§ 141.0422 — Battery Energy Storage Facilities

San Diego Municipal Code (City Clerk PDFs, pages revised through October 2026) · San Diego Municipal Code § 141.0422

Corpus is an independent public-information project, not the official City of San Diego website. Stable reference: corpuslaw.us/code/c874c258-b30a-4795-98a4-5a035522924c

§141.0422 Battery Energy Storage Facilities

This section regulates utility-serving battery energy storage facilities which store energy within enclosed buildings or modular containers and then solely release the energy directly back to the electrical grid. Battery energy storage facilities do not include behind the meter battery installations that provide energy to the same premises on which they are located. This section distinguishes between small-scale battery energy storage facilities with a development footprint of one-quarter acre or less, medium-scale battery energy storage facilities with a development footprint of more than one-quarter acre but less than one acre, and large-scale battery energy storage facilities with a development footprint of one acre or more. Battery energy storage facilities shall comply with the approval process set forth in Section 141.0422(a) through (c) as applicable to the development. All battery energy storage facilities are subject to the general regulations in Section 141.0422(d) and the general design requirements in Section 141.0422(e). (a) Small-scale battery energy storage facilities The following regulations apply to battery energy storage facilities with a development footprint of one-quarter acre or less. (1) Limited Use Regulations Small-scale battery energy storage facilities are permitted as a limited use decided in accordance with Process One in zones indicated by an “L” in the Use Regulations Tables in Chapter 13, Article 1 (Base Zones) subject to the following: (A) In residential, commercial, and mixed-use base zones that permit residential development, battery energy storage facilities shall be limited to no more than 25 percent of the allowable development area and allowable gross floor area, unless the premises cannot be developed with residential uses due to site constraints, except for the presence of environmentally sensitive lands, beyond the applicant’s control, such as the presence of utilities, in which case the 25 percent limitation shall not apply. (B) In the IL (Industrial – Light) and IS (Industrial – Small Scale) Zones, battery energy storage facilities shall be limited to no more than 25 percent of the allowable development area and gross floor area, unless the premises cannot be developed with industrial uses due to site constraints except for the presence of environmentally sensitive lands beyond the applicant’s control, such as the presence of utilities, in which case the 25 percent limitation shall not apply. (2) Conditional Use Permit Regulations Small-scale battery energy storage facilities may be permitted with a Conditional Use Permit decided in accordance with Process Three in zones indicated by a “C” in the Use Regulations Tables in Chapter 13, Article 1 (Base Zones) subject to the following: (A) In the OP (Open Space – Park) and OR (Open Space – Residential) Zones, battery energy storage facilities may be permitted only as follows: (i) If they do not result in loss of any publicly accessible active or passive recreation area; and (ii) Within previously disturbed areas with existing electrical utility easements. (B) In the OP (Open Space – Park) and OR (Open Space – Residential) Zones within the Coastal Overlay Zone, battery energy storage facilities may be permitted only as follows: (i) Within a distance of 500 feet or less of an existing electrical distribution facility; and (ii) Within a distance of 500 feet or greater from environmentally sensitive lands. (C) In the AR (Agricultural-Residential) Zone within the Coastal Overlay Zone, battery storage facilities may be permitted only on premises not containing agricultural land as identified by the California Department of Conservation as Prime Farmland, Farmland of Statewide Importance, Unique Farmland, Farmland of Local Importance, or Farmland of Local Potential as defined in the California Public Resources Code section 10213. (D) In the CV (Commercial-Visitor) Zone within the Coastal Overlay Zone, battery storage facilities shall not be allowed on the ground floor of any development on the premises. (b) Medium-scale battery energy storage facilities The following regulations apply to battery energy storage facilities with a development footprint of more than one-quarter acre but less than one acre. (1) Limited Use Regulations Medium-scale battery energy storage facilities are permitted as a limited use decided in accordance with Process One in zones indicated by an “L” in the Use Regulations Tables in Chapter 13, Article 1 (Base Zones). (2) Conditional Use Permit Regulations (A) Medium-scale battery energy storage facilities may be permitted with a Conditional Use Permit decided in accordance with Process Two in industrial zones indicated by a “C” in the Use Regulations Tables in Chapter 13, Article 1, Division 6. (B) Medium-scale battery energy storage facilities may be permitted with a Conditional Use Permit decided in accordance with Process Three in zones indicated by a “C” in the Use Regulations Tables in Chapter 13, Article 1 (Base Zones) as follows: (i) In commercial base zones that do not permit residential development. (ii) In residential, commercial, and mixed-use base zones that permit residential development if the premises cannot be developed with residential uses due to site constraints, except for the presence of environmentally sensitive lands, beyond the applicant’s control, such as the presence of utilities. (c) Large-scale battery energy storage facilities The following regulations apply to battery energy storage facilities with a development footprint of one acre or more. (1) Conditional Use Permit Regulations (A) Large-scale battery energy storage facilities may be permitted with a Conditional Use Permit decided in accordance with Process Three in industrial zones indicated by a “C” in the Use Regulations Tables in Chapter 13, Article 1, Division 6. (B) Large-scale battery energy storage facilities may be permitted with a Conditional Use Permit decided in accordance with Process Four in zones indicated by a “C” in the Use Regulations Tables in Chapter 13, Article 1 (Base Zones) as follows: (i) In commercial base zones that do not permit residential development. (ii) In residential, commercial, and mixed-use base zones that permit residential development if the premises cannot be developed with residential uses due to site constraints, except for the presence of environmentally sensitive lands, beyond the applicant’s control, such as the presence of utilities. (d) General Regulations The following regulations apply to all battery energy storage facilities regardless of their size. (1) Use Regulations The premises shall not contain a child care facility or school. (2) Operational, Safety and Decommissioning Regulations (A) Every application shall provide the following documentation to the satisfaction of the Chief Building Official: (i) Demonstrating that the battery energy storage facility complies with all applicable requirements imposed by state or federal regulatory agencies; and (ii) Identifying the facility type/application, total rated battery power capacity in kilowatts or megawatts, energy capacity in kilowatt-hours or megawatt-hours, storage duration, cycle life/lifetime, and type of battery chemistry. (B) The applicant shall submit and implement an emergency response plan for battery storage fire events and other emergency events consistent with state and national standards and regulations to the satisfaction of the Fire Marshal. (C) The applicant shall obtain all necessary construction permits to comply with applicable building, fire, mechanical, electrical, and plumbing codes, and state and federal laws. (D) The applicant shall comply with all applicable state and national standards and requirements for the design, construction, installation, commissioning, operation, maintenance, and decommissioning of the battery energy storage facility. (E) Battery energy storage facilities shall be maintained pursuant to title 24, part 9, of the California Fire Code, as amended, and be in good working order, free from trash, debris, and graffiti, and designed to discourage vandalism. The permit holder or record owner shall repair or replace any damaged walls, fences, landscaping, buildings, structures, and equipment within 30 calendar days of receipt of a written notification from the City Manager. (F) The permit holder or record owner shall remove and decommission the battery energy storage facility from the premises and restore the premises to the condition preceding the construction and installation of the battery energy storage facility, at the sole cost and expense of the permit holder or record owner, if any of the following circumstances exists: (i) The permit authorizing the battery energy storage facility is revoked or expired and a new permit has not been obtained; or (iii) The City Manager determines that the battery energy storage facility or components of the battery energy storage facility are non-operational or no longer in use; or (iv) The City Manager determines that the battery energy storage facility is a public nuisance; or (iv) The Fire Code Official determines that the facility constitutes a distinct hazard to life or property. (G) The applicant shall submit a Hazard Mitigation Analysis when technologies are not specifically identified in title 24, part 9, of the California Fire Code or when more than one technology is provided in a room or enclosed area where there is a potential for adverse reactions between technologies. (3) Noise Regulations. Noise generated from battery energy storage facilities shall not exceed the noise limits for the zone as established in the Noise Abatement and Control Regulations (Chapter 5, Article 9.5, Division 4: Limits). (e) General Design Requirements The following design requirements apply to all battery energy storage facilities regardless of their size. (1) Overhead wires connecting the battery energy storage facility to an energy generation station or substation are not permitted, unless the premises containing the energy generation station or substation immediately abuts the premises on which the battery energy storage facility is proposed and existing overhead connections are present on the premises containing the energy generation station or substation. Overhead wires shall not be permitted to cross other private property, public property, or public right-of-way to connect with an energy generation station or substation. (2) Access to a battery energy storage facility shall conform to title 24, part 9, of the California Fire Code and be as direct as possible from primary arterials and major streets and shall avoid residential streets unless no other feasible options exist. Shared access with an adjacent energy generation station or substation is permitted. (3) The development shall comply with the Street Tree and Public Right-of-Way Requirements in Section 142.0409. (4) All mechanical equipment and storage areas shall be located within an enclosed building or modular container, as follows: (A) The building or modular container, or both, shall be located on the premises so that visibility from adjacent public rights-of-way or adjacent development that is not of a similar nature is minimized. (B) Battery energy storage facilities located on the same premises as residential uses shall be located within an enclosed building that is designed to be architecturally consistent with the primary structure. (C) Mechanical equipment that supports the battery energy storage facility, such as HVAC equipment, may be located outside of a building or modular container, provided that the mechanical equipment is completely screened on all sides with a solid wall or fence that is painted or texturized to match the primary building on the premises, if one is present. (5) Battery energy storage facilities that are not located within a building shall be enclosed and screened from the public right-of-way and adjacent properties by walls or fences with a minimum height of 6 feet that incorporate finishes and architectural detailing that are consistent with any buildings on the premises or any applicable design standards. The walls or fences shall be screened by landscaping as follows: (A) Along the street frontage, the walls or fences shall be screened from the public right-of-way with plant material that includes 24-inch box evergreen canopy form trees separated by a maximum distance of 30 feet; and (B) Along the side and rear yards, the walls or fences shall be screened from adjacent properties by 10-foot wide landscape strips that include 24-inch box evergreen species separated by a maximum distance of 30 feet along the side and rear yards. For premises less than 10,000 square feet, the landscape strips may be reduced to 5-feet in width. (6) Brush Management Regulations (A) Battery energy storage facilities in High or Very High Fire Hazard Severity Zones shall meet the City’s defensible space brush management regulations and landscape standards. (i) If unable to meet the brush management regulations and landscape standards, the agent or owner shall be required to provide a technical report from a qualified engineer, specialist, laboratory, or fire safety organization acceptable to the Fire Code Official. The Fire Code Official is authorized to require design submittals to be prepared by and bear the stamp of a registered design professional, as defined in Title 24, Part 9, Chapter 2 of the California Fire Code. The technical report shall be reviewed by the Fire Code Official.

(“Battery Energy Storage Facilities” added 3-7-2023 by O-21618 N.S.; effective 5-6-2023.) (Amended 12-18-2024 by O-21905 N.S.; effective 2-6-2025.)

Ask a question about San Diego law

Corpus searches the San Diego sections it holds and shows the ones that match, with their citations. Free, no sign-in.