§ 128.0302 — Time Limits for Preparation of Environmental Documents

San Diego Municipal Code (City Clerk PDFs, pages revised through October 2026) · San Diego Municipal Code § 128.0302

Corpus is an independent public-information project, not the official City of San Diego website. Stable reference: corpuslaw.us/code/c997642c-dca3-43d4-be3a-824420d4c5b8

§128.0302 Time Limits for Preparation of Environmental Documents

(a) In accordance with CEQA, Section 21151.5, completion and certification of a Negative Declaration shall not exceed 180 calendar days from the date the application for proposed development is deemed complete. Completion and certification of an EIR shall not exceed one year from the date the application is deemed complete. (b) These time limits for document preparation and review are contingent upon the project applicant’s actions and shall be in conformance with the provisions of the Permit Streamlining Act, Government Code Section 65920, et. seq., except that time limits may be suspended as provided in the State CEQA Guidelines, Section 15109. (c) The one year time limit set forth in Section 128.0302(a) may be extended once for a period of not more than 90 days upon consent of the Planning Director and the applicant.

(Added 12-9-1997 by O-18451 N.S; amended 12-6-1999 by O-18728 N.S; effective 1-1-2000.) (Amended 3-22-2018 by O-20917 N.S.; effective 4-21-2018.)