§ 34-04 — Fees for Work Permits and Certificates of Operation

New York City Administrative Code (current through L.L. 2026/147, enacted September 12, 2026, and amendments effective through October 10, 2026) · 15 RCNY § 34-04

Corpus is an independent public-information project, not the official City of New York website. Stable reference: corpuslaw.us/code/c953c9e5-4963-483a-af7a-f59a2eb47fe2

§ 34-04 Fees for Work Permits and Certificates of Operation.

The fee for a new work permit required under § 24-121 of the Air Code, or for a new certificate of operation required under § 24-122 of the Air Code, or for a renewal of a certificate of operation, is as follows: (a) For boilers and water heaters using fuel oil grade # 2 or natural gas: Input in MMBTU/HR Fee 4.2 To Less Than 10 $345 10 To Less Than 20 $470 20 To Less Than 35 $595 35 To Less Than 50 $700 50 To Less Than 70 $830 70 To Less Than 100 $940 100 To Less Than 140 $1,440 140 Or More $1,440 plus $125 per additional 10 MMBTU/HR Or Fraction Thereof Not To Exceed $10,000. (b) For boilers and water heaters using fuel oil grade #4 or fuel oil grade #6: Input in MMBTU/HR Fee 4.2 To Less Than 7 $470 7 To Less Than 14 $595 14 To Less Than 21 $700 21 To Less Than 28 $830 28 To Less Than 35 940 35 To Less Than 42 $1,440 42 Or More $1,440 plus $125 per additional 10 MMBTU/HR Or Fraction Thereof Not To Exceed $10,000. For boiler using both fuel oil and natural gas, the fee imposed will be based on the grade of fuel oil used. (c) For equipment used in a process with an environmental rating of C: Emission in CFM Fee 2,001 thru 5,000 $250 5,001 Thru 20,000 $470 20,001 Thru 50,000 $700 50,001 Thru 100,000 $940 100,001 Or More $1,405 (d) For equipment used in a process with an environmental rating of B: Emission in CFM Fee 5,000 Or Less $280 5,001 Thru 20,000 $525 20,001 Thru 50,000 $795 50,001 Thru 100,000 $1,060 100,001 Or More $1,580 (e) For equipment used in a process with an environmental rating of A: Emission in CFM Fee 5,000 Or Less $315 5,001 Thru 20,000 $590 20,001 Thru 50,000 $875 50,001 Thru 100,000 $1,175 100,001 Or More $1,750 (f) For dry cleaning equipment, two hundred and fifty ($250) dollars per unit. (g) For cogeneration, and other fossil fuel burning equipment: Total Heat Input in MMBTU/HR Fee 4.2 to less Than 10 $345 10 To Less Than 20 $470 20 To Less Than 35 $595 35 To Less Than 50 $700 50 To Less Than 70 $830 70 To Less Than 100 $940 100 To Less Than 140 $1,440 140 Or More $1,440 plus $125 per additional 10 MMBTU/HR Or Fraction Thereof Not To Exceed $10,000. (h) For generators: Output in KW Fee 450 to less than 1,000 $345 1,000 to less than 2,000 $470 2,000 to less than 3,500 $595 3,500 to less than 5,000 $700 5,000 to less than 7,000 $830 7,000 to less than 10,000 $940 10,000 to less than 14,000 $1,440 Over 14,000 $1,440 plus $125 per additional 1,000 KW Or Fraction Thereof Not To Exceed $10,000. (i) For engines: Output in HP Fee 600 to less than 1,340 $345 1,340 to less than 2,680 $470 2,680 to less than 4,695 $595 4,695 to less than 6,705 $700 6,705 to less than 9,385 $830 9,385 to less than 13,410 $940 13,410 to less than 18,775 $1,440 Over 18,775 $1,440 plus $125 per additional 1,350 HP Or Fraction Thereof Not To Exceed $10,000. (j) For refuse burning equipment, incinerators and crematoriums: Cross Section of Chamber in SF Fee 8 Or Less $300 8.1 Through 25 $475 25.1 Through 50 $750 50.1 Through 75 $1,500 75.1 Or More $2,400 (k) The fee to amend a work permit or certificate of operation shall be sixty-five ($65) dollars. (l) The fee for an application to reinstate an expired permit to install or alter equipment or apparatus filed more than thirty days but less than one hundred eighty days after the expiration date of the permit shall be equal to fifty percent of the fee for the permit to install or alter equipment. (m) The fee for an application to reinstate an expired permit to install or alter equipment or apparatus more than one hundred eighty days after the expiration date of the permit shall be equal to the fee for a permit to install or alter equipment. (n) The fee for each field re-inspection required because of a notice of disapproval for a major deficiency shall be equal to the fee required in subdivisions (a) through (i) of this section. (o) There shall be an additional fee imposed for each operating certificate issued or renewed on the basis of a notarized affidavit supplied in response to a notice of disapproval for a minor deficiency issued after a field inspection shall be equal to fifty percent of the fee required in subdivisions (a) through (i) of this section. (p) The expiration date of a valid operating certificate may be abridged by the commissioner for the convenience of the department for good cause shown. The fee to renew the abridged operating certificate shall be reduced by one third per each full or partial year that the unabridged operating certificate would have been, as set forth in subdivisions (a) through (i) of this section. (Added City Record 3/29/2016, eff. 4/28/2016; amended City Record 8/5/2016, eff. 9/4/2016)

Ask a question about New York law

Corpus searches the New York sections it holds and shows the ones that match, with their citations. Free, no sign-in.