffy Trail Sanitary Sewer Improvement Impact Fee shall be $303.95 per 1,000 square feet of Net Developed Area. In areas already developed without public sanitary sewer, or areas that will initially be served by a private lift station upon development, the Impact Fee does not apply, but these parcels may be specially assessed or charged connection fees for sanitary sewer service at a rate of $303.95 per 1,000 square feet. The said Impact Fee and connection fee rates are established in 2013 dollars and shall be indexed for inflation annually (January 1 st ) thereafter with March, 2013 as the base, using the Construction Cost Index as published by the Engineering News Record or equivalent successor index. (12) Pumpkin Hollow Neighborhood Sanitary Sewer Improvement Impact Fee. (a) In response to new and future Development demands in the Pumpkin Hollow Neighborhood, in the area generally east of Interstate 39/90/94 and west of Rattman Road, on the northeast side of Madison, additional new public sanitary sewer facilities must be constructed to allow such Developments to proceed. Specifically, to adequately serve this new and future Development, the City must extend and construct new sanitary sewer interceptors. Therefore, the Common Council hereby establishes the Pumpkin Hollow Neighborhood Sanitary Sewer Improvement Impact Fee District as a mechanism to equitably charge all new Developments in this District their proportional share of the cost for necessary sanitary sewer improvements in the watershed. For purposes of the Pumpkin Hollow Neighborhood Sanitary Sewer Improvement Impact Fee imposed under this section, the said District shall be all existing undeveloped land that currently drains or is altered to drain to the Pumpkin Hollow Neighborhood Sanitary Sewer Improvement drainage area, as more specifically described and identified as follows: Any and all undeveloped parcels (platted and/or metes and bounds), or portions thereof, that are located within, or that are altered or pumped to discharge sewer outflow within the Pumpkin Hollow Neighborhood Sanitary Sewer Improvement service area. These lands are located within parts of the Southern ½ of Section 3, Sections 9, 10, 15, and the Eastern ½ of Section 16, Town 8 North, Range 10 East in the Town of Burke and the City of Madison. The said District shall also be shown on the Development Impact Fee District Map. (b) Calculation of the Impact Fee. The amount of the Pumpkin Hollow Neighborhood Sanitary Sewer Improvement Impact Fee to be imposed on individual properties shall be calculated based on the amount of Net Developable Area of the land being developed within the above-described District. The subject Impact Fee is based upon the estimated Cost to construct the necessary public improvements. Prior to the recording of any certified survey map or any final Subdivision Plat, or the issuance of building permits following approval of a rezoning or conditional use permit, the City shall calculate the amount of net area being developed, based on the proposed certified survey map, final Subdivision Plat, or other applicable public records. In the undeveloped areas of the Pumpkin Hollow Neighborhood Sanitary Sewer Improvement Impact Fee District, the Impact Fee shall be $60.60 per 1,000 square feet of Net Developed Area. In areas already developed without public sanitary sewer, the Impact Fee does not apply, but these parcels may be specially assessed or charged connection fees for sanitary sewer service at a rate of $60.60 per 1,000 square feet. The said Impact Fee, special assessment, and connection fee rates are established in 2024 dollars and shall be indexed for inflation annually (January 1st) thereafter with September, 2024 as the base, using the Construction Cost Index as published by the Engineering News Record or equivalent successor index.

(Rep. by ORD-17-00059, 6-19-17; Cr. by ORD-18-00079, 8-3-18) (Rep. & Rec. by ORD-16-00091, Pub. 11-9-16, Eff. 1-1-17) (Cr. by Ord. 13,542, 3-17-04) (Rep. by ORD-16-00091, Pub. 11-9-16, Eff. 1-1-17; Cr. by ORD-18-00079, 8-3-18) (Cr. by ORD-07-00192, 12-20-07) (Cr. by ORD-08-00126, 11-22-08) (Cr. by ORD-09-00035, 3-14-09) (Cr. by ORD-09-00156, 12-5-09) (Cr. by ORD-13-00033, 3-27-13) (Cr. by ORD-24-00067, 10-4-24)

Ask a question about Madison law

Corpus searches the Madison sections it holds and shows the ones that match, with their citations. Free, no sign-in.