Sec. 66-101. - Turn-ons; unauthorized connection; resale; construction water.

(a) No water from the town water supply shall be turned on for service into any premises by any person except the duly authorized official or employee of the public works department. (b) No person shall connect any pipe, tube or other instrument with any main, service pipe, conduit or flume for conducting water belonging to the town, for any purpose without a permit or other express written authorization from the proper authorities of the town. No utility service that has been terminated by the town shall be reestablished except as provided in section 66-75. (c) Except for construction/temporary use water, water shall be turned on only in compliance with section 66-5. Connection to fire hydrants for construction/temporary use water shall be governed by the provisions of subparagraph (f) of this section. (d) No water shall be turned on for service to premises in which the plumbing does not comply with the provisions of this chapter or ordinances of the town; provided, however, that water may be turned on for construction work in unfinished buildings, subject to the provisions of this chapter. All plumbing fixtures and methods of installation shall comply with the requirements of the plumbing code, as adopted by the town. (e) No water shall be resold or distributed by the recipient thereof from the town supply to any premises other than for which application has been made and the meter installed, except in case of emergency. (f) No person shall connect any pipe, tube, hose or other instrument with any fire hydrant of the town for construction/temporary use water purposes except in compliance with this subsection. (1) The following definitions shall apply to this subsection: Construction/temporary use water shall mean water used by a person other than the town during grading, land preparation or construction on any parcel or lot in the town, for filling swimming pools in the town, or for other one time or short term uses approved by the public works director. Fire hydrant shall mean any fire hydrant owned by the town. Permittee shall mean a person who has been issued a permit to use construction/temporary use water. (2) No construction water from fire hydrants shall be used on parcels or lots of ten acres or more in size, provided however, the director of public works is authorized to issue a permit for construction water to be used on parcels or lots ten acres or more in size if he determines any of the following conditions exist: (i) if construction water from fire hydrants is not made available, an unsafe work environment will exist, (ii) an alternative non-potable water supply is not available, or (iii) it is economically infeasible to obtain an alternative non-potable water supply. In all cases, the permittee has the burden to establish that the conditions exist to justify use of construction water from fire hydrants. (3) For parcels or lots less than ten acres in size, construction water from fire hydrants may be used only with a permit issued by the town. (4) The council shall establish construction/temporary use water rates by resolution. (5) Permits to use construction/temporary use water from fire hydrants may be issued by the town upon written application made to the water section of public works. The permit shall identify the fire hydrant from which the permittee may withdraw construction/temporary use water. Construction/temporary use water used shall be as determined by a meter installed by town on the fire hydrant. All such permits shall be conditioned on the following: a. The permittee shall deposit with the town an amount determined by the water section of the public works department to cover the estimated replacement cost of the meter and related hardware. If town subsequently determines the deposit is not sufficient to cover these costs, permittee shall deposit such additional amount as town establishes for such purposes. Failure to pay such additional amount shall result in revocation of the permit. b. The permittee shall pay the cost of construction/temporary use water within 30 days of the date of an invoice from town. Failure to pay amounts due within 30 days shall result in revocation of the permit. Upon revocation or expiration of the permit, town shall refund to permittee only that portion of the deposit not required to pay all amounts owed to town for construction/temporary use water, meters and related hardware. If an amount is owed in excess of the deposit, permittee shall pay all additional amounts owed to town. No new permit for construction/temporary use water shall be issued to the permittee until all amounts owed pursuant to this section have been paid. c. The meter shall be installed, removed or relocated only by Town of Gilbert Personnel. d. The permittee shall pay all costs related to damage to or theft of the meter and related hardware. e. Construction/temporary use water used for non-construction purposes shall only be authorized for one permittee a total of 30 days in one calendar year. If such water is used for construction purposes, the term of the permit shall be as set forth in the permit.

(Code 1984, § 9-1-4; Ord. No. 1437, § I, 10-29-02; Ord. No. 1636, § I, 2-15-05; Ord. No. 2292, § I, 6-22-10; Ord. No. 2416, § I, 1-17-13)